Professional Documents
Culture Documents
PLC-based Load Management in Steel Rolling Mills
PLC-based Load Management in Steel Rolling Mills
net/publication/254303327
CITATIONS READS
7 3,719
1 author:
Ashok Sas
National Institute of Technology Calicut
152 PUBLICATIONS 1,701 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Improvement of Power Quality and Protection Issues for a Wind Power Based Microgrid Using Solid State Transformer
View project
All content following this page was uploaded by Ashok Sas on 06 September 2017.
ABSTRACT
Keywords: Load management actions, load flow control, steel mill, time-
of-use tariff (TOU)
INTRODUCTION
are made aware of this either by means of price signal or through load
shedding.
Electricity costs can be minimized by taking advantage of incen-
tives and favorable pricing offered by utilities in order to encourage
consumers to use energy in such a way and at suitable times so as to
enable the utility to manage load patterns. By making the best use of
these incentives, it is possible to achieve significant savings in produc-
tion costs, with no adverse effect on product quality and productivity.
The set of options available for load management in industry in-
cludes process rescheduling or load shifting, machinery interruption/
restart cycle, energy storage, captive power, and automation. The choice
of each option must be weighed against the rate system or financial
agreement in effect and the technological constraints posed by the pro-
duction process.
The industrial sector consumes about 41% of the total electrical
energy generated on a worldwide basis [2]. Since industries consume
a significant proportion of the total electrical energy generated, load
management in the industrial sector assumes an important role in peak
demand management. Load shifting, one of the simplest methods of load
management, is to reduce customer demand during the peak period by
shifting the use of appliances and equipment to partial-peak and off-
peak periods. No loads are switched off but only shifted or rescheduled;
hence, the total production is not affected [3].
Load management (LM) is a specific method of controlling the
peak load in the network in order to produce a constant demand. For
applying LM techniques to the industrial sector, a detailed modeling and
optimization of the industrial loads is needed, including the complexi-
ties and constraints of the process. Industrial load management (ILM)
activities are aimed at the economic reduction of an electric utility’s
demand during peak hours without affecting the specified production.
ILM applications have been reported for utilities using interruptible load
control schemes [4].
For iron and steel industries, electricity comprises about 30% of to-
tal production costs. A mathematical model formulation coupled with an
optimization framework for optimal process schedule of the steel plant,
for a specified tariff, minimizing the total operating cost and satisfying
production, process flow, and storage constraints has been reported[5].
A methodology for collecting end-use demand data for devis-
ing demand-side management programs in the commercial sector has
40 Energy Engineering Vol. 107, No. 4 2010
MATHEMATICAL MODEL
where Am, is the rated capacity of the equipment in kW, Umjk, is the utili-
zation of the mth equipment in the interval k when it is processing the jth
product, and ηmjk is the efficiency of the equipment m in the interval k.
The energy consumed in kWh by the equipment m in the kth in-
terval when processing the product j is
N
E mjk = / W mjk * I mjk * t
k=1 (3)
N M J
e Min / / / 6 E mjk * C k @ * H + C d * MD o
k=1 m=1 j=1
(4)
Where,
Ck = Cost of energy (charge per kWh) for the interval
H = Number of working days in the month;
Cd = MD charge (charge/kVA/month),
M = Particular item of equipment;
J = Total number of products
N
/ Pmjk * I mjk ≥ Q j, 6 m = M
k=1 (5)
J
/ Q j ≥ QT
j=1 (6)
J N
/ / R mjk * I mjk ≤ R T, 6m = 1
j=1 k=1 (7)
where Rmjk is the quantity of raw material required for the mth equip-
ment for the product j in the kth interval, and RT is the total raw-material
available for the day.
Maximum demand constraint to avoid penalty from a utility when
processing a product in any interval is ensured by
M
/ S mjk * I mjk ≤ MD k
m=1 8)
where Smjk is the demand due to mth machine when processing jth
product in kth interval, and MDk, is maximum demand imposed by the
utility to industry.
Until one product is completed, the same machine should not be
allocated to any other product in a particular interval. In order to prevent
allocation clashes, the following constraint is included.
J
/ I mjk = 1
j=1 (9)
ALGORITHM
CASE STUDY
Plant Description
The plant [13] has an installed capacity of producing 6000 MT of
44 Energy Engineering Vol. 107, No. 4 2010
Process Flow
Plant loads have the
nature of continuous process.
