HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT
TOKO/QUARRY
1 2 3 4 5 6
I BAHAN PASANGAN
1 Pasir Urug (PU) M3 80,000.00 24,400.00 38,400.00
2 Pasir Pasang (PP) M3 80,000.00 24,400.00 38,400.00
3 Pasir Beton (PB) M3 80,000.00 24,400.00 38,400.00
4 Pasir Kuarsa M3 88,000.00 24,400.00 76,700.00
5 Kerikil (KR) M3 135,000.00 25,100.00 38,400.00
6 Sirtu M3 125,000.00 24,100.00 38,400.00
7 Batu Belah (gunung) 15cm/20 cm M3 230,000.00 55,100.00 101,700.00
8 Batu sungai (mangga) M3 250,000.00 30,100.00 38,500.00
9 Portland Cement (PC) Kg 1,200.00 150.00 300.00
10 Semen putih Kg 2,300.00 75.00 75.00
11 Cornite Compound Jayaboard Zak 70,000.00 3,100.00 800.00
12 Bata Merah ( Ukuran Jumbo ) Buah 550.00 50.00 50.00
13 Kerawang (Roster semen)20x20 cm Buah 22,000.00 50.00 150.00
14 Kerawang (Roster semen)40x40 cm Buah 45,000.00 50.00 150.00
15 Rumput Gajah Mini M2 40,500.00 650.00 1,600.00
16 Rumput Biasa M2 16,500.00 650.00 1,600.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT
TOKO/QUARRY
1 2 3 4 5 6
17 Tanah Hitam M3 55,000.00 23,500.00 29,000.00
18 Tanah Urug Biasa M3 20,000.00 23,500.00 29,000.00
19 Conblock Segi 6 Tebal 8 CM Bh 1,800.00 50.00 150.00
20 Conblock Segi 4 Tebal 8 CM Bh 1,800.00 50.00 150.00
21 Grass Block T= 6 cm Bh 20,600.00 50.00 150.00
22 Buis Beton Dia 20cm P= 50 Cm Bh 51,000.00 6,100.00 7,700.00
23 Buis Beton Dia 40cm P = 60 Cm Bh 158,000.00 12,100.00 23,000.00
24 Buis Beton Dia 60cm P= 80 Cm Bh 280,000.00 18,100.00 23,000.00
25 Buis Beton Dia 80cm P= 100 Cm Bh 350,000.00 24,100.00 30,700.00
26 Buis Beton Dia 100cm P = 100 Cm Bh 448,000.00 24,100.00 30,700.00
27 Batu Split / Pecah M3 320,000.00 12,000.00 16,400.00
28 Bata Beton Ringan Buah 6,000.00 500.00 500.00
29 Batu Tempel Uk. 20 x 20 Buah 5,000.00 150.00 150.00
30 Batu Tempel Uk. 20 x 40 Buah 12,500.00 150.00 150.00
II BAHAN KAYU
1 Kayu Kelas I ( Kulim ) M3 3,500,000.00 55,000.00 54,000.00
2 Kayu Kelas II ( Merantim, Balam ) M3 1,900,000.00 55,000.00 54,000.00
3 Kayu Kelas III M3 1,700,000.00 55,000.00 54,000.00
4 Kayu Kelas IV M3 1,210,750.00 55,000.00 54,000.00
5 Kayu List Profil siku2" M' 2,500.00 50.00 100.00
6 Kayu List Profil 0.8x3" M' 3,000.00 50.00 100.00
7 Papan 2 x 20 M3 1,800,000.00 55,000.00 54,000.00
8 Kayu Cerocok dia. 10 - 15 cm Btg 35,000.00 650.00 5,000.00
9 Dolken Kayu Galam, Ø (8-10)Cm,Panjang 4 M Batang 6,000.00 650.00 1,000.00
10 Kayu Bakar ( Non Kelas ) M3 200,000.00 55,000.00 54,000.00
11 Papan Piri - piri (Siap Ketam 3 sisi) M3 2,200,000.00 55,000.00 54,000.00
12 Papan Lebah Bergayut M' 40,000.00 650.00 1,550.00
13 Singap Ukir kayu M2 750,000.00 3,700.00 15,300.00
14 Singap Ukir GRC M2 400,000.00 3,700.00 15,300.00
15 Selembayung GRC Lebar 30 cm Pasang 400,000.00 1,200.00 7,700.00
16 Selembayung kayu lebar 30 cm Pasang 250,000.00 1,200.00 7,700.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT
TOKO/QUARRY
1 2 3 4 5 6
17 Sayap layang-layang lebar 30 cm Pasang 250,000.00 1,200.00 7,700.00
18 Lisplank papan + anak ( + 30 cm) M' 50,000.00 1,200.00 7,700.00
IV BAHAN PAKU
1 Paku 1 Cm - 2,5 Cm Kg 15,000.00 100.00 200.00
2 Paku 5 Cm - 12 Cm Kg 15,000.00 100.00 200.00
3 Paku Skrup Kg 40,000.00 100.00 200.00
4 Paku Skrup 5 Cm Kg 40,000.00 100.00 200.00
5 Paku Skrup 10 Cm Kg 40,000.00 100.00 200.00
6 Paku Asbes Kg 20,000.00 100.00 200.00
7 Paku Atap Genteng Metal Kg 24,000.00 100.00 200.00
8 Paku Atap Seng Gelombang Kg 20,000.00 100.00 200.00
9 Skrup Fixer Buah 300.00 50.00 50.00
V BAHAN ALLUMUNIUM
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT
TOKO/QUARRY
1 2 3 4 5 6
1 Profil Allumunium "T" M' 23,000.00 350.00 1,700.00
2 Kusen Alumunium 3'' M' 193,000.00 600.00 1,700.00
3 Rangka Jendela Almunium M' 193,000.00 600.00 1,700.00
4 Rangka Pintu Almunium M' 193,000.00 600.00 1,700.00
VI BAHAN LANTAI
1 Homogenius Ukuran ( 60 x 60 ) Cm Buah 59,800.00 150.00 200.00
2 Homogenius Ukuran ( 40 x 40 ) cm Buah 31,700.00 150.00 200.00
3 Homogenius Ukuran ( 30 x 30 ) cm Buah 15,500.00 150.00 200.00
4 Keramik (40x40) Cm Buah 8,850.00 100.00 200.00
5 Keramik (30x30) Cm Buah 4,350.00 100.00 200.00
6 Keramik (20x20) Cm Buah 2,100.00 100.00 150.00
7 Keramik (20x25) Cm Buah 2,700.00 100.00 150.00
8 Granit Warna (60x60) Cm Buah 85,000.00 150.00 200.00
9 Keramik Warna (40x40) Cm Buah 9,400.00 100.00 150.00
10 Keramik Warna (30x30) Cm Buah 4,900.00 75.00 150.00
11 Keramik Warna (20x20) Cm Buah 2,300.00 75.00 150.00
12 Plint Keramik (10x20) Cm Buah 1,400.00 75.00 75.00
13 Plint Keramik (10x30) Cm Buah 2,300.00 75.00 75.00
14 Plint Keramik (10x40) Cm Buah 3,200.00 75.00 75.00
15 Plint Homogenius (10x60) Cm Buah 12,000.00 75.00 75.00
16 Plint Homogenius (10x40) Cm Buah 11,000.00 100.00 150.00
17 Plint Keramik Warna (10x20) Cm Buah 1,300.00 75.00 75.00
18 Plint Keramik Warna (10x30) Cm Buah 2,300.00 75.00 75.00
19 Plint Keramik Warna (10x40) Cm Buah 3,200.00 75.00 75.00
20 Plint Granit Warna (10x60) Cm Buah 13,300.00 75.00 75.00
21 Bon-bon Keramik M' 7,700.00 100.00 150.00
22 Floor hardener M2 34,800.00 100.00 100.00
23 Parquette M2 225,000.00 100.00 200.00
24 Karpet M2 12,900.00 400.00 5,200.00
IX BAHAN LANGIT-LANGIT
1 Teakwood Tebal 3,6 mm Lembar 150,000.00 650.00 1,550.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT
TOKO/QUARRY
1 2 3 4 5 6
2 Triplek Tebal 12 MM Lembar 202,000.00 650.00 1,200.00
3 Triplek Tebal 9,0 MM Lembar 145,000.00 650.00 1,000.00
4 Triplek Tebal 3,6 MM Lembar 65,000.00 650.00 1,550.00
5 Triplek Tebal 3,0 MM Lembar 57,200.00 600.00 1,200.00
6 Gypsum Board 9 mm Lembar 85,000.00 650.00 1,550.00
7 List Gypsum lbr 15-20cm M' 17,600.00 650.00 1,550.00
8 Asbes Semen M2 50,000.00 650.00 1,550.00
9 Triplek melamin Lembar 75,000.00 650.00 1,550.00
XI BAHAN PINTU
1 Pintu Besi M2 660,000.00 6,100.00 30,700.00
2 Pintu Fiber Warna Lbr 754,000.00 6,100.00 30,700.00
3 Pintu Fiber KM/WC (lengkap) Lbr 300,000.00 6,100.00 30,700.00
4 Pintu Panel kelas I ( Setara Balam ) Lbr 850,000.00 6,100.00 30,700.00
5 Pintu Panel Kelas II ( Setara Meranti ) Lbr 700,000.00 6,100.00 30,700.00
6 Pintu Plywood (triplek depan blkg) Lbr 190,000.00 6,100.00 30,700.00
7 Pintu Teakwood (lapis jati) depan belakang Lbr 620,000.00 6,100.00 30,700.00
8 Vertical Blind M2 90,000.00 6,100.00 4,100.00
9 Rolling Door M2 500,000.00 5,000.00 15,500.00
10 Folding Gate M2 650,000.00 5,000.00 15,500.00
11 Pintu Aluminium Kaca Lbr 2,100,000.00 5,000.00 15,500.00
XV BAHAN CAT
1 Cat Tembok Standar Kg 12,000.00 200.00 350.00
2 Cat Tembok Akrilik Kg 25,000.00 200.00 350.00
3 Cat Tembok Weather Shield Kg 75,000.00 200.00 350.00
4 Cat Kayu dan Besi ( Cat Minyak ) Kg 58,000.00 200.00 350.00
5 Cat Dasar / Kapur Kg 8,000.00 200.00 350.00
6 Cat Dasar / Menie Kayu Kg 30,000.00 200.00 350.00
7 Cat Vernish Kg 56,000.00 200.00 350.00
8 Cat Impra Kg 41,500.00 200.00 350.00
9 Cat Residu Kg 35,350.00 200.00 350.00
10 Soda Api Kg 11,600.00 200.00 350.00
11 Plamir setara RJ Kg 27,200.00 200.00 350.00
12 Dempul Kayu Kg 38,400.00 200.00 350.00
13 Kertas Amplas Lbr 6,100.00 100.00 150.00
14 Kuas 3" Bh 17,300.00 100.00 150.00
15 Kuas Golong/rol Bh 26,350.00 100.00 150.00
16 Thinner Ltr 36,400.00 150.00 350.00
17 Flincote / Menie Besi Kg 16,500.00 150.00 350.00
9 Kuda - Kuda Maks. Bentangan 8 M & Rangka Atap Baja Ringan Setara Taso + M2 - - -
Atap Genteng Metal Tbl. 0,25 MM
10 Kuda - Kuda Maks. Bentangan 8 M & Rangka Atap Baja Ringan Setara Taso + M2 - - -
Atap Longspan Setara Spandek Tbl. 0,25 MM
11 Atap Canopy ( Polycarbonat + Rangka Hollow Stalbuis ) M2 - - -
12 Atap Canopy ( Longspan + Rangka Hollow Stalbuis ) M2 - - -
13 Partisi Kaca ( Tebal 5 MM ) + Rangka U PVC M2 - - -
14 Partisi Kaca ( Tebal 8 MM ) Frameless M2 - - -
15 Partisi Kaca ( Tebal 12 MM ) Frameless M2 - - -
16 Pintu Kaca Tempered Frameless Uk. 80 x 200 CM (Tebal 12 MM) Lengkap Unit - - -
dengan Handle, Kunci dan Engsel Pivot
17 Pintu Kaca Tempered Fitting Uk. 80 x 200 CM ( Tebal 12 MM ) Lengkap Unit - - -
dengan Handle, Kunci dan Engsel Pivot
18 Pintu Kaca Polos Swing Uk. 80 x 200 CM ( Tebal 5 MM ) Lengkap dengan Unit - - -
Handle, Kunci dan Engsel
19 Pintu Kaca Polos Sliding Uk. 80 x 200 CM ( Tebal 5 MM ) Lengkap dengan Unit - - -
Handle, Kunci dan Rel
KETERANGAN
5
JUMLAH
7 ( 4+5+6)
142,800.00
142,800.00
142,800.00
189,100.00
198,500.00
187,500.00
386,800.00
318,600.00
1,650.00
2,450.00
73,900.00
650.00
22,200.00
45,200.00
42,750.00
18,750.00
JUMLAH
7 ( 4+5+6)
107,500.00
72,500.00
2,000.00
2,000.00
20,800.00
64,800.00
193,100.00
321,100.00
404,800.00
502,800.00
348,400.00
7,000.00
5,300.00
12,800.00
3,609,000.00
2,009,000.00
1,809,000.00
1,319,750.00
2,650.00
3,150.00
1,909,000.00
40,650.00
7,650.00
309,000.00
2,309,000.00
42,200.00
769,000.00
419,000.00
408,900.00
258,900.00
JUMLAH
7 ( 4+5+6)
258,900.00
58,900.00
9,200.00
20,200.00
10,600.00
11,400.00
245,300.00
18,150.00
16,150.00
20,150.00
13,950.00
13,200.00
260,000.00
18,400.00
17,100.00
13,500.00
13,500.00
15,300.00
15,300.00
40,300.00
40,300.00
40,300.00
20,300.00
24,300.00
20,300.00
400.00
JUMLAH
7 ( 4+5+6)
25,050.00
195,300.00
195,300.00
195,300.00
60,150.00
32,050.00
15,850.00
9,150.00
4,650.00
2,350.00
2,950.00
85,350.00
9,650.00
5,125.00
2,525.00
1,550.00
2,450.00
3,350.00
12,150.00
11,250.00
1,450.00
2,450.00
3,350.00
13,450.00
7,950.00
35,000.00
225,300.00
18,500.00
JUMLAH
7 ( 4+5+6)
34,500.00
40,500.00
40,500.00
25,500.00
46,500.00
71,500.00
59,500.00
5,500.00
250,500.00
22,000.00
28,500.00
13,500.00
42,200.00
40,500.00
7,200.00
10,700.00
4,600.00
6,600.00
36,400.00
20,200.00
25,426.76
12,426.76
31,426.76
1,076.76
1,076.76
8,426.76
6,926.76
152,200.00
JUMLAH
7 ( 4+5+6)
203,850.00
146,650.00
67,200.00
59,000.00
87,200.00
19,800.00
52,200.00
77,200.00
4,350.00
4,650.00
6,250.00
15,450.00
17,950.00
25,450.00
30,450.00
110,450.00
15,450.00
60,450.00
90,450.00
123,450.00
39,450.00
21,450.00
31,450.00
52,450.00
10,450.00
100,450.00
256,800.00
336,800.00
1,786,800.00
286,800.00
JUMLAH
7 ( 4+5+6)
1,336,800.00
486,800.00
5,350.00
160,450.00
15,450.00
536,800.00
636,800.00
1,386,800.00
1,636,800.00
3,236,800.00
17,650.00
696,800.00
790,800.00
336,800.00
886,800.00
736,800.00
226,800.00
656,800.00
100,200.00
520,500.00
670,500.00
2,120,500.00
200,350.00
130,350.00
50,350.00
50,350.00
7,850.00
5,350.00
JUMLAH
7 ( 4+5+6)
20,350.00
11,350.00
8,850.00
6,850.00
7,850.00
390,350.00
20,350.00
7,800.00
7,800.00
85,200.00
95,700.00
368,900.00
513,100.00
97,100.00
119,700.00
188,700.00
100,700.00
128,700.00
97,700.00
28,700.00
189,000.00
6,750.00
8,450.00
75,250.00
50,250.00
74,450.00
310,450.00
100,450.00
JUMLAH
7 ( 4+5+6)
94,250.00
188,250.00
14,750.00
14,750.00
21,850.00
27,250.00
50,300.00
12,550.00
25,550.00
75,550.00
58,550.00
8,550.00
30,550.00
56,550.00
42,050.00
35,900.00
12,150.00
27,750.00
38,950.00
6,350.00
17,550.00
26,600.00
36,900.00
17,000.00
102,900.00
3,675,000.00
50.00
3,000.00
JUMLAH
7 ( 4+5+6)
31,300.00
4,800.00
20,700.00
25,850.00
12,550.00
2,100.00
8,850.00
25,300.00
4,900.00
9,150.00
49,900.00
15,500.00
30,500.00
97,700.00
52,200.00
12,250.00
23,050.00
41,500.00
787,500.00
26,300.00
66,250.00
204,000.00
161,000.00
212,000.00
80,000.00
170,000.00
145,500.00
115,500.00
220,500.00
JUMLAH
7 ( 4+5+6)
210,000.00
346,500.00
93,500.00
199,500.00
189,000.00
370,000.00
370,000.00
1,260,000.00
892,500.00
966,000.00
5,197,500.00
6,063,750.00
1,559,250.00
1,617,000.00
603,750.00
367,500.00
603,750.00
630,000.00
JUMLAH
7 ( 4+5+6)
