Summary of Cost and Major Works
Summary of Cost and Major Works
Major works
Road 4.45km Road 2.9km Road 6.65km
Covered 8.90km Covered 5.8km Covered 13.3km
Lined Lined Lined
drain drain drain
Culverts 2Nos -2.5m x 2.5m Culverts 1No.- 3/3.0mx3.5m Culverts 2Nos – 3.0m x 3.5m
1No. – 3.0mx3.5m 1No.-2.5m x 2.5m 2Nos – 3/3.0m x 3.5m
1No.- 2/3.0m x 3.5m 2Nos – 2/3.0m x 3.5m
1No.-3.0mx3.5m
(Total = 6Nos) (Total = 2Nos) (Total = 6Nos)
Bridges 1No. 15m Span bridge Bridges 2Nos – 2span / 15m Lined 4m x 2.5m = 500m
span bridge = 30m Channel 2.5m x 1.5m = 200m