Contract No: 4400005948 Contractor: NCC

AVR (ZIV) FAINAL SETTING TEST REPORT (T/T2 Parallel) Client: National Grid SA

DIE 4B 115/13.8kV SS Sheet : Page 1 of 1


Panel No :RTCC.1 / RTCC.2 CONTROL ROOM

Circulating Current Test:

VComp (%) = VCON (%) + KR (%). (Icirc-sec / 0.1 In)

Circulating Current for the case T1 and T2 in parallel condition:

Kr=4.4% CTR:2803/1 VTR:120


Voltage Input: VRY Current Input: IY Correction angle:210
BW=2.0
I circulating =I1Sinⱷ1-I2sinⱷ2
=1*sin(246.5-240)-1*sin(240-240)
=0.113=2803*0.113= +141.8A(T1)
= -141.8A(T2)
T2 P
Sl. T1 L T2-Vcomp
PARALLE T1-Icir T2- Icir T1-Vcomp (%)
No LOCAL (%)
L

1 1 242.9º 1 240º 140 -141 102.19 97.79

2 1 240º 1 240º 6.7 -7.3 100.09 99.70

3 1 240º 1 242.9º -145.0 143.1 97.75 102.27

4 1 242.9º 1 242.9º 2.3 -3.3 100.05 99.75

5 1 242.9º 1 62.9º 326.1 -322.9 105.11 94.93

6 1 62.9º 1 242.9º -328.0 327.1 94.85 105.13

Test Equipment:
1-Freja 300
S.NO:1302708
CAL.EXPIRY:26.9.2017
2-Multimeter FLUKE
S.NO:30850238
CAL.EXPIRY:17.11.2017

TESTING ENGINEER CSD- Engineer


Signature: ________________ Signature: ________________
Name : VINODE KUMAR(XER-062) Name : ZULQARNAIN MUSHTAQ