210,000.00
DAFTAR HARGA SATUAN UPAH DAN BAHAN BANGUNAN
TAHUN ANGGARAN 2018
DAERAH SEDANG
DAFTAR UPAH
1 2 3 4 5
1 Pekerja OH 67,900.00
2 Tukang Bangunan ( Batu, Kayu, Pipa, Bongkar, Cat dan Besi ) OH 83,200.00
3 Kepala Tukang OH 88,000.00
4 Mandor Bangunan OH 90,000.00
1 2 3 4 5
I BAHAN PASANGAN
1 Pasir Urug (PU) M3 142,800.00
2 Pasir Pasang (PP) M3 142,800.00
3 Pasir Beton (PB) M3 142,800.00
4 Pasir Kuarsa M3 189,100.00
5 Kerikil (KR) M3 198,500.00
6 Sirtu M3 187,500.00
7 Batu Belah (gunung) 15cm/20 cm M3 386,800.00
8 Batu sungai (mangga) M3 318,600.00
9 Portland Cement (PC) Kg 1,650.00
10 Semen putih Kg 2,450.00
11 Cornite Compound Jayaboard Zak 73,900.00
12 Bata Merah ( Ukuran Jumbo ) Buah 650.00
13 Kerawang (Roster semen)20x20 cm Buah 22,200.00
14 Kerawang (Roster semen)40x40 cm Buah 45,200.00
15 Rumput Gajah Mini M2 42,750.00
16 Rumput Biasa M2 18,750.00
17 Tanah Hitam M3 107,500.00
18 Tanah Urug Biasa M3 72,500.00
19 Conblock Segi 6 Tebal 8 CM Bh 2,000.00
20 Conblock Segi 4 Tebal 8 CM Bh 2,000.00
21 Grass Block T= 6 cm Bh 20,800.00
22 Buis Beton Dia 20cm P= 50 Cm Bh 64,800.00
23 Buis Beton Dia 40cm P = 60 Cm Bh 193,100.00
24 Buis Beton Dia 60cm P= 80 Cm Bh 321,100.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.
1 2 3 4 5
25 Buis Beton Dia 80cm P= 100 Cm Bh 404,800.00
26 Buis Beton Dia 100cm P = 100 Cm Bh 502,800.00
27 Batu Split / Pecah M3 348,400.00
28 Bata Beton Ringan Buah 7,000.00
29 Batu Tempel Uk. 20 x 20 Buah 5,300.00
30 Batu Tempel Uk. 20 x 40 Buah 12,800.00
II BAHAN KAYU
1 Kayu Kelas I ( Kulim ) M3 3,609,000.00
2 Kayu Kelas II ( Merantim, Balam ) M3 2,009,000.00
3 Kayu Kelas III M3 1,809,000.00
4 Kayu Kelas IV M3 1,319,750.00
5 Kayu List Profil siku2" M' 2,650.00
6 Kayu List Profil 0.8x3" M' 3,150.00
7 Papan 2 x 20 M3 1,909,000.00
8 Kayu Cerocok dia. 10 - 15 cm Btg 40,650.00
9 Dolken Kayu Galam, Ø (8-10)Cm,Panjang 4 M Batang 7,650.00
10 Kayu Bakar ( Non Kelas ) M3 309,000.00
11 Papan Piri - piri (Siap Ketam 3 sisi) M3 2,309,000.00
12 Papan Lebah Bergayut M' 42,200.00
13 Singap Ukir kayu M2 769,000.00
14 Singap Ukir GRC M2 419,000.00
15 Selembayung GRC Lebar 30 cm Pasang 408,900.00
16 Selembayung kayu lebar 30 cm Pasang 258,900.00
17 Sayap layang-layang lebar 30 cm Pasang 258,900.00
18 Lisplank papan + anak ( + 30 cm) M' 58,900.00
1 2 3 4 5
14 Wiremesh M6 Kg 13,500.00
15 Wiremesh M8 Kg 13,500.00
IV BAHAN PAKU
1 Paku 1 Cm - 2,5 Cm Kg 15,300.00
2 Paku 5 Cm - 12 Cm Kg 15,300.00
3 Paku Skrup Kg 40,300.00
4 Paku Skrup 5 Cm Kg 40,300.00
5 Paku Skrup 10 Cm Kg 40,300.00
6 Paku Asbes Kg 20,300.00
7 Paku Atap Genteng Metal Kg 24,300.00
8 Paku Atap Seng Gelombang Kg 20,300.00
9 Skrup Fixer Buah 400.00
V BAHAN ALLUMUNIUM
1 Profil Allumunium "T" M' 25,050.00
2 Kusen Alumunium 3'' M' 195,300.00
3 Rangka Jendela Almunium M' 195,300.00
4 Rangka Pintu Almunium M' 195,300.00
VI BAHAN LANTAI
1 Homogenius Ukuran ( 60 x 60 ) Cm Buah 60,150.00
2 Homogenius Ukuran ( 40 x 40 ) cm Buah 32,050.00
3 Homogenius Ukuran ( 30 x 30 ) cm Buah 15,850.00
4 Keramik (40x40) Cm Buah 9,150.00
5 Keramik (30x30) Cm Buah 4,650.00
6 Keramik (20x20) Cm Buah 2,350.00
7 Keramik (20x25) Cm Buah 2,950.00
8 Granit Warna (60x60) Cm Buah 85,350.00
9 Keramik Warna (40x40) Cm Buah 9,650.00
10 Keramik Warna (30x30) Cm Buah 5,125.00
11 Keramik Warna (20x20) Cm Buah 2,525.00
12 Plint Keramik (10x20) Cm Buah 1,550.00
13 Plint Keramik (10x30) Cm Buah 2,450.00
14 Plint Keramik (10x40) Cm Buah 3,350.00
15 Plint Homogenius (10x60) Cm Buah 12,150.00
16 Plint Homogenius (10x40) Cm Buah 11,250.00
17 Plint Keramik Warna (10x20) Cm Buah 1,450.00
18 Plint Keramik Warna (10x30) Cm Buah 2,450.00
19 Plint Keramik Warna (10x40) Cm Buah 3,350.00
20 Plint Granit Warna (10x60) Cm Buah 13,450.00
21 Bon-bon Keramik M' 7,950.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.
1 2 3 4 5
22 Floor hardener M2 35,000.00
23 Parquette M2 225,300.00
24 Karpet M2 18,500.00
IX BAHAN LANGIT-LANGIT
1 Teakwood Tebal 3,6 mm Lembar 152,200.00
2 Triplek Tebal 12 MM Lembar 203,850.00
3 Triplek Tebal 9,0 MM Lembar 146,650.00
4 Triplek Tebal 3,6 MM Lembar 67,200.00
5 Triplek Tebal 3,0 MM Lembar 59,000.00
6 Gypsum Board 9 mm Lembar 87,200.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.
1 2 3 4 5
7 List Gypsum lbr 15-20cm M' 19,800.00
8 Asbes Semen M2 52,200.00
9 Triplek melamin Lembar 77,200.00
XI BAHAN PINTU
1 Pintu Besi M2 696,800.00
2 Pintu Fiber Warna Lbr 790,800.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.
1 2 3 4 5
3 Pintu Fiber KM/WC (lengkap) Lbr 336,800.00
4 Pintu Panel kelas I ( Setara Balam ) Lbr 886,800.00
5 Pintu Panel Kelas II ( Setara Meranti ) Lbr 736,800.00
6 Pintu Plywood (triplek depan blkg) Lbr 226,800.00
7 Pintu Teakwood (lapis jati) depan belakang Lbr 656,800.00
8 Vertical Blind M2 100,200.00
9 Rolling Door M2 520,500.00
10 Folding Gate M2 670,500.00
11 Pintu Aluminium Kaca Lbr 2,120,500.00
1 2 3 4 5
2 Lampu Pijar 25 Watt Buah 6,750.00
3 Lampu Pijar 40 Watt Buah 8,450.00
4 Lampu Neon Jantung Buah 75,250.00
5 Lampu Save Energy (Lilin) Setara Philips Buah 50,250.00
6 Lampu TL Komplit 1 x 20 watt Buah 74,450.00
7 Lampu TL Komplit 2 x 20 Watt Buah 310,450.00
8 Lampu TL Komplit 1 x 40 Watt Buah 100,450.00
9 Lampu Down Light 4" komplit Buah 94,250.00
10 Lampu Baret Buah 188,250.00
11 Stop Kontak (setara broco) Buah 14,750.00
12 Saklar Tunggal (setara broco) Buah 14,750.00
13 Saklar Ganda (setara broco) Buah 21,850.00
14 Saklar Triple (setara broco) Buah 27,250.00
15 Zakering Khas (setara merlin gerlin) Buah 50,300.00
XV BAHAN CAT
1 Cat Tembok Standar Kg 12,550.00
2 Cat Tembok Akrilik Kg 25,550.00
3 Cat Tembok Weather Shield Kg 75,550.00
4 Cat Kayu dan Besi ( Cat Minyak ) Kg 58,550.00
5 Cat Dasar / Kapur Kg 8,550.00
6 Cat Dasar / Menie Kayu Kg 30,550.00
7 Cat Vernish Kg 56,550.00
8 Cat Impra Kg 42,050.00
9 Cat Residu Kg 35,900.00
10 Soda Api Kg 12,150.00
11 Plamir setara RJ Kg 27,750.00
12 Dempul Kayu Kg 38,950.00
13 Kertas Amplas Lbr 6,350.00
14 Kuas 3" Bh 17,550.00
15 Kuas Golong/rol Bh 26,600.00
16 Thinner Ltr 36,900.00
17 Flincote / Menie Besi Kg 17,000.00
1 2 3 4 5
8 Lem Kayu Kg 25,850.00
9 Sealant Kg 12,550.00
10 Profil Kaca M' 2,100.00
11 Solar Liter 8,850.00
12 Minyak Pelumas Liter 25,300.00
13 Minyak Bekisting Liter 4,900.00
14 Aspal Drum Kg 9,150.00
15 Tempat Masak Aspal BH 49,900.00
16 Ijuk Kg 15,500.00
17 Water proofing Coating Kg 30,500.00
18 Water proofing Membran M2 97,700.00
19 Batu Coral sikat ZAK 52,200.00
20 Alat Pemadat ( 6 s/d 8 Ton) M2 12,250.00
21 List Profil GRC Lebar 10 CM M1 23,050.00
22 Penjaga Jarak Bekisting / Spacer Buah 41,500.00
23 Jump Piller Driver + Hammer Jam 787,500.00
24 Pupuk Kandang Krg 26,300.00
25 Wallpaper M2 66,250.00
26 Sunscreeen Alluminium M2 204,000.00
27 Tiang Pancang Mini Pile Uk. 20 x 20 CM K-500 M1 161,000.00
28 Tiang Pancang Mini Pile Uk. 25 x 25 CM K-500 M1 212,000.00
9 Kuda - Kuda Maks. Bentangan 8 M & Rangka Atap Baja Ringan M2 199,500.00
Setara Taso + Atap Genteng Metal Tbl. 0,25 MM
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.
1 2 3 4 5
10 Kuda - Kuda Maks. Bentangan 8 M & Rangka Atap Baja Ringan M2 189,000.00
Setara Taso + Atap Longspan Setara Spandek Tbl. 0,25 MM
1 2 3
I. PEKERJAAN PERSIAPAN 1
2
3
4
5
6
1 2 3
1 2 3
33
34
35
36
37
38
39
40
1 2 3
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
1 2 3
17
18
19
20
21
22
X. PEKERJAAN ATAP 1
2
3
4
5
6
7
1 2 3
11
12
13
14
15
16
17
1 2 3
9
10
3 4
3 4
Membuat 1 M3 beton mutu f'c = 7,4 Mpa ( K 100 ), slump ( 12 ± 2 ) cm, w/c = 0,87 Rp 838,149.95
Membuat 1 M3 beton mutu f'c = 9,8 Mpa ( K 125 ), slump ( 12 ± 2 ) cm, w/c = 0,78 Rp 928,544.65
Membuat 1 M3 beton mutu f'c = 12,2 Mpa ( K 150 ), slump ( 12 ± 2 ) cm, w/c = 0,72 Rp 967,909.25
Membuat 1 M3 lantai kerja beton mutu f'c = 7,4 Mpa ( K 100 ), slump ( 3 - 6 ) cm, w/c = 0,87 Rp 811,223.60
Membuat 1 M3 beton mutu f'c = 14,5 Mpa ( K 175 ), slump ( 12 ± 2 ) cm, w/c = 0,66 Rp 1,014,503.60
Membuat 1 M3 beton mutu f'c = 16,9 Mpa ( K 200 ), slump ( 12 ± 2 ) cm, w/c = 0,61 Rp 1,058,658.15
