Bajaj Institute of Technology, Wardha

Internship report submitted to


Dr. Babasaheb Ambedkar Technological University, Maharashtra
in partial fulfilment of the requirements for the award of
the degree

Bachelor of Technology
In
_______________ Engineering

By

Mr. Pravin .R. Bhagwat Prof. Arpit Sharma


Chairman Internal Supervisor
Shiv Sai Developers Ltd. Civil Engineering Department

Department of __________________ Engineering


Bajaj Institute of Technology
Wardha-442 001 (India)
2020 – 21

BAJAJ INSTITUTE OF TECHNOLOGY, WARDHA


DEPARTMENT OF ____________ ENGINEERING

CERTIFICAT

II
Bajaj Institute of Technology, Wardha
DECLARATION
I, the undersigned declare that this report is personally prepared and
compiled by me and that the contents within this report have not been
duplicated or published anywhere or submitted to any other university
for any degree/diploma program by student or any other person. I
have personally compiled it based on the training i had with Shiv Sai
Developers Ltd.

Project title: - Internship Report of Site Engineer at Shiv Sai


Developers Ltd.

Location: - Carried Out at Shiv Sai Deveolpers Ltd, Omkar Nagar,


Nagpur.

Session: - 2021-22

Name: -

Signatures: -

Date: -

Place: - Wardha

II
Bajaj Institute of Technology, Wardha
ACKNOWLEDGEMENT

I would like to express our sincere gratitude to Dr. N.M Kanhe,


Principal, Bajaj Institute of Technology and Dr. S. M. Mahajan, Head,
Department of Civil Engineering, Bajaj Institute of Technology for
having allowed us to work on this project.

I feel very much thankful to our internal guide Prof. Arpit Sharma,
Internal Supervisor, Department of Civil Engineering, Bajaj Institute
of Technology, Wardha for his constant and valuable support, advice,
encouragement and belief in our work.

Special thanks to Mr. Pravin.R.Bhagwat (Shiv Sai Developers Ltd.)


for guiding and training us.

Last but not the least, I would like to thank our family and friends
who stood by us and provided us with valuable guidance and
encouragement to make this endeavor a success.

Name of Student :-

PRN No. :-

Date : -

Place : - Wardha

Signature

III
Bajaj Institute of Technology, Wardha
TABLE OF CONTENTS

CHAPTER TITLE PAGE


NO. NO.
Declaration II

Acknowledgement III

1. Introduction V

2. Role as a Site Engineer VI

3. Site Specification VII

4. Site Location VIII

5. Supervision Work and On-Site IX


Interaction
6. Actual Site Images X

7. Conclusion XII

IV
Bajaj Institute of Technology, Wardha
1.Introduction

About Shiv Sai Developers

Shiv Sai Developers a name that stands for relationship


beyond Structures. Our focus is relationship & the
relationship comes in to being with the complete involvement
with planning, dedication & Sacrifices .

We are the people who convert dreams into reality. Our


projects speaks about us. Honesty & Commitment are our
ornaments. Indeed we do business, but the business is coined
with ethics & values, you can bank upon us. Join us to form a
permanent relationship forever.

V
Bajaj Institute of Technology, Wardha
2.Role as On-Site Engineer

I have been assigned as on site engineer and supervisor at


the aforementioned projects. The first task assigned was to
read and interpret the drawings at the start and understand the
basic terms.

As site engineer, our daily task included site


management, estimating the quantities required of various
materials. This included bar bending schedule and a detailed
report of the material being consumed and available at the
site. Managing, supervising labour and foreman along with
monitoring the work that the work is being carried out as
mentioned in the drawing.

In the underground sump, we also had the opportunity to


understand and how to check the steel work. This included
checking the diameters of steel assigned in the drawing,
numbers and spacing of bars, and check the appropriate
covers as mentioned in the notes of drawing.

VI
Bajaj Institute of Technology, Wardha
3.Site Specification

STRUCTURE :- R.C.C. frame structure.

WALLS :- 150 mm th. External & 115mm th. Internal brick wall.

PLASTER :- External & Internal side fanty finish plaster.

PAINTING :- Water proof paint to external wall. All rooms with


Putty Finish oil bound distemper.

FLOORING :- Vitrified Tiles (2’X4’) in all rooms.

TOILET :- 7 ft. height tiles.

DOOR :- Front door with teak wood panel & other of Flush doors.

WINDOW :- Powder coated Aluminum window with M.S grill.

KITCHEN :- Modular Kitchen with steel sink. Water filter &


Kitchen chimney.

WATER SUPPLY :- Through corporation & Well/Borewell.

ELECTRIC FIXTURES :- Concealed wiring 4 ½ points with quality


switch in all rooms.

PLUMBING :- All fitting will be Concealed with proper taps over it.

POP :- POP artwork for all rooms.

PARKING :- Spacious parking.

VII
Bajaj Institute of Technology, Wardha
4.Site Location

The site location are as follows :

VIII
Bajaj Institute of Technology, Wardha
5.Supervision Work and On-Site Interaction

The toughest job was to carry out day-to-day


management of the site, including supervising and monitoring
the site labour force. It was necessary to plan the work and
efficiently organize the plant and site facilities to meet agreed
deadlines. Daily logs of materials consumed and stored, daily
records of labours, meeting the requirements of labour and
equipment’s, interacting with the department engineers were
the tasks that were required to be fulfilled.

Due to the internship, I had a chance to interact with


Senior Site Engineers (SSE) and have a grasp of their
knowledge and learn from their expertise. Each day new
observations were pointed out by him to increase the
efficiency of the work and the same helped me to understand
IX
Bajaj Institute of Technology, Wardha
various concepts and cleared my doubts when and where
required.

X
Bajaj Institute of Technology, Wardha
6.Actual Site Images

As a undergraduate trainee was offered an internship as site


engineer. For this I used to report at the site sharp 10am in the
morning. Their first of all attendance used to be taken. After
this, labours used to start with their work and I was given
charge of handlling daily input of raw materials it's usage on
site, required materials and other minimal works

XI
Bajaj Institute of Technology, Wardha
XII
Bajaj Institute of Technology, Wardha
Conclusion

As an undergraduate, this was an excellent opportunity


for us to get the ground level experience and experience the
things that were learned conceptually. The biggest learning
was to understand and observe the management practices at a
construction site. Each day new problems would arise,
especially while excavations, and since at our construction the
excavation was up to 8 m, daily soil would slide and extensive
measures for dewatering was necessary to ensure work is
carried out smoothly. Working with machines is easy
overtime, but not with people. Interacting with the field
workers and ensuring their safety was the foremost task for
us. It’s a great engineering challenge to ensure that the
drawing is implemented on the site without any hazard.
Various times, things designed cannot be implemented in site
due to numerous reasons, so making necessary amendments,
XIII
Bajaj Institute of Technology, Wardha
working with labours, managing daily site requirements,
interacting with the department officers, interpreting
drawings, providing quality assurance and service and
maintaining the organization integrity are all part of the
construction and each of this is needed to be carried out daily,
time and again to ensure the said project is done on the
scheduled time. It has been a great learning experience and
the same has ensured me to face the challenge with shear
confidence.

XIV
Bajaj Institute of Technology, Wardha

You might also like