Area # Task Pred Days Trade 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81

1 Framing, hanging & finish drywall None 22 Drywall Sub #1 22 days


2 Hard tile installation 1 10 Masonry Sub 10 days
3 Complete stone columns 1 5 Masonry Sub 5 days
4 Millwork None 18 Carpentry Sub 18 days
5 Casework 4 5 Labor Crew #3 5 days
Cafe
6 Flooring installation 5 10 Flooring Sub #1 10 days
7 Glass installation 2,3 3 Labor Crew #3 3 days
8 Painting 7 10 Labor Crew #1 10 days
9 Doors installation 6,8 6 Labor Crew #1 6 days
10 Mechanical, electrical, and plumbing 6,8 10 MEP Sub 10 days
11 Reception area None 10 Labor Crew #1 10 days
12 Hard ceiling None 15 Labor Crew #2 15 days
13 Drywall installation None 15 Drywall Sub #2 15 days
14 Painting 11 5 Labor Crew #2 5 days
15 Put in a thin concrete layer 11 6 Masonry Sub 6 days
16 Hard tile 13 5 Masonry Sub 5 days
17 Wood treatment 16 8 Labor Crew #2 8 days
Lobby
18 Flooring installation 17 25 Flooring Sub #1 25 days
19 Carpeting 16,18 9 Flooring Sub #2 9 days

n
tio
20 Public restroom 12 9 Labor Crew #2 9 days

ys ec
21 Glass installation 12 3 Labor Crew #1 3 days

da sp
22 Ceiling tile 14 5 Labor Crew #3 5 days

15 In
d
23 Doors installation 18, 19, 20, 22 10 Labor Crew #1 10 days

an
24 Mechanical, electrical, and plumbing 18, 19, 20, 22 10 MEP Sub 10 days

up
an
25 Hanging drywall None 16 Drywall Sub #2 16 days

le
26 Core drill for the rails None 2 Labor Crew #3

C
2 days

27 Rails installation 26 5 Labor Crew #3 5 days


28 Carpeting at seats 26 15 Flooring Sub #2 15 days
29 Carpeting at rails 27 5 Flooring Sub #2 5 days
30 Wood paneling, trim & stage 28 25 Carpentry Sub 25 days
31 Painting 36 20 Labor Crew #1 20 days
32 Seats at Audi 33 20 Seat Sub 20 days
33 Seats at Bowl 25 20 Seat Sub 20 days
Lecture 34 Stain floor 35 5 Labor Crew #2 5 days
Hall 35 Wood stage steps 26 5 Carpentry Sub 5 days
36 Carpeting at Bowl None 5 Flooring Sub #2 5 days
37 Doors installation 31 6 Labor Crew #3 6 days
38 Windows installation None 8 Labor Crew #3 8 days
39 Waterproofing 25 7 Labor Crew #3 7 days
40 Insulation 39 3 Labor Crew #3 3 days
41 Deck completion 40 8 Carpentry Sub 8 days
42 Stairs 41 10 Labor Crew #2 10 days
43 Aluminum rails installation 41 5 Labor Crew #2 5 days
44 Masonry on the stairs 42 5 Masonry Sub 5 days