Membuat 1 M3 beton mutu f'c = 19,3 Mpa ( K 225 ), slump ( 12 ± 2 ) cm, w/c = 0,58 Rp 1,092,060.75
Membuat 1 M3 beton mutu f'c = 21,7 Mpa ( K 250 ), slump ( 12 ± 2 ) cm, w/c = 0,56 Rp 1,113,672.45
Membuat 1 M3 beton mutu f'c = 24 Mpa ( K 275 ), slump ( 12 ± 2 ) cm, w/c = 0,53 Rp 1,150,739.70
Membuat 1 M3 beton mutu f'c = 26,4 Mpa ( K 300 ), slump ( 12 ± 2 ) cm, w/c = 0,52 Rp 1,162,234.70
Membuat 1 M3 beton mutu f'c = 28,8 Mpa ( K 325 ), slump ( 12 ± 2 ) cm, w/c = 0,49 Rp 1,249,118.75
Membuat 1 M3 beton mutu f'c = 31,2 Mpa ( K 350 ), slump ( 12 ± 2 ) cm, w/c = 0,48 Rp 1,264,025.40
Pembesian 10 Kg dengan besi polos Rp 121,963.05
Pembesian 10 Kg dengan besi ulir Rp 249,013.05
Pemasangan 1 M2 bekisting untuk pondasi Rp 152,908.80
Pemasangan 1 M2 bekisting untuk sloof Rp 162,858.30
Pemasangan 1 M2 bekisting untuk kolom Rp 279,803.15
Pemasangan 1 M2 bekisting untuk Balok Rp 286,432.85
Pemasangan 1 M2 bekisting untuk lantai Rp 313,463.15
Pemasangan 1 M2 bekisting untuk dinding Rp 461,968.65
Pemasangan 1 M2 bekisting untuk Tangga Rp 259,634.65
Pemasangan 1 M2 jembatan Rangka Kayu untuk pengecoran beton Rp 83,894.36
Pemasangan 1 M3 pondasi beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting ) Rp 3,623,422.55
Pemasangan 1 M3 pondasi beton Camp. 1 PC : 2 Psr : 3 Krk ( termasuk bekisting ) Rp 1,984,601.30
Membuat 1 M3 sloof beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting ) Rp 4,408,137.80
Membuat 1 M3 sloof beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting ) Rp 3,861,864.05
Membuat 1 M3 kolom beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting ) Rp 5,993,906.60
Membuat 1 M3 kolom beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting ) Rp 5,417,685.35
Membuat 1 M3 balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting ) Rp 5,493,879.60
Membuat 1 M3 balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting ) Rp 4,947,605.85
Membuat 1 M3 pelat beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 kg besi + bekisting ) Rp 4,883,729.95
Membuat 1 M3 dinding beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 kg besi + bekisting ) Rp 4,745,323.55
JENIS PEKERJAAN HARGA
3 4
Membuat 1 M3 dinding beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 kg besi + bekisting ) Rp 5,141,540.80
Membuat 1 M' kolom praktis beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 11 cm x 11 cm ) Rp 82,152.18
Membuat 1 M' ring balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 10 cm x 15 cm ) Rp 100,189.43
Membuat 1 M3 Jalan Beton Mutu K.175 Rp 1,455,981.12
Membuat 1 M3 Dinding dan Lantai Drainase Beton Bertulang Mutu K-175 ( 60 Kg Besi ) Rp 2,659,931.34
Membuat 1 M3 Skor Drainase ( 160 Kg Besi + Bekisting ) Mutu K-175 Rp 4,218,789.74
Membuat Beton Camp. 1 PC : 3 Psr : 5 Krk Rp 823,774.60
Membuat Beton Camp. 1 PC : 2 Psr : 3 Krk Rp 1,155,326.70
3 4
Pemasangan 1 M2 Plesteran 1 PC : 3 PP Tebal 15 mm Rp 56,798.28
Pemasangan 1 M2 Plesteran 1 PC : 4 PP Tebal 15 mm Rp 54,167.52
Pemasangan 1 M2 Plesteran 1 PC : 5 PP Tebal 15 mm Rp 52,565.04
Pemasangan 1 M2 Plesteran 1 PC : 6 PP Tebal 15 mm Rp 51,328.20
Pemasangan 1 M2 Plesteran 1 PC : 7 PP Tebal 15 mm Rp 50,614.08
Pemasangan 1 M2 Plesteran 1 PC : 8 PP Tebal 15 mm Rp 49,899.96
Pemasangan 1 M2 Plesteran 1 PC : 1 PP Tebal 20 mm Rp 81,277.24
Pemasangan 1 M2 Plesteran 1 PC : 3 PP Tebal 20 mm Rp 64,633.80
Pemasangan 1 M2 Plesteran 1 PC : 4 PP Tebal 20 mm Rp 72,421.36
Pemasangan 1 M2 Plesteran 1 PC : 5 PP Tebal 20 mm Rp 70,337.08
Pemasangan 1 M2 Plesteran 1 PC : 6 PP Tebal 20 mm Rp 68,635.60
Pemasangan 1 M2 Berapen 1 PC : 5 PP Tebal 15 mm Rp 33,126.94
Pemasangan 1 M2 Plesteran Ciprat 1 PC : 2 PP Rp 42,795.28
Pemasangan 1 M2 Acian Rp 31,946.75
Pemasangan 1 M2 Finishing Siar Pasangan Bata Merah Rp 25,274.92
3 4
Pemasangan 1 M2 Lantai Karpet Rp 53,314.80
Pemasangan 1 M2 Lantai Parquet Rp 353,369.50
Pemasangan 1 M2 Dinding Batu Tempel Uk. 20 X 20 CM Rp 272,487.05
Pemasangan 1 M2 Dinding Batu Tempel Uk. 20 X 40 CM Rp 308,072.05
Pemasangan 1 M2 Wallpaper Lebar 50 CM Rp 205,151.10
Pemasangan 1 M' Plint Kayu Tebal 2 CM Lebar 10 CM Rp 34,452.00
Pembuatan & Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas I Rp 7,099,042.50
Pembuatan & Pemasangan Kusen Kayu Kelas II Rp 5,000,792.50
Pembuatan dan Pemasangan 1 M2 Pintu Klamp Standar, Kayu Kelas II Rp 223,421.00
Pembuatan & Pemasangan 1 M2 Pintu Klamp Sederhana, Kayu Klam Kelas III Rp 214,621.00
Pembuatan & Pemasangan 1 M2 Daun Pintu Panel, Kayu Kelas I Rp 556,253.50
Pembuatan & Pemasangan 1M2 Pintu/Jendela Kaca Kayu Kelas II Rp 461,880.10
Pembuatan & Pemasangan 1 M2 Jalusi Pintu/Jendela Kayu Kelas II Rp 538,891.10
Pembuatan 1 M2 Daun Pintu Plywood Rangkap, Rangka Kayu Kelas II Tertutup ( Lebar sampai 90 cm ) Rp 412,157.90
Pembuatan & Pemasangan 1M2 Jalusi Kusen Kayu kelas II Rp 420,725.80
Pembuatan & Pemasangan 1 M2 Teakwood Rangka Ekspos Kayu Kelas I Rp 582,294.90
JENIS PEKERJAAN HARGA
3 4
Pemasangan 1M3 Kuda-kuda Konvensional Kayu Kelas II Rp 4,275,898.00
Pemasangan 1 M3 Konstruksi Gordeng, Kayu Kelas II Rp 5,266,888.00
Pemasangan 1 M2 Rangka Langit-langit 60x60 Kayu Kelas II Rp 86,516.87
Pemasangan 1 M2 Rangka Dinding Pemisah ( 60 x 120 ) CM Kayu Kelas II Rp 119,800.45
Pemasangan 1 M2 Dinding Pemisah Plywood Rangkap Rangka Kayu Kelas II Rp 220,544.50
Pemasangan 1 M' Listplank Ukuran ( 3x20 ) cm , Kayu Kelas II Rp 53,753.92
Pemasangan 1 M' Listplank Ukuran ( 3x30 ) Kayu Kelas II Rp 53,354.40
3 4
Pengecatan 1 M2 Permukaan Baja Dengan Menie Besi Rp 24,044.35
Pengecatan 1 M2 Permukaan Baja Galvanis secara semprot Sistem 3 Lapis Cat Mutakhir Rp 86,295.00
A TENAGA
Pekerja L.01 OH 0.1000 Rp 67,900.00 Rp 6,790.00
Operator OH 0.1034 Rp 83,200.00 Rp 8,602.88
Mandor L.04 OH 0.0500 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 19,892.88
B BAHAN
Jump Piller Driver + Hammer Jam 0.050 787,500.00 Rp 39,375.00
JUMLAH HARGA BAHAN Rp 39,375.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 59,267.88
E Overhead & Profit ( 10 % ) 10% x D Rp 5,926.79
F Harga Satuan Pekerjaan (D+E) Rp 65,194.67
A TENAGA
Pekerja L.01 OH 0.7500 Rp 67,900.00 Rp 50,925.00
Mandor L.04 OH 0.0375 Rp 90,000.00 Rp 3,375.00
JUMLAH TENAGA KERJA Rp 54,300.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 54,300.00
E Overhead & Profit ( 10 % ) 10% x D Rp 5,430.00
F Harga Satuan Pekerjaan (D+E) Rp 59,730.00
IV. PEKERJAAN BETON
1 Membuat 1 M3 beton mutu f'c = 7,4 Mpa ( K 100 ), slump ( 12 ± 2 ) cm, w/c = 0,87
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 247.000 Rp 1,650.00 Rp 407,550.00
Pasir beton M3 0.621 Rp 142,800.00 Rp 88,638.00
Kerikil ( Maks 30 MM ) Kg 0.555 Rp 198,500.00 Rp 110,167.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 617,105.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 761,954.50
E Overhead & Profit ( 10 % ) 10% x D Rp 76,195.45
F Harga Satuan Pekerjaan (D+E) Rp 838,149.95
2 Membuat 1 M3 beton mutu f'c = 9,8 Mpa ( K 125 ), slump ( 12 ± 2 ) cm, w/c = 0,78
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 276.000 Rp 1,650.00 Rp 455,400.00
Pasir beton M3 0.591 Rp 142,800.00 Rp 84,456.00
Kerikil ( Maks 30 MM ) M3 0.749 Rp 198,500.00 Rp 148,676.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 699,282.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 844,131.50
E Overhead & Profit ( 10 % ) 10% x D Rp 84,413.15
F Harga Satuan Pekerjaan (D+E) Rp 928,544.65
3 Membuat 1 M3 beton mutu f'c = 12,2 Mpa ( K 150 ), slump ( 12 ± 2 ) cm, w/c = 0,72
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 299.000 Rp 1,650.00 Rp 493,350.00
Pasir beton M3 0.571 Rp 142,800.00 Rp 81,498.00
Kerikil ( Maks 30 MM ) M3 0.753 Rp 198,500.00 Rp 149,470.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 735,068.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 879,917.50
E Overhead & Profit ( 10 % ) 10% x D Rp 87,991.75
F Harga Satuan Pekerjaan (D+E) Rp 967,909.25
4 Membuat 1 M3 lantai kerja beton mutu f'c = 7,4 Mpa ( K 100 ), slump ( 3 - 6 ) cm, w/c = 0,87
