Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Comments / Observations on the BOQ and Alternative suggestions

1. LVUPs

Observations / Comments Alternative suggestions


• Corbel quantities for supporting • Top slab & side wall can be
Approach slab need to be included. considered as 600mm and bottom
• Kindly modify the wearing coat slab as 650mm with 100Kg/Cum
thickness considered in the BOQ. It Indices. If this option works out to
shall be corrected to 26.2m instead be economic, this can be adopted.
of 25.2m.
• In approach slab quantities the
length considered as 32m. Kindly
deduct the crash barrier thickness
in that as the approach slab will be
provided only between the crash
barriers.
• Since RE wall is considered in all
LVUP locations, back filling behind
box can be removed.
• Kindly ensure Geotechnical
investigation quantities are
considered.
• All the existing CVUPs / PUPs are
upgraded into LVUP by
reconstructing at same location.
Hence Dismantling quantities for all
the 8 existing CUPs / PUPs shall be
included.

2. MNB

Observations / Comments Alternative suggestions


• The overall structure width of MNB • Abutment stem thickness shall be
in Main carriageway is mentioned modified to 1.2m for all MNBs.
as 16m in Schedule-B. Kindly • RCC girder depth shall be
modify. considered as 1.2m for all the
• The width Abutment foundation in MNBs.
LHS Service road shall be modified • For skew MNB, the number girders
to 8.3m in lines with the other can be increased to 6 nos instead of
structures. 5. Accordingly pedestals & Bearings
• Retaining wall length considered shall be increased.
beyond Abutment returns shall be • For open foundation, the steel
corrected. Length of retaining wall indices shall be considered as
= ((FRL-GL) x 1.5)-Abutment return 80Kg/Cum
length. • For RCC girder the indices shall e
• Kindly ensure the median width is 220Kg/Cum.
as per TCS. • For RCC Deck slab, the steel indices
• In approach slab quantities the shall be considered as 150Kg/Cum
width considered as 14m. Kindly
deduct the crash barrier thickness
at the end from the overall deck
width & consider the exact width.
• Deck slab & Diaphragm HYSD steel
quantity is not considered.
• Kindly ensure Geotechnical
investigation quantities are
considered.

3. ROB

Observations / Comments Alternative suggestions


• The overall structure width of ROB • Abutment stem size shall be
in Main carriageway is mentioned modified to 5.0m x 1.0mm for all
as 16m and for Service road ROBs.
Bridges 12.5m in Schedule-B. • Kindly ensure Structural steel
Kindly modify. quantity is based on RDSO
• In approach slab quantities the drawings for 12.5m deck width &
width considered shall be 16m deck width.
corrected. Kindly deduct the crash • Modular type expansion joint shall
barrier thickness at the end from be considered as the span is 50m.
the overall deck width & consider • For open foundation, the steel
the exact width. indices shall be considered as
• The RCC deck slab width shall be as 80Kg/Cum
per width mentioned in Schedule-B. • Repair & rehabilitation quantity for
• Kindly ensure Geotechnical existing ROB need to considered.
investigation quantities are • For RCC Deck slab, the steel indices
considered. shall be considered as 150Kg/Cum.

You might also like