Professional Documents
Culture Documents
For Industrial Township DMIC-Vikram Udyogpuri Industrial Area
For Industrial Township DMIC-Vikram Udyogpuri Industrial Area
For Industrial Township DMIC-Vikram Udyogpuri Industrial Area
www.abctechnolab.com mumbai@abctechnolab.com
1
BRIEF SUMMARY
2
1. INTRODUCTION
1.1.1 Project:
Create Vikram Udyogpuri sustainable and financially viable with appropriate proportioning of
Land use product mix. Create a ―Smart City‖ in which Information & Communication
Technology (ICT) and networking infrastructure is integrated with the trunk physical
infrastructure. The Government of Madhya Pradesh (GoMP) and Delhi Mumbai Industrial
Corridor Development Corporation (DMICDC) intend to facilitate development of trunk internal
and external infrastructure for Vikram Udyogpuri. This proposal has been submitted for
obtaining Environmental Clearance for establishment of Vikram Udyogpuri Industrial Area in
Narwar, Karchha, Munjakhedi, Gawdi, Piplodha Dwarkadhish, Madhopur Village, Ujjain Taluk,
Ujjain District.
3
1.3 Need of the project and its importance for the country:
The project will generate direct and indirect employment opportunities for the local people.
The plant will create additional employment during construction & operational phase.
Additionally, certain works like security will be outsourced on contract. The secondary
employment in the form of providing services to the employed manpower will also be
developed in the neighboring villages.
Raw materials can be sourced locally. Hence the cost for procurement is less.
Increase in Market & Business Establishment facilities.
The State Government also Central Govt will benefit through revenue recovery from excise
duty etc.
Import:
On Establishment of industries and start production, the import v/s indigenous production
factor can be worked out.
4
2. PROJECT DESCRIPTION
5
Figure 3.1 Location Map of Project Site:
6
Figure 3.3 Master Layout:
7
2.3 Details of alternate site:
No alternative site proposed- Land developed by Madhya Pradesh Industrial Development
corporation Ltd. (MPIDC).
8
domestic, commercial, institutional and industrial areas which are depicted in the following
Table
Floating Population :
Students 6250 20 25 0.12 0.16
9
10
2.8 Quantity of waste generation (Liquid and Solid) & its management:
The solid waste generation for the proposed city is estimated based on
CPHEEO manual for SWM and the report published by NEERI for metro cities
in India.
The basis for solid waste generation from different sectors is presented in below:
Basis of Solid Waste Generation from Different Sectors
*Biomedical waste from Hospital waste is not included in total solid waste as it has to be
handled separately by Hospital.
Solid waste can further be categorized according to their nature (qualitative) as given in
below
11
Solid Waste Categorization
12
Effluent Generation and Treatment:
The Zone wise sewage flows (average & peak) to each STP are mentioned in table below:
It is proposed that the sewage which is generated to be treated to such standards that it can be
used for flushing and gardening purposes.
From the point of view of better environment it is contemplated that Vikram udyogpuri
following a zero liquid discharge system and the entire sewage will be treated to 10mg/l (BOD
and TSS) standards.
13
3. SITE ANALYSIS
3.1 Connectivity:
3.3 Topography:
Site topography is an important aspect in any site development project. This section
focuses on the effective use of site elevation and formation levels at strategic locations for the
development of “Vikram Udyogpuri” site.
14
4. PLANNING BRIEF AND INFRASTRUCTURE FOR PROPOSED PROJECT
15
5. PROPOSED INFRASTRUCTURE
5.2.1 GENERAL
The objective of solid waste management system for the township is to manage waste
generation, storage, collection, transportation, treatment and disposal of solid waste in a
manner that is in accordance with the applicable statutory norms and the best principles of
public health, economics, engineering, aesthetics, and other environmental considerations.
16
1. Residential: Waste generation from residential colonies of the students and faculties and
other employees of the industries
2. Commercial: There would some commercial areas like shopping malls, Banks etc.
3. Institutional: Some waste would also be generated from educational institutions like schools
and colleges.
4. Biomedical waste: Some amount of biomedical waste would be generated from hospitals and
nursing homes.
5. Industrial Waste: The industrial waste would mostly be recyclables like metals, paper etc.
Hazardous waste is not envisaged.
6. Street sweeping and garden waste: Small amount of waste would be generated from street
and road sweepings and garden waste.
The solid waste generation for the proposed city is estimated based on CPHEEO manual for
SWM and the report published by NEERI for metro cities in India.