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.200 Rp 67,900.00 Rp 81,480.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.060 Rp 90,000.00 Rp 5,400.00
JUMLAH TENAGA KERJA Rp 105,280.00
B BAHAN
Semen Portland Kg 230.000 Rp 1,650.00 Rp 379,500.00
Pasir beton M3 0.638 Rp 142,800.00 Rp 91,086.00
Kerikil ( Maks 30 MM ) M3 0.760 Rp 198,500.00 Rp 150,860.00
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 632,196.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 737,476.00
E Overhead & Profit ( 10 % ) 10% x D Rp 73,747.60
F Harga Satuan Pekerjaan (D+E) Rp 811,223.60
5 Membuat 1 M3 beton mutu f'c = 14,5 Mpa ( K 175 ), slump ( 12 ± 2 ) cm, w/c = 0,66
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 326.000 Rp 1,650.00 Rp 537,900.00
Pasir beton M3 0.543 Rp 142,800.00 Rp 77,520.00
Kerikil ( Maks 30 MM ) M3 0.762 Rp 198,500.00 Rp 151,257.00
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 777,427.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 922,276.00
E Overhead & Profit ( 10 % ) 10% x D Rp 92,227.60
F Harga Satuan Pekerjaan (D+E) Rp 1,014,503.60
6 Membuat 1 M3 beton mutu f'c = 16,9 Mpa ( K 200 ), slump ( 12 ± 2 ) cm, w/c = 0,61
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 352.000 Rp 1,650.00 Rp 580,800.00
Pasir beton M3 0.522 Rp 142,800.00 Rp 74,562.00
Kerikil ( Maks 30 MM ) M3 0.763 Rp 198,500.00 Rp 151,455.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 817,567.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 962,416.50
E Overhead & Profit ( 10 % ) 10% x D Rp 96,241.65
F Harga Satuan Pekerjaan (D+E) Rp 1,058,658.15
7 Membuat 1 M3 beton mutu f'c = 19,3 Mpa ( K 225 ), slump ( 12 ± 2 ) cm, w/c = 0,58
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 371.000 Rp 1,650.00 Rp 612,150.00
Pasir beton M3 0.499 Rp 142,800.00 Rp 71,196.00
Kerikil ( Maks 30 MM ) M3 0.775 Rp 198,500.00 Rp 153,837.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 847,933.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 992,782.50
E Overhead & Profit ( 10 % ) 10% x D Rp 99,278.25
F Harga Satuan Pekerjaan (D+E) Rp 1,092,060.75
8 Membuat 1 M3 beton mutu f'c = 21,7 Mpa ( K 250 ), slump ( 12 ± 2 ) cm, w/c = 0,56
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 384.000 Rp 1,650.00 Rp 633,600.00
Pasir beton M3 0.494 Rp 142,800.00 Rp 70,584.00
Kerikil ( Maks 30 MM ) M3 0.769 Rp 198,500.00 Rp 152,646.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 867,580.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,012,429.50
E Overhead & Profit ( 10 % ) 10% x D Rp 101,242.95
F Harga Satuan Pekerjaan (D+E) Rp 1,113,672.45
9 Membuat 1 M3 beton mutu f'c = 24 Mpa ( K 275 ), slump ( 12 ± 2 ) cm, w/c = 0,53
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 406.000 Rp 1,650.00 Rp 669,900.00
Pasir beton M3 0.489 Rp 142,800.00 Rp 69,768.00
Kerikil ( Maks 30 MM ) M3 0.760 Rp 198,500.00 Rp 150,860.00
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 901,278.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,046,127.00
E Overhead & Profit ( 10 % ) 10% x D Rp 104,612.70
F Harga Satuan Pekerjaan (D+E) Rp 1,150,739.70
10 Membuat 1 M3 beton mutu f'c = 26,4 Mpa ( K 300 ), slump ( 12 ± 2 ) cm, w/c = 0,52
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 413 Rp 1,650.00 Rp 681,450.00
Pasir beton M3 0.486 Rp 142,800.00 Rp 69,462.00
Kerikil ( Maks 30 MM ) M3 0.756 Rp 198,500.00 Rp 150,066.00
Air Liter 215 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 911,728.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,056,577.00
E Overhead & Profit ( 10 % ) 10% x D Rp 105,657.70
F Harga Satuan Pekerjaan (D+E) Rp 1,162,234.70
11 Membuat 1 M3 beton mutu f'c = 28,8 Mpa ( K 325 ), slump ( 12 ± 2 ) cm, w/c = 0,49
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 2.100 Rp 67,900.00 Rp 142,590.00
Tukang Batu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.105 Rp 90,000.00 Rp 9,450.00
JUMLAH TENAGA KERJA Rp 184,240.00
B BAHAN
Semen Portland Kg 439.000 Rp 1,650.00 Rp 724,350.00
Pasir beton M3 0.479 Rp 142,800.00 Rp 68,340.00
Kerikil ( Maks 30 MM ) M3 0.745 Rp 198,500.00 Rp 147,882.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 951,322.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,135,562.50
E Overhead & Profit ( 10 % ) 10% x D Rp 113,556.25
F Harga Satuan Pekerjaan (D+E) Rp 1,249,118.75
12 Membuat 1 M3 beton mutu f'c = 31,2 Mpa ( K 350 ), slump ( 12 ± 2 ) cm, w/c = 0,48
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 2.100 Rp 67,900.00 Rp 142,590.00
Tukang Batu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.105 Rp 90,000.00 Rp 9,450.00
JUMLAH TENAGA KERJA Rp 184,240.00
B BAHAN
Semen Portland Kg 448.000 Rp 1,650.00 Rp 739,200.00
Pasir beton M3 0.476 Rp 142,800.00 Rp 68,034.00
Kerikil ( Maks 30 MM ) M3 0.740 Rp 198,500.00 Rp 146,890.00
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 964,874.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,149,114.00
E Overhead & Profit ( 10 % ) 10% x D Rp 114,911.40
F Harga Satuan Pekerjaan (D+E) Rp 1,264,025.40
A TENAGA
Pekerja L.01 OH 0.070 Rp 67,900.00 Rp 4,753.00
Tukang Besi L.02 OH 0.070 Rp 83,200.00 Rp 5,824.00
Kepala Tukang L.03 OH 0.007 Rp 88,000.00 Rp 616.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 11,553.00
B BAHAN
Besi beton Ulir U-39 Kg 10.500 Rp 20,200.00 Rp 212,100.00
Kawat Beton Kg 0.150 Rp 18,150.00 Rp 2,722.50
JUMLAH HARGA BAHAN Rp 214,822.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 226,375.50
E Overhead & Profit ( 10 % ) 10% x D Rp 22,637.55
F Harga Satuan Pekerjaan (D+E) Rp 249,013.05
23 Pemasangan 1 M3 pondasi beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.200 Rp 1,809,000.00 Rp 361,800.00
Paku 5 cm - 12 cm Kg 1.500 Rp 15,300.00 Rp 22,950.00
Minyak Bekisting Liter 0.400 Rp 4,900.00 Rp 1,960.00
Besi Beton Polos Kg 157.500 Rp 9,200.00 Rp 1,449,000.00
Kawat Beton Kg 2.250 Rp 18,150.00 Rp 40,837.50
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
JUMLAH HARGA BAHAN Rp 2,668,844.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 3,294,020.50
E Overhead & Profit ( 10 % ) 10% x D Rp 329,402.05
F Harga Satuan Pekerjaan (D+E) Rp 3,623,422.55
24 Pemasangan 1 M3 pondasi beton Camp. 1 PC : 2 Psr : 3 Krk ( termasuk bekisting )
A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.200 Rp 1,809,000.00 Rp 361,800.00
Paku 5 cm - 12 cm Kg 1.500 Rp 15,300.00 Rp 22,950.00
Minyak Bekisting Liter 0.400 Rp 4,900.00 Rp 1,960.00
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
JUMLAH HARGA BAHAN Rp 1,179,007.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,804,183.00
E Overhead & Profit ( 10 % ) 10% x D Rp 180,418.30
F Harga Satuan Pekerjaan (D+E) Rp 1,984,601.30
25 Membuat 1 M3 sloof beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.650 Rp 67,900.00 Rp 383,635.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.560 Rp 83,200.00 Rp 129,792.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.323 Rp 88,000.00 Rp 28,424.00
Mandor L.04 OH 0.283 Rp 90,000.00 Rp 25,470.00
JUMLAH TENAGA KERJA Rp 706,681.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.270 Rp 1,809,000.00 Rp 488,430.00
Paku 5 cm - 12 cm Kg 2.000 Rp 15,300.00 Rp 30,600.00
Minyak Bekisting Liter 0.600 Rp 4,900.00 Rp 2,940.00
Besi Beton Polos Kg 210.000 Rp 9,200.00 Rp 1,932,000.00
Kawat Beton Kg 3.000 Rp 18,150.00 Rp 54,450.00
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
JUMLAH HARGA BAHAN Rp 3,300,717.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,007,398.00
E Overhead & Profit ( 10 % ) 10% x D Rp 400,739.80
F Harga Satuan Pekerjaan (D+E) Rp 4,408,137.80
26 Membuat 1 M3 sloof beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting )
A TENAGA
Pekerja L.01 OH 5.650 Rp 67,900.00 Rp 383,635.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.560 Rp 83,200.00 Rp 129,792.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.323 Rp 88,000.00 Rp 28,424.00
Mandor L.04 OH 0.283 Rp 90,000.00 Rp 25,470.00
JUMLAH TENAGA KERJA Rp 706,681.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.270 Rp 1,809,000.00 Rp 488,430.00
