Professional Documents
Culture Documents
Module 5 Lecture Slides
Module 5 Lecture Slides
Module 5 Lecture Slides
Overview
• LCOE = the average revenue per unit of electricity generated that would be required to recover
the costs of building and operating a generating plant.
• For technologies with no fuel costs and relatively small variable O&M costs, such as solar and
wind electric generating technologies, LCOE changes nearly in proportion to the estimated
capital cost of the technology.
Levelized Cost of Electricity for Generation Resources (2023 in $/MWh)
Wind versus CCGT—Global Markets
*The Evolving Scenario considers the impact of continuing the historical trend of increasing global action on climate change
throughout the projection period.
Source: Canada Energy Regulator Energy Futures: Canada's Energy Future 2020 Classification: Pr
Wind and Solar Capital Costs : Evolving scenario to 2050
70
60
50
40
30
20
10
1400
1200
1000
800
600
400
200
0
2015 2020 2025 2030 2035 2040 2045 2050 2055
Source:based on IRENA, 2019c and future projections based on IRENA’s forthcoming report: Solar and wind cost reduction potential to 2030 in the G20 countries (IRENA, n.d.).
Component % Share of Total Cost
Wind Farm Capital Costs Turbine (Tower, Nacelle, Rotors) 68 - 84
Grid Connection 2 - 10
Foundation (Concrete pour, mounting, 1-9
guy wires)
Electric Installation 1-9
Land Acquisition or Lease 1-5
Financial Costs 1-5
Road Construction 1-5
Source: European Wind Energy Association. Economics of Wind Energy, 2009
Classification: Protected A External Consulting 1
Wind Operation and
Maintenance Costs
• Typically constitute 10-15 % of the LCOE in the first few years of operation.
• Typically constitute 20-35 % of the LCOE in the last few years of operation.
• O&M costs are related to a limited number of cost components, including:
• Insurance
• Regular maintenance
• Repair
• Spare parts
• Administration
• Blade erosion and repair remain a huge concern for offshore wind, causing
an estimated 5,000 days cumulative downtime globally and resulting in more
than $80 million (CAD) of direct repair costs and lost revenue.
Source: Wood Mackenzie. Offshore Wind Operations and Maintenance Trends (2019)
This Photo by Unknown Author is licensed under CC BY-S
Why is the Levelized Cost of
Energy (LCOE) Important?
• The LCOE will determine if a project will break even or be profitable. If not,
then the firm will not go ahead with building the power-generating asset
and will look for an alternative. Using the LCOE to assess a project is one of
the first fundamental steps taken in analyzing projects of this nature.
Classification: Protected A
How to Calculate the
LCOE?
The LCOE can be calculated by first taking the net present value of the total cost of
building and operating the power generating asset. This number is then divided by the
total electricity generation over its lifetime.
Total Costs include:
• The initial cost of investment (I)
• Maintenance and operations expenditures (M)
• Fuel expenditures (F) (not applicable for renewables)
Classification: Protected A
Renewable Project Financing
• They are either financed from companies
balance sheet or through traditional financing
routes
• Off-take agreements via Power Purchase Agreements
(PPA)
• Virtual Power Purchase Agreements (VPPA)
• Merchant financing
Off-take Agreements: PPA and VPPA
Typical AB Merit Order Curve: Pool Price determination
Classification: Protected A