Distribution : Controlled X Uncontrolled Available on computer X

Document status : TO :

F.I ( Information )

F.C ( Comments ) PT. PLN (PERSERO)


F.E ( Execution )

F.A X ( Application )

Title : INTERTRIPPING TEST


OHL FEEDER TANJUNG MORAWA-1

Type : FIELD TEST REPORT

Contract :
PEKERJAAN PENGADAAN DAN PEMASANGAN
GITET 275/150kV SUMUT 3 DELI SERDANG
SUMATERA UTARA

0132.PJ/041/DIR/2014 GITET 275/150kV GALANG


Contract specific number Name

by
on
by
on
by
B
on
A by Nopi Rianto Nosarimba R Adrian I Costumize for GITET 275/150kV SUMUT 3 Project 6
on 18.03.2018 18.03.2018 18.03.2018
Ind Rev Prepared Checked Approved Modification Sheets

PT. GRID SOLUTIONS INDONESIA


FA SECTION

Place of issue File number

This document is the property of PT GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 2

Rev. B

SUMMARY SHEET REVISION

1 LIST OF EQUIPMENT USED 2 B

2 SIGNALING CHANNEL CHECK 3 B

3 INTERTRIPPING TEST FROM DISTANCE RELAY 4 B

1 - LIST OF TEST EQUIPMENT USED

Identification Test corresponding to paragr.


Designation
Number 3 4 5

This document is the property of PT. GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 3
Rev. B

3. SIGNALING CHANNEL DISTANCE PROTECTION RELAY

System 1

1. Action to simulate signal send :


Result : OK

2. Action to simulate signal receive :


Result : OK

System 2

1. Action to simulate signal send :


Result : OK

2. Action to simulate signal receive :


Result : OK

This document is the property of PT. GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 4
Rev. B

4. INTERTRIPPING TEST FROM DISTANCE PROTECTION RELAY

GITET GALANG 275/150kV GI TANJUNG MORAWA 150kV


OHL Feeder TANJUNG MORAWA-1 OHL GALANG-1

GITET GALANG 1 1 GI TJ. MORAWA


2 2

Fault Type GITET GALANG 275/150kV GI TJ. MORAWA 150kV


No TJ
GALANG MORAW Relay Panel CB HMI Relay Panel CB HMI
A
Start Phase A F21 Trip Distance Ph A

Zone 1 Zone 2 Trip Phase A Reclose F21 Dist. Trip Sending PLN UPT Medan
A-N A-N Distance Trip Z1 (1P) F21 Autoreclose 1 Pole Scope
F21 Send F21 AR In Proggress
Start Phase B F21 Trip Distance Ph B

Zone 1 Zone 2 Trip Phase B Reclose F21 Dist. Trip Sending PLN UPT Medan
1
B-N B-N Distance Trip Z1 (1P) F21 Autoreclose 1 Pole Scope
F21 Send F21 AR In Proggress
Start Phase C F21 Trip Distance Ph C

Zone 1 Zone 2 Trip Phase C Reclose F21 Dist. Trip Sending PLN UPT Medan
C-N B-N Distance Trip Z1 (1P) F21 Autoreclose 1 Pole Scope
F21 Send F21 AR In Proggress
Start Phase AB F21 Trip Distance Ph AB
Zone 1 Zone 2 Trip Phase AB Reclose F21 Dist. Trip Sending PLN UPT Medan
A-B A-B (3P) Scope
Distance Trip Z1 F21 Autoreclose 3 Pole
F21 Send F21 AR In Proggress
Start Phase BC F21 Trip Distance Ph BC
Zone 1 Zone 2 Trip Phase BC F21 Dist. Trip Sending
Reclose PLN UPT Medan
2 B-C B-C (3P) Scope
Distance Trip Z1 F21 Autoreclose 3 Pole
F21 Send F21 AR In Proggress
Start Phase AC F21 Trip Distance Ph AC