Paku 5 cm - 12 cm Kg 2.000 Rp 15,300.00 Rp 30,600.00
Minyak Bekisting Liter 0.600 Rp 4,900.00 Rp 2,940.00
Besi Beton Polos Kg 157.500 Rp 9,200.00 Rp 1,449,000.00
Kawat Beton Kg 2.250 Rp 18,150.00 Rp 40,837.50
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
JUMLAH HARGA BAHAN Rp 2,804,104.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 3,510,785.50
E Overhead & Profit ( 10 % ) 10% x D Rp 351,078.55
F Harga Satuan Pekerjaan (D+E) Rp 3,861,864.05
27 Membuat 1 M3 kolom beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 7.050 Rp 67,900.00 Rp 478,695.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.650 Rp 83,200.00 Rp 137,280.00
Tukang Besi L.02 OH 2.100 Rp 83,200.00 Rp 174,720.00
Kepala Tukang L.03 OH 0.403 Rp 88,000.00 Rp 35,464.00
Mandor L.04 OH 0.353 Rp 90,000.00 Rp 31,770.00
JUMLAH TENAGA KERJA Rp 880,809.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.400 Rp 1,809,000.00 Rp 723,600.00
Paku 5 cm - 12 cm Kg 4.000 Rp 15,300.00 Rp 61,200.00
Minyak Bekisting Liter 2.000 Rp 4,900.00 Rp 9,800.00
Besi Beton Polos Kg 210.000 Rp 9,200.00 Rp 1,932,000.00
Kawat Beton Kg 4.500 Rp 18,150.00 Rp 81,675.00
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
Kayu Kelas II Balok M3 0.150 Rp 2,009,000.00 Rp 301,350.00
Plywood 9 mm Lbr 3.500 Rp 146,650.00 Rp 513,275.00
Dolken Kayu Ø ( 8 cm - 10 cm ) Batang 20.000 Rp 7,650.00 Rp 153,000.00
panjang 4 meter
JUMLAH HARGA BAHAN Rp 4,568,197.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 5,449,006.00
E Overhead & Profit ( 10 % ) 10% x D Rp 544,900.60
F Harga Satuan Pekerjaan (D+E) Rp 5,993,906.60
28 Membuat 1 M3 kolom beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting )
A TENAGA
Pekerja L.01 OH 7.050 Rp 67,900.00 Rp 478,695.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.650 Rp 83,200.00 Rp 137,280.00
Tukang Besi L.02 OH 2.100 Rp 83,200.00 Rp 174,720.00
Kepala Tukang L.03 OH 0.403 Rp 88,000.00 Rp 35,464.00
Mandor L.04 OH 0.353 Rp 90,000.00 Rp 31,770.00
JUMLAH TENAGA KERJA Rp 880,809.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.400 Rp 1,809,000.00 Rp 723,600.00
Paku 5 cm - 12 cm Kg 4.000 Rp 15,300.00 Rp 61,200.00
Minyak Bekisting Liter 2.000 Rp 4,900.00 Rp 9,800.00
Besi Beton Polos Kg 157.500 Rp 9,200.00 Rp 1,449,000.00
Kawat Beton Kg 2.250 Rp 18,150.00 Rp 40,837.50
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
Kayu Kelas II Balok M3 0.150 Rp 2,009,000.00 Rp 301,350.00
Plywood 9 mm Lbr 3.500 Rp 146,650.00 Rp 513,275.00
Dolken Kayu Ø ( 8 cm - 10 cm ) Batang 20.000 Rp 7,650.00 Rp 153,000.00
panjang 4 meter
JUMLAH HARGA BAHAN Rp 4,044,359.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,925,168.50
E Overhead & Profit ( 10 % ) 10% x D Rp 492,516.85
F Harga Satuan Pekerjaan (D+E) Rp 5,417,685.35
29 Membuat 1 M3 balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 6.350 Rp 67,900.00 Rp 431,165.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.650 Rp 83,200.00 Rp 137,280.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.333 Rp 88,000.00 Rp 29,304.00
Mandor L.04 OH 0.318 Rp 90,000.00 Rp 28,620.00
JUMLAH TENAGA KERJA Rp 765,729.00
B BAHAN
Kayu Kelas III M3 0.320 Rp 1,809,000.00 Rp 578,880.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,300.00 Rp 48,960.00
Minyak Bekisting Liter 1.600 Rp 4,900.00 Rp 7,840.00
Besi Beton Polos Kg 210.000 Rp 9,200.00 Rp 1,932,000.00
Kawat Beton Kg 3.000 Rp 18,150.00 Rp 54,450.00
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
Kayu Kelas II Balok M3 0.140 Rp 2,009,000.00 Rp 281,260.00
Plywood 9 mm Lembar 2.800 Rp 146,650.00 Rp 410,620.00
30 Membuat 1 M3 balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting )
A TENAGA
Pekerja L.01 OH 6.350 Rp 67,900.00 Rp 431,165.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.650 Rp 83,200.00 Rp 137,280.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.333 Rp 88,000.00 Rp 29,304.00
Mandor L.04 OH 0.318 Rp 90,000.00 Rp 28,620.00
JUMLAH TENAGA KERJA Rp 765,729.00
B BAHAN
Kayu Kelas III M3 0.320 Rp 1,809,000.00 Rp 578,880.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,300.00 Rp 48,960.00
Minyak Bekisting Liter 1.600 Rp 4,900.00 Rp 7,840.00
Besi Beton Polos Kg 157.500 Rp 9,200.00 Rp 1,449,000.00
Kawat Beton Kg 2.250 Rp 18,150.00 Rp 40,837.50
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
Kayu Kelas II Balok M3 0.140 Rp 2,009,000.00 Rp 281,260.00
Plywood 9 mm Lembar 2.800 Rp 146,650.00 Rp 410,620.00
Dolken Kayu Ø ( 8 cm - 10 cm ) Batang 16.000 Rp 7,650.00 Rp 122,400.00
panjang 4 meter
JUMLAH HARGA BAHAN Rp 3,732,094.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,497,823.50
E Overhead & Profit ( 10 % ) 10% x D Rp 449,782.35
F Harga Satuan Pekerjaan (D+E) Rp 4,947,605.85
31 Membuat 1 M3 pelat beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.265 Rp 88,000.00 Rp 23,320.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,440.00
B BAHAN
Kayu Kelas III M3 0.320 Rp 1,809,000.00 Rp 578,880.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,300.00 Rp 48,960.00
Minyak Bekisting Liter 1.600 Rp 4,900.00 Rp 7,840.00
Besi Beton Polos Kg 157.500 Rp 9,200.00 Rp 1,449,000.00
Kawat Beton Kg 2.250 Rp 18,150.00 Rp 40,837.50
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
Kayu Kelas II Balok M3 0.120 Rp 2,009,000.00 Rp 241,080.00
Plywood 9 mm Lembar 2.800 Rp 146,650.00 Rp 410,620.00
32 Membuat 1 M3 dinding beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III M3 0.240 Rp 1,809,000.00 Rp 434,160.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,300.00 Rp 48,960.00
Minyak Bekisting Liter 1.600 Rp 4,900.00 Rp 7,840.00
Besi Beton Polos Kg 157.500 Rp 9,200.00 Rp 1,449,000.00
Kawat Beton Kg 2.250 Rp 18,150.00 Rp 40,837.50
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
Kayu Kelas II Balok M3 0.160 Rp 2,009,000.00 Rp 321,440.00
Plywood 9 mm Lembar 2.800 Rp 146,650.00 Rp 410,620.00
33 Membuat 1 M3 dinding beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.650 Rp 67,900.00 Rp 383,635.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.560 Rp 83,200.00 Rp 129,792.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.323 Rp 88,000.00 Rp 28,424.00
Mandor L.04 OH 0.283 Rp 90,000.00 Rp 25,470.00
JUMLAH TENAGA KERJA Rp 706,681.00
B BAHAN
Kayu Kelas III M3 0.250 Rp 1,809,000.00 Rp 452,250.00
Paku 5 cm - 12 cm Kg 3.000 Rp 15,300.00 Rp 45,900.00
Minyak Bekisting Liter 1.200 Rp 4,900.00 Rp 5,880.00
Besi Beton Polos Kg 210.000 Rp 9,200.00 Rp 1,932,000.00
Kawat Beton Kg 3.000 Rp 18,150.00 Rp 54,450.00
Semen Portland Kg 336.000 Rp 1,650.00 Rp 554,400.00
Pasir Beton M3 0.540 Rp 142,800.00 Rp 77,112.00
Kerikil M3 0.810 Rp 198,500.00 Rp 160,785.00
Kayu Kelas II Balok M3 0.105 Rp 2,009,000.00 Rp 210,945.00
Plywood 9 mm Lembar 2.500 Rp 146,650.00 Rp 366,625.00
Dolken Kayu Ø ( 8 cm - 10 cm ) Rp 107,100.00
panjang 4 meter Batang 14.000 Rp 7,650.00
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 4.500 Rp 67,900.00 Rp 305,550.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 0.260 Rp 83,200.00 Rp 21,632.00
Kepala Tukang L.04 OH 0.423 Rp 88,000.00 Rp 37,224.00
Mandor L.05 OH 0.580 Rp 90,000.00 Rp 52,200.00
JUMLAH TENAGA KERJA Rp 439,486.00
B BAHAN
Balok Kayu Kelas II Uk. 4/6 CM M3 0.019 2,009,000.00 Rp 38,572.80
Paku 5 Cm - 12 Cm KG 0.250 15,300.00 Rp 3,825.00
Papan Kayu Kelas II Uk. 2 x 20 CM M3 0.032 2,009,000.00 Rp 64,288.00
Semen Portland KG 326.000 Rp 1,650.00 Rp 537,900.00
Pasir Beton M3 0.543 Rp 142,800.00 Rp 77,540.40
Kerikil M3 0.762 Rp 198,500.00 Rp 151,257.00
Air LTR 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 884,133.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,323,619.20
E Overhead & Profit ( 10 % ) 10% x D Rp 132,361.92
F Harga Satuan Pekerjaan (D+E) Rp 1,455,981.12
37 Membuat 1 M3 Dinding dan Lantai Drainase Beton Bertulang Mutu K-175 ( 60 Kg Besi )
A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III M3 0.133 Rp 1,809,000.00 Rp 240,597.00
Paku 5 cm - 12 cm Kg 1.330 Rp 15,300.00 Rp 20,349.00
Minyak Bekisting Liter 1.200 Rp 4,900.00 Rp 5,880.00