Solid waste can further be categorized according to their nature (qualitative) as given in below
table
17
Solid Waste categorization
S.N. Type of waste Quantity in ton/day
1 Total solid waste 38.3
2 Biodegradable 19.2
3 Recycle 11.5
4 Inert/ miscellaneous 7.7
Secondary Collection
Secondary collection will have contribution from all primary collection bins, street and road
sweeping and garden waste. Common bin of a large capacity say 4.5 m3 will be provided at
different points for the collection of waste.
Transportation
Waste collected in the secondary bins will be transferred to the compactors trucks which may
have capacity of 8m3. These trucks will transport the waste to the Transfer station and then to
the Treatment plant for further segregation and treatment.
Transfer Station
Two transfer stations will be provided one for zone 1 and other for zone 2 & 3 located at plot
nos. 74 and 48 respectively. Total waste of entire zone will be collected at the transfer station
and then transferred to the treatment facility. The source segregation would be adopted for
residential and institutional areas. However another screening would be carried out at the
transfer stations. A layout of transfer station is depicted in drawings available in Volume IV.
18
Treatment Plant
Total waste of entire area will be transferred to the treatment facility where it will be further
segregated. Composting, biomethanation, incineration, Refuse derived fuel and waste-to-
energy are the various available options for the treatment of biodegradable waste. Composting
would be the recommended treatment option for the bio-degradable portion of the waste as
this is the simple and feasible for the small amount of waste. The compost can also be used
within VU for gardening purpose.
Option for incineration can also be kept for the future requirement.
Total area including treatment plant may require about 4 acres land considering mechanized
composting plant as per offers available from leading companies in this sector. The area for
conventional treatment and composting (Windrow composting) plant may require about 8 -10
acres of land. Similarly, two Transfer stations would require about 1 acres of land each.
The waste treatment and composting facilities as well as Transfer stations are located with
waste water treatment facilities to optimize on green belt requirement and other ancillary
facilities. The treatment facility for biodegradable waste including transfer station for zone II
will be located at plot no. 48
Disposal
As stated above, the entire solid waste would be treated within the site and only residual waste
(from composting) may require disposal. The residual waste would be only about 5% i.e. 2- 3
tons/ day and this would be disposed to the external landfill site in arrangement with nearest
municipality.
Inert waste and debris would be used for filling low lying areas.
Solid waste management system for VU would be an integrated system for collection,
transportation, treatment, processing and final disposal.
19
5.2.5 CONCLUSION AND RECOMMENDATIONS
20
6. REHABILITATION AND RESETTLEMENT (R&R) PLAN
At present no need of rehabilitation and resettlement plan as MPIDC has acquired the necessary land.
In case some area from the private is acquired and the compensation for the land losers is made as per
the policy of the MPIDC.
Backfilling of trenches/pits will be done by selected excavated material such as soil and broken soft rock
and excess excavated material such as hard rock will be disposed of upto 5 km. Since majority of cases
hard rock will be met with, trenches will be required to be backfilled also by murrum brought from
outside.
7.1.2 Transportation
The cost estimate is based on the detailed quantities worked out for various items of work to be
executed in the project on the basis of detailed engineering design of roads and structures and
drawings and the rates for relevant items of work.
The rates of items are based on Schedule of Rates for Road works issued by Office of Engineer in Chief
P.W.D. (MP) in force from 01/02/2013 and the market rates adopted by PWD (Ujjain).The unit rates as
given in SOR are directly used for each item.
RCC culverts of required size are considered for passage of surface runoff across the main trunk road.
The costs of these culverts are based on detailed design. Similarly cost is estimated for underpass across
the main trunk road.
The cost of site grading is computed based on cut and fill required for the road works based on existing
and proposed ground levels with respect to finished road levels of main trunk road and intra sectoral
roads.
The cost estimate has been arrived at using the computed quantities and the unit rates for each item in
the Bill of Quantities.
7.1.3 Site Grading, Storm Water Drainage and Rain Water Harvesting
The cost of storm water drains (pipes/channels) are taken after referring relevant rates in SOR. Provision
has been made for connection to main storm water drains for individual plot by RCC pipe connection
and suitable brick masonry chamber.
The cost of rain water harvesting is based on deepening of existing ponds and de-silting of nalas crossing
across the main trunk road.
21
7.1.4 Water Supply and Fire Fighting
DI-K9 class pipes of required diameters are considered for water supply transmission and distribution
system, the cost of which is based on SOR. Suitable provision is made for specials/fittings for pipelines.
Various types of valves such as sluice valves, air valves, scour valves etc. are considered in the estimates.
