Saudi Aramco 2617-ENG (11/2010) 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 ##

DRAFTING OFFICE PERIOD ENDING DRAFTING SCHED. END OF LAST PERIOD PROJECT ENG. PLANT NO. BUDGET ITEM WORK ORDER NO. EWO NO. JOB ORDER NO.
PROGRESS
DRAWING START COMPL TO END OF THIS PERIOD SAPMT

CONTROL JACOBS ZATE 14-Sep-21 12/1/2019 12/30/2020


DRAWING IS CONSIDERED 65% COMPLETE
WHEN READY FOR CHECKING
DESIGN ENG. K04 103-262 10-00844-0001
JZ PM

STARTING COMPLETION TRANSMITTED


DRAWING SHEET REV. PERCENT COMPLETE HOURS REVISION
DRAWING TITLES DATE DATE* TO FIELD REMARKS
NUMBER NO. NO.
SCHED ACTUAL 10 20 30 40 50 60 70 80 90 SCHED ACTUAL SCHED ACTUAL NO DATE LETTER DATE

PA-00B119 001 C HALON SYSTEM FP LAYOUT, CONTROL ROOM - DEMOLITION


PA-00B120 001 C CO2 SYSTEM FP SCHEMATIC LAYOUT, DIESEL GENERATOR
PA-00B121 001 C CO2 FIRE SUPPRESSION SYSTEM PIPING LAYOUT, DIESEL GENERATOR
PE-03BCAL 001 C CO2 FIRE SUPPRESSION SYSTEM CALCULATIONS
EAST/WEST PIPELINE PUMP STATION #4
PA-00B122 001 C CO2 SYSTEM FP SCHEMATIC LAYOUT, FT-4 TURBINE ENCLOSURE (ML-1/2/3)
PA-00B123 001 C CO2 FIRE SUPPRESSION SYSTEM PIPING LAYOUT, FT-4 TURBINE ENCLOSURE (ML-1/2/3)
PA-00B124 001 C HALON SYSTEM FP LAYOUT, FT-4, TURBINE ENCL.(ML-1,2,3) - DEMOLITION
PA-00B125 001 C HALON SYSTEM FP LAYOUT, CONTROL VAN (1/2/3) - DEMOLITION
PA-00B126 001 C HALON SYSTEM FP LAYOUT, CONTROL ROOM - DEMOLITION
PA-00B127 001 C CO2 SYSTEM FP SCHEMATIC LAYOUT, DIESEL GENERATOR
PA-00B128 001 C CO2 FIRE SUPPRESSION SYSTEM PIPING LAYOUT, DIESEL GENERATOR
PE-04BCAL 001 C CO2 FIRE SUPPRESSION SYSTEM CALCULATIONS
EAST/WEST PIPELINE PUMP STATION #5
PA-00B129 001 C CO2 SYSTEM FP SCHEMATIC LAYOUT, FT-4 TURBINE ENCLOSURE (ML-1/2/3)
PA-00B130 001 C CO2 FIRE SUPPRESSION SYSTEM PIPING LAYOUT, FT-4 TURBINE ENCLOSURE (ML-1/2/3)
PA-00B131 001 C HALON SYSTEM FP LAYOUT, FT-4, TURBINE ENCL.(ML-1,2,3) - DEMOLITION
PA-00B132 001 C HALON SYSTEM FP LAYOUT, CONTROL VAN (1/2/3) - DEMOLITION
PA-00B133 001 C HALON SYSTEM FP LAYOUT, CONTROL ROOM - DEMOLITION
PA-00B134 001 C CO2 SYSTEM FP SCHEMATIC LAYOUT, DIESEL GENERATOR
PA-00B135 001 C CO2 FIRE SUPPRESSION SYSTEM PIPING LAYOUT, DIESEL GENERATOR
PA-00B136 001 C CO2 SYSTEM FP SCHEMATIC LAYOUT, SOLAR POWER GENERATOR (1/2/4)
PA-00B137 001 C CO2 FIRE SUPPRESSION SYSTEM PIPING LAYOUT, SOLAR POWER GENERATOR (1/2/4)
PA-00B138 001 C HALON SYSTEM FP LAYOUT, SOLAR POWER GEN. (1/2/4)- DEMOLITION
PE-05BCAL 001 C CO2 FIRE SUPPRESSION SYSTEM CALCULATIONS
EAST/WEST PIPELINE PUMP STATION #6
PA-00B139 001 C CO2 SYSTEM FP SCHEMATIC LAYOUT, FT-4 TURBINE ENCLOSURE (ML-1/2/3)
PA-00B140 001 C CO2 FIRE SUPPRESSION SYSTEM PIPING LAYOUT, FT-4 TURBINE ENCLOSURE (ML-1/2/3)
PA-00B141 001 C HALON SYSTEM FP LAYOUT, FT-4, TURBINE ENCL.(ML-1,2,3) - DEMOLITION
PA-00B142 001 C HALON SYSTEM FP LAYOUT, CONTROL VAN (1/2/3) - DEMOLITION
PA-00B143 001 C HALON SYSTEM FP LAYOUT, CONTROL ROOM - DEMOLITION
PE-06BCAL 001 C CO2 FIRE SUPPRESSION SYSTEM CALCULATIONS
EAST/WEST PIPELINE PUMP STATION #7
PA-00B144 001 C CO2 SYSTEM FP SCHEMATIC LAYOUT, FT-4 TURBINE ENCLOSURE (ML-1/2/3)
PA-00B145 001 C CO2 FIRE SUPPRESSION SYSTEM PIPING LAYOUT, FT-4 TURBINE ENCLOSURE (ML-1/2/3)
PA-00B146 001 C HALON SYSTEM FP LAYOUT, FT-4, TURBINE ENCL.(ML-1,2,3) - DEMOLITION
PA-00B147 001 C HALON SYSTEM FP LAYOUT, CONTROL VAN (1/2/3) - DEMOLITION
PA-00B148 001 C HALON SYSTEM FP LAYOUT, CONTROL ROOM - DEMOLITION
PA-00B149 001 C CO2 SYSTEM FP SCHEMATIC LAYOUT, DIESEL GENERATOR
PA-00B150 001 C CO2 FIRE SUPPRESSION SYSTEM PIPING LAYOUT, DIESEL GENERATOR