Besi Beton Polos Kg 60.000 Rp 9,200.00 Rp 552,000.00
Kawat Beton Kg 1.000 Rp 18,150.00 Rp 18,150.00
Semen Portland Kg 326.000 Rp 1,650.00 Rp 537,900.00
Pasir Beton M3 0.543 Rp 142,800.00 Rp 77,540.40
Kerikil M3 0.762 Rp 198,500.00 Rp 151,257.00
Air Liter 215.000 Rp 50.00 Rp 10,750.00
Plywood 9 mm Lembar 0.800 Rp 146,650.00 Rp 117,320.00
Dolken Kayu Ø ( 8 cm - 10 cm )
Batang 8.000 Rp 7,650.00 Rp 61,200.00
panjang 4 meter
JUMLAH HARGA BAHAN Rp 1,792,943.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 2,418,119.40
E Overhead & Profit ( 10 % ) 10% x D Rp 241,811.94
F Harga Satuan Pekerjaan (D+E) Rp 2,659,931.34
A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III M3 0.240 Rp 1,809,000.00 Rp 434,160.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,300.00 Rp 48,960.00
Besi Beton Polos Kg 160.00 Rp 9,200.00 Rp 1,472,000.00
Kawat Beton Kg 2.000 Rp 18,150.00 Rp 36,300.00
Semen Portland Kg 326.000 Rp 1,650.00 Rp 537,900.00
Pasir Beton M3 0.543 Rp 142,800.00 Rp 77,540.40
Kerikil M3 0.762 Rp 198,500.00 Rp 151,257.00
Air Liter 215.000 Rp 50.00 Rp 10,750.00
Plywood 9 mm Lembar 2.800 Rp 146,650.00 Rp 410,620.00
Dolken Kayu Ø ( 8 cm - 10 cm )
panjang 4 meter Batang 4.000 Rp 7,650.00 Rp 30,600.00
JUMLAH HARGA BAHAN Rp 3,210,087.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 3,835,263.40
E Overhead & Profit ( 10 % ) 10% x D Rp 383,526.34
F Harga Satuan Pekerjaan (D+E) Rp 4,218,789.74
A TENAGA
Pekerja L.01 OH 0.043 Rp 67,900.00 Rp 2,919.70
Tukang Khusus Aluminium L.03 OH 0.043 Rp 83,200.00 Rp 3,577.60
Kepala Tukang L.03 OH 0.0043 Rp 88,000.00 Rp 378.40
Mandor L.04 OH 0.0021 Rp 90,000.00 Rp 189.00
JUMLAH TENAGA KERJA Rp 7,064.70
B BAHAN
Profil Aluminium M2 1.100 Rp 25,050.00 Rp 27,555.00
Skrup Fixer Buah 2.000 Rp 400.00 Rp 800.00
Sealent Tube 0.060 Rp 12,550.00 Rp 753.00
JUMLAH HARGA BAHAN Rp 29,108.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 36,172.70
E Overhead & Profit ( 10 % ) 10% x D Rp 3,617.27
F Harga Satuan Pekerjaan (D+E) Rp 39,789.97
A TENAGA
Pekerja L.01 OH 0.350 Rp 67,900.00 Rp 23,765.00
Tukang L.03 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.018 Rp 90,000.00 Rp 1,620.00
JUMLAH TENAGA KERJA Rp 57,585.00
B BAHAN
Venetions Blind dan Vertical Blinds
( Tirai ) M 1.000 Rp 100,200.00 Rp 100,200.00
JUMLAH HARGA BAHAN Rp 100,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 157,785.00
E Overhead & Profit ( 10 % ) 10% x D Rp 15,778.50
F Harga Satuan Pekerjaan (D+E) Rp 173,563.50
VI. PEKERJAAN PASANGAN DINDING
A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata Merah Buah 140.000 Rp 650.00 Rp 91,000.00
Semen Protland Kg 32.950 Rp 1,650.00 Rp 54,367.50
Pasir Pasang M3 0.091 Rp 142,800.00 Rp 12,994.80
JUMLAH HARGA BAHAN Rp 158,362.30
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 220,202.30
E Overhead & Profit ( 10 % ) 10% x D Rp 22,020.23
F Harga Satuan Pekerjaan (D+E) Rp 242,222.53
3 Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:4PP
A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata Merah Buah 140.000 Rp 650.00 Rp 91,000.00
Semen Protland Kg 26.550 Rp 1,650.00 Rp 43,807.50
Pasir Pasang M3 0.093 Rp 142,800.00 Rp 13,280.40
JUMLAH HARGA BAHAN Rp 148,087.90
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 209,927.90
E Overhead & Profit ( 10 % ) 10% x D Rp 20,992.79
F Harga Satuan Pekerjaan (D+E) Rp 230,920.69
A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata Merah Buah 140.000 Rp 650.00 Rp 91,000.00
Semen Protland Kg 22.200 Rp 1,650.00 Rp 36,630.00
Pasir Pasang M3 0.102 Rp 142,800.00 Rp 14,565.60
JUMLAH HARGA BAHAN Rp 142,195.60
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 204,035.60
E Overhead & Profit ( 10 % ) 10% x D Rp 20,403.56
F Harga Satuan Pekerjaan (D+E) Rp 224,439.16
A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata Merah Buah 140.000 Rp 650.00 Rp 91,000.00
Semen Protland Kg 18.500 Rp 1,650.00 Rp 30,525.00
Pasir Pasang M3 0.122 Rp 142,800.00 Rp 17,421.60
JUMLAH HARGA BAHAN Rp 138,946.60
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 200,786.60
E Overhead & Profit ( 10 % ) 10% x D Rp 20,078.66
F Harga Satuan Pekerjaan (D+E) Rp 220,865.26
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 650.00 Rp 45,500.00
Semen Protland Kg 18.950 Rp 1,650.00 Rp 31,267.50
Pasir Pasang M3 0.038 Rp 142,800.00 Rp 5,426.40
JUMLAH HARGA BAHAN Rp 82,193.90
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 113,113.90
E Overhead & Profit ( 10 % ) 10% x D Rp 11,311.39
F Harga Satuan Pekerjaan (D+E) Rp 124,425.29
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 650.00 Rp 45,500.00
Semen Protland Kg 14.370 Rp 1,650.00 Rp 23,710.50
Pasir Pasang M3 0.040 Rp 142,800.00 Rp 5,712.00
JUMLAH HARGA BAHAN Rp 74,922.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 105,842.50
E Overhead & Profit ( 10 % ) 10% x D Rp 10,584.25
F Harga Satuan Pekerjaan (D+E) Rp 116,426.75
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 650.00 Rp 45,500.00
Semen Protland Kg 11.500 Rp 1,650.00 Rp 18,975.00
Pasir Pasang M3 0.043 Rp 142,800.00 Rp 6,140.40
JUMLAH HARGA BAHAN Rp 70,615.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 101,535.40
E Overhead & Profit ( 10 % ) 10% x D Rp 10,153.54
F Harga Satuan Pekerjaan (D+E) Rp 111,688.94
9 Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:5PP
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 650.00 Rp 45,500.00
Semen Protland Kg 9.680 Rp 1,650.00 Rp 15,972.00
Pasir Pasang M3 0.045 Rp 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 67,898.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 98,818.00
E Overhead & Profit ( 10 % ) 10% x D Rp 9,881.80
F Harga Satuan Pekerjaan (D+E) Rp 108,699.80
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 650.00 Rp 45,500.00
Semen Portland Kg 8.320 Rp 1,650.00 Rp 13,728.00
Pasir Pasang M3 0.049 Rp 142,800.00 Rp 6,997.20
JUMLAH HARGA BAHAN Rp 66,225.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 97,145.20
E Overhead & Profit ( 10 % ) 10% x D Rp 9,714.52
F Harga Satuan Pekerjaan (D+E) Rp 106,859.72
VII. PEKERJAAN PLESTERAN
16 Pemasangan 1 M2 Acian
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.200 Rp 67,900.00 Rp 13,580.00
Tukang Batu L.03 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.010 Rp 90,000.00 Rp 900.00
JUMLAH TENAGA KERJA Rp 23,680.00
B BAHAN
Portland Cement Kg 3.250 1,650.00 Rp 5,362.50
JUMLAH HARGA BAHAN Rp 5,362.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 29,042.50
E Overhead & Profit ( 10 % ) 10% x D Rp 2,904.25
F Harga Satuan Pekerjaan (D+E) Rp 31,946.75
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Batu L.03 OH 0.075 Rp 83,200.00 Rp 6,240.00
Kepala Tukang L.03 OH 0.008 Rp 88,000.00 Rp 704.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 17,849.00
B BAHAN
Portland Cement Kg 3.108 1,650.00 Rp 5,128.20
JUMLAH HARGA BAHAN Rp 5,128.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 22,977.20
E Overhead & Profit ( 10 % ) 10% x D Rp 2,297.72
F Harga Satuan Pekerjaan (D+E) Rp 25,274.92
VIII. PEKERJAAN PENUTUP LANTAI & PENUTUP DINDING
A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Batu L.02 OH 0.125 Rp 83,200.00 Rp 10,400.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 29,689.00
B BAHAN
Ubin abu-abu Uk. 30 x 30 cm Buah 11.870 4,650.00 Rp 55,195.50
Semen portland Kg 10.000 1,650.00 Rp 16,500.00
Pasir Pasang M3 0.045 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 78,121.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 107,810.50
E Overhead & Profit ( 10 % ) 10% x D Rp 10,781.05
F Harga Satuan Pekerjaan (D+E) Rp 118,591.55
3 Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20x20
A TENAGA
Pekerja L.01 OH 0.270 Rp 67,900.00 Rp 18,333.00
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.014 Rp 88,000.00 Rp 1,232.00
Mandor L.04 OH 0.014 Rp 90,000.00 Rp 1,260.00
JUMLAH TENAGA KERJA Rp 32,057.00
B BAHAN
Ubin abu-abu Uk. 20 x 20 cm Bh 26.500 Rp 2,350.00 Rp 62,275.00
Semen portland Kg 10.400 Rp 1,650.00 Rp 17,160.00
Pasir Pasang M 3
