Professional Documents
Culture Documents
4
4
4
ITEMS
NO Description UNITS Total Quantity Unit Rate Amount
A.Demolishing Work
Demolishing Exsiting EGA Roof and Wall . Work Includes Properly and safely
1
removing the existing Truss and Wall Steel Structure side runners M2 60.00 100 6,000.00
2 Demolish Column, Beam, HCB, M2 75.00 110 8,250.00
3 Demolish Existing Masonary Foundation Pad for tanker M3 8.75 150 1,312.50
3 Demolish Existing Concrete Foundation Pad M3 8.75 250 2,187.50
4 Cart Away All unnessary Demolished Material. M3 31.25 150 4,687.50
Sub Total 22,437.50
B. EARTHWORK AND EXCAVATION
2 Bulk excavation in soil formation to a depth not Exceeding 1500mm form NGL. M3 12.10 110 1,330.56
Pit excavation to reduce the NGL to a depth not exceeding 1500 mm from avg.
3
Natural ground level & 75cm offset area from foundation line. M3 4.00 150 600.00
Granular selected & imported backfill material consisting of gravel, crushed stone 7
gravel mix under foundation. Compaction shall be made in layers of 200mm with
7 roller and by sprinkling water to achieve the required proctor density, which is 8.05
(95% of the maximum dry Density). All work shall comply with ASTM D2487.
M3 380 3,058.24
Cartaway surplus excavated material to a distance not exceeding 10kms. The
8
contractor is responsible for permission from relevant authorities. M3 16.10 120 1,931.52
Hard core 250mm thick with basaltic stone or equivalent, blinded with 20mm
crushed aggregate (for only under 10 cm thick slab around cooling tower). (Quality
9
approval is required before transporting the material from quarry to the construction
site.) M3 12.50 400 5,000.00
Sub Total 11,920.32
B. CONCRETE WORK
LEAN CONCRETE
Providing, mixing, handling and pouring 50mm lean concretee under new
foundation,concrete floor/slabs using 20mm down gauge graded crushed stone as
1
coarse aggregate with a 1:3:5 ratio including screening and washing of aggregates,
mechanical mixing, lifting, placing and curing complete all as per drawings,
specifications and as directed by the Enginner-in-charge. M2 30.00 270 8,100.00
a Under foundation, masonry, ground floor slab & beam
Reinforced concrete works
Providing and laying in-situ /Ready mixed reinforced cement concrete using
Ordinary Portland Cement , sand and 20mm down size graded crushed stone
aggregates/gravel in all types of structures such as foundations, grade slab,pipe
encasement, manholes, ,including construction joint, expansion joint, contraction
joint, openings, recesses, chamfering etc, wherever required, vibrating, tamping,
curing and rendering if required to give a smooth/ even surface, etc (excluding the
2 Cost of Reinforcement and formwork) for all depths below and above Ground level
in any shape, size, position, thickness, finish and all materials and measures to
complete the work required. concrete quality Should be C-25/30,with 28 day
150x150mm cube compression strength of 30 MPA,
Use concrete admixtures like MasterRheobuild1100,Sikament NN or equivalent that
will help in rapid setting and early strength achieving of concrete.