Zone 1 Zone 2 Trip Phase AC Reclose F21 Dist. Trip Sending PLN UPT Medan
A-C A-C Distance Trip Z1 (3P) F21 Autoreclose 3 Pole Scope
F21 Send F21 AR In Proggress
Start Phase A-B F21 Trip Distance Ph AB
With Zone 1 Zone 2 Trip Phase A-B F21 Dist. Trip Zone 1 PLN UPT Medan
out A-B A-B Trip
Scope
Distance Trip Z1 F21 AR Lockout
Syn
AR Lockout

This document is the property of PT. GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 5
Rev. B

GITET GALANG 275/150kV GI TANJUNG MORAWA 150kV


OHL Feeder TANJUNG MORAWA-1 OHL GALANG-1
Scheme : Permissive Underreach

GITET GALANG 1 1 GI TJ. MORAWA


2 2

Fault Type GITET GALANG 275/150kV GI TJ. MORAWA 150kV


No TJ
Galang Relay Panel CB HMI Relay Panel CB HMI
Morawa
Start Phase A F21 Trip Distance Ph A

Zone 2 Zone 1 Trip Phase A Reclose F21 Dist. Trip Sending PLN UPT Medan
A-N A-N Aided F21 Trip (1P) F21 Autoreclose 1 Pole Scope
F21 Received F21 AR In Proggress
Start Phase B F21 Trip Distance Ph B

Zone 2 Zone 1 Trip Phase B Reclose F21 Dist. Trip Sending PLN UPT Medan
3
B-N B-N Aided F21 Trip (1P) F21 Autoreclose 1 Pole Scope
F21 Received F21 AR In Proggress
Start Phase C F21 Trip Distance Ph C

Zone 2 Zone 1 Trip Phase C Reclose F21 Dist. Trip Sending PLN UPT Medan
B-N C-N Aided F21 Trip (1P) F21 Autoreclose 1 Pole Scope
F21 Received F21 AR In Proggress
Start Phase AB F21 Trip Distance Ph AB

Zone 2 Zone 1 Trip Phase AB Reclose F21 Dist. Trip Sending PLN UPT Medan
A-B A-B Aided F21 Trip (3P) F21 Autoreclose 3 Pole Scope
F21 Received F21 AR In Proggress
Start Phase BC F21 Trip Distance Ph BC

Zone 2 Zone 1 Trip Phase BC Reclose F21 Dist. Trip Sending PLN UPT Medan
4
B-C B-C Aided F21 Trip (3P) F21 Autoreclose 3 Pole Scope
F21 Received F21 AR In Proggress
Start Phase CA F21 Trip Distance Ph AC

Zone 2 Zone 1 Trip Phase CA Reclose F21 Dist. Trip Sending PLN UPT Medan
A-C A-C Aided F21 Trip (3P) F21 Autoreclose 3 Pole Scope
F21 Received F21 AR In Proggress
Start Phase A-C F21 Trip Distance Ph AC
With
Zone 2 Zone 1 Trip Phase A-C F21 Dist. Trip Zone 2 PLN UPT Medan
out Trip
A-C A-C Distance Trip Z2 F21 AR Lockout Scope
Syn
AR Lockout

This document is the property of PT. GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 6###
Rev. B

GITET GALANG 275/150kV GI TANJUNG MORAWA 150kV


OHL Feeder TANJUNG MORAWA-1 OHL GALANG-1
Scheme : Programmable

GITET GALANG 1 1 GI TJ. MORAWA


2 2

Fault Type GITET GALANG 275/150kV GI TJ. MORAWA 150kV


No
Local Remote Relay Panel CB HMI Relay Panel CB HMI

Aided 2 F21 DEF Send


DEF DEF AR 1P F21 AR 1P
Reclose PLN UPT Medan
Forward Forward (1P) Scope
Aided DEF Trip Aided Trip
(Sent) (Sent)
AR IN PROG

Tested by Witnessed by Approved by


PT. Grid Solutions PT. PLN (Persero)
PT. ENDIRA PT. PLN PUSERTIF
Indonesia UPP MEDAN
This document is the property of PT. GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
B

ved by
PUSERTIF