0.045 Rp 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 85,861.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 117,918.00
E Overhead & Profit ( 10 % ) 10% x D Rp 11,791.80
F Harga Satuan Pekerjaan (D+E) Rp 129,709.80
A TENAGA
Pekerja L.01 OH 0.240 Rp 67,900.00 Rp 16,296.00
Tukang Batu L.02 OH 0.120 Rp 83,200.00 Rp 9,984.00
Kepala Tukang L.03 OH 0.012 Rp 88,000.00 Rp 1,056.00
Mandor L.04 OH 0.012 Rp 90,000.00 Rp 1,080.00
JUMLAH TENAGA KERJA Rp 28,416.00
B BAHAN
Homogenius Uk. 60 x 60 cm Bh 3.100 Rp 60,150.00 Rp 186,465.00
Semen portland Kg 9.600 Rp 1,650.00 Rp 15,840.00
Semen warna Kg 1.500 Rp 2,450.00 Rp 3,675.00
Pasir Pasang M3 0.045 Rp 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 212,406.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 240,822.00
E Overhead & Profit ( 10 % ) 10% x D Rp 24,082.20
F Harga Satuan Pekerjaan (D+E) Rp 264,904.20
A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Batu L.02 OH 0.125 Rp 83,200.00 Rp 10,400.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 29,689.00
B BAHAN
Homogenius Uk.40 x 40 cm Bh 6.630 Rp 32,050.00 Rp 212,491.50
Semen portland Kg 9.800 Rp 1,650.00 Rp 16,170.00
Semen warna Kg 1.300 Rp 2,450.00 Rp 3,185.00
Pasir Pasang M3 0.045 Rp 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 238,272.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 267,961.50
E Overhead & Profit ( 10 % ) 10% x D Rp 26,796.15
F Harga Satuan Pekerjaan (D+E) Rp 294,757.65
6 Pemasangan 1 M2 Lantai Homogenius Uk. 30/30
A TENAGA
Pekerja L.01 OH 0.260 Rp 67,900.00 Rp 17,654.00
Tukang Batu L.02 OH 0.130 Rp 83,200.00 Rp 10,816.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 30,784.00
B BAHAN
Homogenius Uk. 30 x 30 cm Bh 11.870 Rp 15,850.00 Rp 188,139.50
Semen portland Kg 10.000 Rp 1,650.00 Rp 16,500.00
Semen warna Kg 1.500 Rp 2,450.00 Rp 3,675.00
Pasir Pasang M3 0.045 Rp 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 214,740.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 245,524.50
E Overhead & Profit ( 10 % ) 10% x D Rp 24,552.45
F Harga Satuan Pekerjaan (D+E) Rp 270,076.95
A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Batu L.02 OH 0.125 Rp 83,200.00 Rp 10,400.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 29,689.00
B BAHAN
Keramik warna Uk.40 x 40 cm Bh 6.630 Rp 9,650.00 Rp 63,979.50
Semen portland Kg 9.800 Rp 1,650.00 Rp 16,170.00
Semen warna Kg 1.300 Rp 2,450.00 Rp 3,185.00
Pasir Pasang M3 0.045 Rp 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 89,760.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 119,449.50
E Overhead & Profit ( 10 % ) 10% x D Rp 11,944.95
F Harga Satuan Pekerjaan (D+E) Rp 131,394.45
A TENAGA
Pekerja L.01 OH 0.260 Rp 67,900.00 Rp 17,654.00
Tukang Batu L.02 OH 0.130 Rp 83,200.00 Rp 10,816.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 30,784.00
B BAHAN
Keramik warna Uk. 30 x 30 cm Buah 11.870 Rp 5,125.00 Rp 60,833.75
Semen portland Kg 10.000 Rp 1,650.00 Rp 16,500.00
Semen warna Kg 1.500 Rp 2,450.00 Rp 3,675.00
Pasir Pasang M 3
0.045 Rp 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 87,434.75
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 118,218.75
E Overhead & Profit ( 10 % ) 10% x D Rp 11,821.88
F Harga Satuan Pekerjaan (D+E) Rp 130,040.63
9 Pemasangan 1 m2 lantai keramik warna ukuran 20x20
A TENAGA
Pekerja L.01 OH 0.270 Rp 67,900.00 Rp 18,333.00
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.014 Rp 88,000.00 Rp 1,232.00
Mandor L.04 OH 0.014 Rp 90,000.00 Rp 1,260.00
JUMLAH TENAGA KERJA Rp 32,057.00
B BAHAN
Keramik warna Uk. 20 x 20 cm Buah 26.500 Rp 2,525.00 Rp 66,912.50
Semen portland Kg 10.400 Rp 1,650.00 Rp 17,160.00
Semen warna Kg 1.620 Rp 2,450.00 Rp 3,969.00
Pasir Pasang M 3
0.045 Rp 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 94,467.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 126,524.50
E Overhead & Profit ( 10 % ) 10% x D Rp 12,652.45
F Harga Satuan Pekerjaan (D+E) Rp 139,176.95
A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Plint Keramik Warna Uk. 10 x 20 cm Buah 5.300 Rp 1,450.00 Rp 7,685.00
Semen portland Kg 1.140 Rp 1,650.00 Rp 1,881.00
Semen warna Kg 0.100 Rp 2,450.00 Rp 245.00
Pasir Pasang M3 0.003 Rp 142,800.00 Rp 428.40
JUMLAH HARGA BAHAN Rp 10,239.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 25,080.40
E Overhead & Profit ( 10 % ) 10% x D Rp 2,508.04
F Harga Satuan Pekerjaan (D+E) Rp 27,588.44
11 Pemasangan 1 m' plint keramik warna ukuran 10 x 30 cm
A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Keramik warna Uk. 10 x 30 cm Buah 3.530 Rp 2,450.00 Rp 8,648.50
Semen portland Kg 1.140 Rp 1,650.00 Rp 1,881.00
Semen warna Kg 0.100 Rp 2,450.00 Rp 245.00
Pasir Pasang M 3
0.003 Rp 142,800.00 Rp 428.40
JUMLAH HARGA BAHAN Rp 11,202.90
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 26,043.90
E Overhead & Profit ( 10 % ) 10% x D Rp 2,604.39
F Harga Satuan Pekerjaan (D+E) Rp 28,648.29
A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Keramik warna Uk. 10 x 40 cm Buah 2.650 Rp 3,350.00 Rp 8,877.50
Semen portland Kg 1.140 Rp 1,650.00 Rp 1,881.00
Semen warna Kg 0.100 Rp 2,450.00 Rp 245.00
Pasir Pasang M3 0.030 Rp 142,800.00 Rp 4,284.00
JUMLAH HARGA BAHAN Rp 15,287.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 30,128.50
E Overhead & Profit ( 10 % ) 10% x D Rp 3,012.85
F Harga Satuan Pekerjaan (D+E) Rp 33,141.35
A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Homogenius Uk. 10 x 60 cm M1 1.700 Rp 12,150.00 Rp 20,655.00
Semen portland Kg 1.140 Rp 1,650.00 Rp 1,881.00
Semen warna Kg 0.100 Rp 2,450.00 Rp 245.00
Pasir Pasang M3 0.003 Rp 142,800.00 Rp 428.40
JUMLAH HARGA BAHAN Rp 23,209.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 38,050.40
E Overhead & Profit ( 10 % ) 10% x D Rp 3,805.04
F Harga Satuan Pekerjaan (D+E) Rp 41,855.44
14 Pemasangan 1 m' plint homogenius warna ukuran 10 x 40 cm
A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Homogenius Uk. 10 x 40 cm M1 1.700 Rp 11,250.00 Rp 19,125.00
Semen portland Kg 1.140 Rp 1,650.00 Rp 1,881.00
Semen warna Kg 0.100 Rp 2,450.00 Rp 245.00
Pasir Pasang M3 0.030 Rp 142,800.00 Rp 4,284.00
JUMLAH HARGA BAHAN Rp 25,535.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 40,376.00
E Overhead & Profit ( 10 % ) 10% x D Rp 4,037.60
F Harga Satuan Pekerjaan (D+E) Rp 44,413.60
A TENAGA
Pekerja L.01 OH 0.270 Rp 67,900.00 Rp 18,333.00
Tukang Batu L.02 OH 0.130 Rp 83,200.00 Rp 10,816.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.014 Rp 90,000.00 Rp 1,260.00
JUMLAH TENAGA KERJA Rp 31,553.00
B BAHAN
Keramik warna Uk. 20 x 20 cm Buah 26.500 Rp 2,525.00 Rp 66,912.50
Semen portland Kg 9.300 Rp 1,650.00 Rp 15,345.00
Pasir pasang M3 0.018 Rp 142,800.00 Rp 2,570.40
Semen warna Kg 1.940 Rp 2,450.00 Rp 4,753.00
JUMLAH HARGA BAHAN Rp 89,580.90
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 121,133.90
E Overhead & Profit ( 10 % ) 10% x D Rp 12,113.39
F Harga Satuan Pekerjaan (D+E) Rp 133,247.29
A TENAGA
Pekerja L.01 OH 0.270 Rp 67,900.00 Rp 18,333.00
Tukang Batu L.02 OH 0.130 Rp 83,200.00 Rp 10,816.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.014 Rp 90,000.00 Rp 1,260.00
JUMLAH TENAGA KERJA Rp 31,553.00
B BAHAN
Keramik Uk. 20 x 25 cm Buah 21.500 Rp 2,950.00 Rp 63,425.00
Semen portland Kg 10.400 Rp 1,650.00 Rp 17,160.00
Semen warna Kg 1.620 Rp 2,450.00 Rp 3,969.00
Pasir Pasang M3 0.045 Rp 142,800.00 Rp 6,426.00
JUMLAH HARGA BAHAN Rp 90,980.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 122,533.00
E Overhead & Profit ( 10 % ) 10% x D Rp 12,253.30
F Harga Satuan Pekerjaan (D+E) Rp 134,786.30
17 Pemasangan 1 M2 Lantai Karpet
A TENAGA
Pekerja L.01 OH 0.170 Rp 67,900.00 Rp 11,543.00
Tukang Kayu L.02 OH 0.170 Rp 83,200.00 Rp 14,144.00
Kepala Tukang L.03 OH 0.017 Rp 88,000.00 Rp 1,496.00
Mandor L.04 OH 0.009 Rp 90,000.00 Rp 810.00
JUMLAH TENAGA KERJA Rp 27,993.00
B BAHAN
Karpet M2 1.050 Rp 18,500.00 Rp 19,425.00
Lem Kg 0.350 Rp 3,000.00 Rp 1,050.00
JUMLAH HARGA BAHAN Rp 20,475.00
C PERALATAN
JUMLAH HARGA ALAT Rp 48,468.00