The pipes will be provided with suitable bedding (granular, full encasement) and relevant items are
provided in the estimate.
Brick masonry chambers of required size with CI frame and cover are considered for chambers along
roads. Provision is made for water supply connection by ferrule/tee with wheel/ gate valve and brick
masonry chamber to individual plot upto their plot boundary. Similarly the cost of clear water reservoir,
pump house and elevated service reservoirs is computed based on detailed design and relevant items
consisting of civil, mechanical, electrical and instrumentation works. The cost of water treatment plant is
based on design of individual unit of civil structure, mechanical and electrical and instrumentation
equipment. Cost provision has been made for miscellaneous items such as internal roads, storm water
drains, fencing, interconnecting pipes and channels etc.
The cost of firefighting system consists of two fire stations which will have two fire tenders each,
underground tank and fire station building. The cost of fire tender and water tanker is based on market
rate whereas that for underground tank and building is based on design.
RCC NP3 class pipes of required diameters are considered for sewage collection system whereas HDPE
pipes of PE100 and PN6 class are considered for recycling system, the cost of which are based on SOR.
Suitable provision is made for specials/fittings for HDPE pipes including necessary valves.
Ancillary structures such as manholes, vent shafts are considered for sewage collection system. The
brick masonry manholes of required size will be provided on roads with heavy duty CI frame and cover
whereas in open spaces, SFRC frame and cover are considered. Provisions are made for connection to
manhole from individual plot for sewage as well as recycle water in the form of pipe (RCC/HDPE) with
manhole/chamber.
The cost of ISPS (5 nos.) and TSPS (3 nos.) is worked out based on design for civil, mechanical and
electrical works. The cost of STP (3 nos.) is based on design of individual unit of civil structure,
mechanical and electrical equipment and instrumentation. Suitable cost provision is made for internal
roads and SWD fencing, interconnecting pipes and channels etc.
The recycling system consists of RCWR and pump house and recycle water distribution system, the cost
of which is worked out based on detailed design of the system.
22
7.1.7 Power Supply
Total cost of the power supply to the project area; mainly consist of the electrical equipment required
for bringing the immediate power arrangement (construction power) & Permanent power supply
arrangement with options, as per the design & philosophy of power distribution proposed. The cost of
the electrical equipment & system are considered as per the current market rate.
Following are the main electrical equipment’s involved in the immediate power supply:
33kV Bays at Ujjain
33kV Switchgears
33kV Double circuit/ Single circuit overhead lines
33kV 4 Pole/ 2 Pole Structures with metering Following are the main electrical equipment’s
involved in the Permanent power supply:
220kV Bays at Dewas & 220kV Air Insulated Switchyard at project site
220kV Transmission lines
Power Transformers of 220/ 33kV & 33/ 11kV
33kV & 11kV Switchgears
Compact Substations
Battery, Battery charger & DCDB
Earthing system
Lighting system
33kV, 11kV & 1.1kV Cables and its terminations
Following are the main ICT equipment’s involved in the initial development of VU city:
Fiber optic cables
Fiber optic distribution frames and its accessories
Street cabinets, ducts, manholes
Access layer Switches
Core & Distribution layer Routers
CCTV Cameras, DVM database servers, DVM camera servers, SAN storage system, Display
monitors, Human Machine Interface (HMI), cabling and all other related accessories.
Access control system consisting of Card readers, break glass modules, motorized boom
barriers, Reader modules, Intelligent controllers, ACS database servers, cabling and all other
related accessories.
23
7.3 SUMMARY OF COSTS
The summary of cost estimates for VU is given below:
S.NO. Description Base cost as of 2013-14
(Rs cores)
1 Transportation (including culverts, street lighting) 98.99
24
8. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
Proposed DMIC Vikram Udyogpuri Industrial Township at Narvar, Karchha, Munjakhedi, Gawdi,
Piplodhwar, Dwarkadhish Madhupur Village, Ujjain Taluka, Ujjain District and other surrounding villages
will have very little negative impacts on the surrounding areas or on the environment.
However all necessary pollution control measures will be adopted. The Project would indeed help the
socio-economic condition of the area and it is highly recommended for the development of industrial
area. Due the proposed industrial area development at Narvar, Karchha, Munjakhedi, Gawdi,
Piplodhwar, Dwarkadhish Madhupur Village, Ujjain Taluka, Ujjain District.
There will positive impacts on the socio- economic status of the surrounding areas.
More employment opportunities will be generated
Physical infrastructure development such as improvement to roads, street lights etc. will take place.
25