A process flow diagram of the
plant operation is shown in
Figure 2.
rate specified is generalized for all, although there are actually differ-
ent production rates for different products. Specifications of the major
equipment are shown in Table 1.
46 Energy Engineering Vol. 107, No. 4 2010
Production Requirement
For the case study, the production requirement for an average day
is about 180MT, consisting of all products (presently producing one
product daily), and the total monthly production is about 5000 MT,
including all the products. Plant monthly production of each product is
listed in Table 2 for typical monthly data.
After conducting the load management study, it is observed that
instead of producing one product for an entire day, industry can produce
many products on the same day, with the less energy-consuming prod-
ucts being processed in the peak hours such that the monthly electricity
bill is reduced.
It is observed that production can be scheduled in the following
manner for a typical month.
47
Presently the plant is running under two shifts, due to utility re-
strictions. For the high tension industrial consumers, the utility (Kerala
State Electricity Board-KSEB) [14] follows a differential pricing system
for both energy and maximum demand, as given in Table 4. Tariff 1 is
the prevailing tariff for the industry.
The utility has already included the furnace loads in a power- in-
tensive group and will charge as per the power-intensive tariff (Tariff
2) in the future.
48 Energy Engineering Vol. 107, No. 4 2010
under the prevailing tariff (Tariff 1), the load rescheduling or production
rescheduling will result in an annual saving of Rs.9.92 lacks (2.65 %) in
the electricity cost. The response to load scheduling operation under the
power-intensive tariff (Tariff 2) is more encouraging. Monthly electricity
cost gets reduced from Rs.38.94 lacks to Rs.37.01 lacks. It results in an
annual saving of Rs.23.16 lacks (5.21%).
After scheduling, the optimal response load curve is compared with the
existing 8mm load curve, shown in Figure 3.
Figure 3. Comparison
of load curve before
and after scheduling
with 8mm load
50 Energy Engineering Vol. 107, No. 4 2010
APPLICATIONS
CONCLUSION
ACKNOWLEDGEMENTS
The authors would like to thank M/s Peekay Rolling Mills, Calicut,
for providing the plant data.
References
[1] Ministry of Power, Government of India, Feb-2008, AnnualRep.[Online].
Available:http://www.powermin.nic.in.
[2] C.A. Babu and S. Ashok “Peak Load Management in Electrolytic Process indus-
tries” IEEE Transactions on Power Syst. vol. 23, no. 2, 399-405, May 2008.
[3] Ashok, S and R. Banerjee,” Industrial Load Management,” Int. Journal on Applied
Energy, Vol. 66 (2),2000, pp105-111.
[4] C.S. Chen and J.T. Leu, “Interruptible load control for Taiwan power company,”
IEEE Trans. Power Syst., vol. 5, no. 2, pp. 460–465, May 1990.
[5] S. Ashok “Peak-load management in steel plants” Int. Journal on Applied Energy,
Vol.83, 2006 pp413–424.
[6] U. Atikol, “A demand-side planning approach for the commercial sector of devel-
oping countries,” Energy, vol. 29, pp. 257–266, Feb. 2004.
[7] D. Mignon and J. Hermia, “Peak utility load reduction in batch processes operated
periodically and under uncertainty,” Comput. Chem. Eng., vol. 20, pp. 249–263, Mar.
1996.
[8] Z. Iou, R. Kumar, J. Sottle, and J.C. Yingling, “An MILP formulation for load side
demand control,” Elect. Mach. Power Syst., vol. 26, pp. 935–949, 1998.
[9] T.-Y. Wu, S.-S. Shieh, S.-S. Jang, and C.C.L. Liu, “Optimal energy management
53
————————————————————————————————
ABOUT THE AUTHOR
S. Ashok received M.Tech and Ph.D. degrees from the Indian In-
stitute of Technology (IIT) Delhi, New Delhi, India, and the IIT Bombay,
Mumbai, India, respectively. His research interests are peak demand
management, energy modeling, captive power, power system protection,
and hybrid energy systems. Dr. Ashok is a senior member of the IEEE
power engineering society.
He is an assistant professor at NIT Calicut.
Email: ashoks@nitc.ac.in