LEGEND: NOTES: REVISION VALIDATION


SAUDI ARABIAN OIL COMPANY
A- GENERAL / CIVIL / PROCESS / PIPING 1) LIST DRAWINGS BY INDEX IN NUMERICAL ORDER. THIS REVISION NO. C IS COVERED, FOR ALL APPROVAL AND CERTIFICATION
B- FIRE ALARM AND FIRE PROTECTION
D- VESSELS 2) *NORMALLY THE FIELD ETA OF DRAWINGS CAN BE OBTAINED BY REQUIREMENTS, PER SAEP-334, UNDER DRAWING COMPLETION CERTIFICATE NO: DRAWING TYPE
DRAWING CONTROL SHEET
G- LIQUID HANDLING EQUIPMENT ADDING 2 TO 3 WEEKS TO THE SCHEDULED COMPLETION DATE ABOVE. DSC
H- PAINTS / COATINGS
10-00844-0001-001
J- INSTRUMENTATION
K- HVAC REPLACE HALON SYSTEM EAST/WEST PIPELINE PUMP STATIONS
L- PIPING
DESIGN CERTIFICATION REVIEW FOR KEY DRAWINGS
M- STEEL STRUCTURE OTHER
O- SECURITY (DESIGN AGENCY) REQUIRED (SAUDI ARAMCO)
P- ELECTRICAL EAST/WEST PIPELINE PUMP STATION #1
ENGG./DATE CERT. BY/DATE CONST. AGENCY/DATE OPERATIONS/DATE BY/DATE
Q- CONCRETE STRUCTURE
R- ARCHITECTURE
S- PLUMBING / CIVIL / UTILITY SERVICES / LANDSCAPING
YANBU SAUDI ARABIA
T- COMMUNICATION
REV. NO. DATE REVISION DESCRIPTION PLANT NO. INDEX DRAWING NO. SHEET NO. REV NO.
X- CATHODIC PROTECTION
U- SPECIAL EQUIPMENT C 07/01/2021 ISSUED FOR 100% - PP
Z- PROCESS CONTROL SYSTEMS
JOB ORDER/EWO NO. THIS REVISION IS NOT TO BE USED FOR CONSTRUCTION UNTIL CERTIFIED AND K04 A PD-00ADCL 002 C
10-00844-0001 DATED

EKRD/2617-1110.XLS