Pt. PLN (Persero) : Intertripping Test
Pt. PLN (Persero) : Intertripping Test
Pt. PLN (Persero) : Intertripping Test
Document status : TO :
F.I ( Information )
F.A X ( Application )
Contract :
PEKERJAAN PENGADAAN DAN PEMASANGAN
GITET 275/150kV SUMUT 3 DELI SERDANG
SUMATERA UTARA
by
on
by
on
by
B
on
A by Nopi Rianto Nosarimba R Adrian I Costumize for GITET 275/150kV SUMUT 3 Project 6
on 18.03.2018 18.03.2018 18.03.2018
Ind Rev Prepared Checked Approved Modification Sheets
This document is the property of PT GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 2
Rev. B
This document is the property of PT. GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 3
Rev. B
System 1
System 2
This document is the property of PT. GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 4
Rev. B
Zone 1 Zone 2 Trip Phase A Reclose F21 Dist. Trip Sending PLN UPT Medan
A-N A-N Distance Trip Z1 (1P) F21 Autoreclose 1 Pole Scope
F21 Send F21 AR In Proggress
Start Phase B F21 Trip Distance Ph B
Zone 1 Zone 2 Trip Phase B Reclose F21 Dist. Trip Sending PLN UPT Medan
1
B-N B-N Distance Trip Z1 (1P) F21 Autoreclose 1 Pole Scope
F21 Send F21 AR In Proggress
Start Phase C F21 Trip Distance Ph C
Zone 1 Zone 2 Trip Phase C Reclose F21 Dist. Trip Sending PLN UPT Medan
C-N B-N Distance Trip Z1 (1P) F21 Autoreclose 1 Pole Scope
F21 Send F21 AR In Proggress
Start Phase AB F21 Trip Distance Ph AB
Zone 1 Zone 2 Trip Phase AB Reclose F21 Dist. Trip Sending PLN UPT Medan
A-B A-B (3P) Scope
Distance Trip Z1 F21 Autoreclose 3 Pole
F21 Send F21 AR In Proggress
Start Phase BC F21 Trip Distance Ph BC
Zone 1 Zone 2 Trip Phase BC F21 Dist. Trip Sending
Reclose PLN UPT Medan
2 B-C B-C (3P) Scope
Distance Trip Z1 F21 Autoreclose 3 Pole
F21 Send F21 AR In Proggress
Start Phase AC F21 Trip Distance Ph AC
Zone 1 Zone 2 Trip Phase AC Reclose F21 Dist. Trip Sending PLN UPT Medan
A-C A-C Distance Trip Z1 (3P) F21 Autoreclose 3 Pole Scope
F21 Send F21 AR In Proggress
Start Phase A-B F21 Trip Distance Ph AB
With Zone 1 Zone 2 Trip Phase A-B F21 Dist. Trip Zone 1 PLN UPT Medan
out A-B A-B Trip
Scope
Distance Trip Z1 F21 AR Lockout
Syn
AR Lockout
This document is the property of PT. GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 5
Rev. B
Zone 2 Zone 1 Trip Phase A Reclose F21 Dist. Trip Sending PLN UPT Medan
A-N A-N Aided F21 Trip (1P) F21 Autoreclose 1 Pole Scope
F21 Received F21 AR In Proggress
Start Phase B F21 Trip Distance Ph B
Zone 2 Zone 1 Trip Phase B Reclose F21 Dist. Trip Sending PLN UPT Medan
3
B-N B-N Aided F21 Trip (1P) F21 Autoreclose 1 Pole Scope
F21 Received F21 AR In Proggress
Start Phase C F21 Trip Distance Ph C
Zone 2 Zone 1 Trip Phase C Reclose F21 Dist. Trip Sending PLN UPT Medan
B-N C-N Aided F21 Trip (1P) F21 Autoreclose 1 Pole Scope
F21 Received F21 AR In Proggress
Start Phase AB F21 Trip Distance Ph AB
Zone 2 Zone 1 Trip Phase AB Reclose F21 Dist. Trip Sending PLN UPT Medan
A-B A-B Aided F21 Trip (3P) F21 Autoreclose 3 Pole Scope
F21 Received F21 AR In Proggress
Start Phase BC F21 Trip Distance Ph BC
Zone 2 Zone 1 Trip Phase BC Reclose F21 Dist. Trip Sending PLN UPT Medan
4
B-C B-C Aided F21 Trip (3P) F21 Autoreclose 3 Pole Scope
F21 Received F21 AR In Proggress
Start Phase CA F21 Trip Distance Ph AC
Zone 2 Zone 1 Trip Phase CA Reclose F21 Dist. Trip Sending PLN UPT Medan
A-C A-C Aided F21 Trip (3P) F21 Autoreclose 3 Pole Scope
F21 Received F21 AR In Proggress
Start Phase A-C F21 Trip Distance Ph AC
With
Zone 2 Zone 1 Trip Phase A-C F21 Dist. Trip Zone 2 PLN UPT Medan
out Trip
A-C A-C Distance Trip Z2 F21 AR Lockout Scope
Syn
AR Lockout
This document is the property of PT. GSI and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. GRID SOLUTION INDONESIA INTERTRIPPING TEST Ref.
FA Section OHL FEEDER PROTECTION Chapt.
TANJUNG MORAWA-1 Sheet : 6###
Rev. B
ved by