D Jumlah (A+B+C) Rp 4,846.80
E Overhead & Profit ( 10 % ) 10% x D Rp 53,314.80
F Harga Satuan Pekerjaan (D+E) Rp 53,314.80
A TENAGA
Pekerja L.01 OH 0.700 Rp 67,900.00 Rp 47,530.00
Tukang Kayu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.035 Rp 90,000.00 Rp 3,150.00
JUMLAH TENAGA KERJA Rp 82,880.00
B BAHAN
Parquet M2 1.050 Rp 225,300.00 Rp 236,565.00
Lem Kg 0.600 Rp 3,000.00 Rp 1,800.00
JUMLAH HARGA BAHAN Rp 238,365.00
C PERALATAN
JUMLAH HARGA ALAT Rp 321,245.00
D Jumlah (A+B+C) Rp 32,124.50
E Overhead & Profit ( 10 % ) 10% x D Rp 353,369.50
F Harga Satuan Pekerjaan (D+E) Rp 353,369.50
19 Pemasangan 1 M2 Dinding Batu Tempel Uk. 20 X 20 CM
A TENAGA
Pekerja L.01 OH 0.700 Rp 67,900.00 Rp 47,530.00
Tukang Batu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.035 Rp 90,000.00 Rp 3,150.00
JUMLAH TENAGA KERJA Rp 82,880.00
B BAHAN
Batu Tempel Bh 26.500 Rp 5,300.00 Rp 140,450.00
Semen Portland Kg 11.750 Rp 1,650.00 Rp 19,387.50
Pasir Pasang M3 0.035 Rp 142,800.00 Rp 4,998.00
JUMLAH HARGA BAHAN Rp 164,835.50
C PERALATAN
JUMLAH HARGA ALAT Rp 247,715.50
D Jumlah (A+B+C) Rp 24,771.55
E Overhead & Profit ( 10 % ) 10% x D Rp 272,487.05
F Harga Satuan Pekerjaan (D+E) Rp 272,487.05
A TENAGA
Pekerja L.01 OH 0.700 Rp 67,900.00 Rp 47,530.00
Tukang Batu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.035 Rp 90,000.00 Rp 3,150.00
JUMLAH TENAGA KERJA Rp 82,880.00
B BAHAN
Batu Tempel Bh 13.500 Rp 12,800.00 Rp 172,800.00
Semen Portland Kg 11.750 Rp 1,650.00 Rp 19,387.50
Pasir Pasang M3 0.035 Rp 142,800.00 Rp 4,998.00
JUMLAH HARGA BAHAN Rp 197,185.50
C PERALATAN
JUMLAH HARGA ALAT Rp 280,065.50
D Jumlah (A+B+C) Rp 28,006.55
E Overhead & Profit ( 10 % ) 10% x D Rp 308,072.05
F Harga Satuan Pekerjaan (D+E) Rp 308,072.05
A TENAGA
Pekerja L.01 OH 0.350 Rp 67,900.00 Rp 23,765.00
Tukang Batu L.02 OH 0.175 Rp 83,200.00 Rp 14,560.00
Kepala Tukang L.03 OH 0.017 Rp 88,000.00 Rp 1,496.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 40,001.00
B BAHAN
Wallpaper M 2.200 Rp 66,250.00 Rp 145,750.00
Lem Kg 0.250 Rp 3,000.00 Rp 750.00
JUMLAH HARGA BAHAN Rp 146,500.00
C PERALATAN
JUMLAH HARGA ALAT Rp 186,501.00
D Jumlah (A+B+C) Rp 18,650.10
E Overhead & Profit ( 10 % ) 10% x D Rp 205,151.10
F Harga Satuan Pekerjaan (D+E) Rp 205,151.10
A TENAGA
Pekerja L.01 OH 0.120 Rp 67,900.00 Rp 8,148.00
Tukang Batu L.02 OH 0.120 Rp 83,200.00 Rp 9,984.00
Kepala Tukang L.03 OH 0.012 Rp 88,000.00 Rp 1,056.00
Mandor L.04 OH 0.006 Rp 90,000.00 Rp 540.00
JUMLAH TENAGA KERJA 19,728.000
B BAHAN
Papan Kayu Kelas 1 M3 0.003 Rp 3,609,000.00 Rp 10,827.00
Paku / Skrup 5 CM Kg 0.050 Rp 15,300.00 Rp 765.00
JUMLAH HARGA BAHAN Rp 11,592.00
C PERALATAN
JUMLAH HARGA ALAT Rp 31,320.00
D Jumlah (A+B+C) Rp 3,132.00
E Overhead & Profit ( 10 % ) 10% x D Rp 34,452.00
F Harga Satuan Pekerjaan (D+E) Rp 34,452.00
IX. PEKERJAAN PLAFOND
A TENAGA
Pekerja L.01 OH 0.800 Rp 67,900.00 Rp 54,320.00
Tukang Kayu L.02 OH 0.800 Rp 83,200.00 Rp 66,560.00
Kepala Tukang L.03 OH 0.080 Rp 88,000.00 Rp 7,040.00
Mandor L.04 OH 0.040 Rp 90,000.00 Rp 3,600.00
JUMLAH TENAGA KERJA Rp 131,520.00
B BAHAN
Kayu papan Kelas II M3 0.015 Rp 2,009,000.00 Rp 30,135.00
Paku tripleks Kg 0.010 Rp 15,300.00 Rp 153.00
JUMLAH HARGA BAHAN Rp 30,288.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 161,808.00
E Overhead & Profit ( 10 % ) 10% x D Rp 16,180.80
F Harga Satuan Pekerjaan (D+E) Rp 177,988.80
A TENAGA
Pekerja L.01 OH 0.100 Rp 67,900.00 Rp 6,790.00
Tukang Kayu L.02 OH 0.050 Rp 83,200.00 Rp 4,160.00
Kepala Tukang L.03 OH 0.005 Rp 88,000.00 Rp 440.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 11,840.00
B BAHAN
Gypsum board Lembar 0.364 Rp 87,200.00 Rp 31,740.80
Paku skrup Kg 0.110 Rp 40,300.00 Rp 4,433.00
JUMLAH HARGA BAHAN Rp 36,173.80
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 48,013.80
E Overhead & Profit ( 10 % ) 10% x D Rp 4,801.38
F Harga Satuan Pekerjaan (D+E) Rp 52,815.18
A TENAGA
Pekerja L.01 OH 0.050 Rp 67,900.00 Rp 3,395.00
Tukang Kayu L.02 OH 0.050 Rp 83,200.00 Rp 4,160.00
Kepala Tukang L.03 OH 0.005 Rp 88,000.00 Rp 440.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 8,265.00
B BAHAN
List kayu profil M 1.050 Rp 2,650.00 Rp 2,782.50
Paku Kg 0.010 Rp 15,300.00 Rp 153.00
JUMLAH HARGA BAHAN Rp 2,935.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 11,200.50
E Overhead & Profit ( 10 % ) 10% x D Rp 1,120.05
F Harga Satuan Pekerjaan (D+E) Rp 12,320.55
A TENAGA
Pekerja L.01 OH 0.230 Rp 67,900.00 Rp 15,617.00
Tukang Kayu L.02 OH 0.670 Rp 83,200.00 Rp 55,744.00
Kepala Tukang L.03 OH 0.067 Rp 88,000.00 Rp 5,896.00
Mandor L.04 OH 0.012 Rp 90,000.00 Rp 1,080.00
JUMLAH TENAGA KERJA Rp 78,337.00
B BAHAN
Papan Piri - Piri ( Siap Ketam ) M3 0.020 Rp 2,309,000.00 Rp 46,180.00
Paku Kg 0.200 Rp 15,300.00 Rp 3,060.00
JUMLAH HARGA BAHAN Rp 49,240.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 127,577.00
E Overhead & Profit ( 10 % ) 10% x D Rp 12,757.70
F Harga Satuan Pekerjaan (D+E) Rp 140,334.70
X. PEKERJAAN ATAP
A TENAGA
Pekerja L.01 OH 0.120 Rp 67,900.00 Rp 8,148.00
Tukang Kayu L.02 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.006 Rp 90,000.00 Rp 540.00
JUMLAH TENAGA KERJA Rp 14,208.00
B BAHAN
Seng gelombang Lembar 0.700 Rp 46,500.00 Rp 32,550.00
paku biasa 1/2"-1" Kg 0.020 Rp 15,300.00 Rp 306.00
JUMLAH HARGA BAHAN Rp 32,856.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 47,064.00
E Overhead & Profit ( 10 % ) 10% x D Rp 4,706.40
F Harga Satuan Pekerjaan (D+E) Rp 51,770.40
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Kayu L.02 OH 0.070 Rp 83,200.00 Rp 5,824.00
Kepala Tukang L.03 OH 0.007 Rp 88,000.00 Rp 616.00
Mandor L.04 OH 0.007 Rp 90,000.00 Rp 630.00
JUMLAH TENAGA KERJA Rp 17,255.00
B BAHAN
Seng plat Lembar 0.300 Rp 59,500.00 Rp 17,850.00
paku biasa 1/2"-1" Kg 0.040 Rp 15,300.00 Rp 612.00
JUMLAH HARGA BAHAN Rp 18,462.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 35,717.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,571.70
F Harga Satuan Pekerjaan (D+E) Rp 39,288.70
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Kayu L.02 OH 0.050 Rp 83,200.00 Rp 4,160.00
Kepala Tukang L.03 OH 0.005 Rp 88,000.00 Rp 440.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 15,505.00
B BAHAN
Aluminium foil M2 1.050 13,500.00 Rp 14,175.00
JUMLAH HARGA BAHAN Rp 14,175.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 29,680.00
E Overhead & Profit ( 10 % ) 10% x D Rp 2,968.00
F Harga Satuan Pekerjaan (D+E) Rp 32,648.00
A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 31,945.00
B BAHAN
Terpal Lebar 50 CM M1 1.200 Rp 20,200.00 Rp 24,240.00
paku biasa 1/2"-1" Kg 0.050 Rp 17,000.00 Rp 850.00
JUMLAH HARGA BAHAN Rp 25,090.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 57,035.00
E Overhead & Profit ( 10 % ) 10% x D Rp 5,703.50
F Harga Satuan Pekerjaan (D+E) Rp 62,738.50
A TENAGA
Pekerja L.01 OH 0.060 Rp 67,900.00 Rp 4,074.00
Tukang Las Kontruksi L.03 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 9,864.00
B BAHAN
Besi Baja IWF KG 1.150 Rp 18,400.00 Rp 21,160.00
JUMLAH HARGA BAHAN Rp 21,160.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 31,024.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,102.40
F Harga Satuan Pekerjaan (D+E) Rp 34,126.40
XI. HARGA SATUAN PEKERJAAN KAYU
1 Pembuatan & Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas I
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 7.000 Rp 67,900.00 Rp 475,300.00
Tukang Kayu L.02 OH 21.000 Rp 83,200.00 Rp 1,747,200.00
Kepala Tukang L.03 OH 2.100 Rp 88,000.00 Rp 184,800.00
Mandor L.04 OH 0.350 Rp 90,000.00 Rp 31,500.00
JUMLAH TENAGA KERJA Rp 2,438,800.00
B BAHAN
Balok Kayu Kelas I M3 1.100 Rp 3,609,000.00 Rp 3,969,900.00
Paku 10 cm Kg 1.250 Rp 15,300.00 Rp 19,125.00
Lem Kayu Kg 1.000 Rp 25,850.00 Rp 25,850.00
JUMLAH HARGA BAHAN Rp 4,014,875.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 6,453,675.00
E Overhead & Profit ( 10 % ) 10% x D Rp 645,367.50
F Harga Satuan Pekerjaan (D+E) Rp 7,099,042.50
A TENAGA
Pekerja L.01 OH 6.000 Rp 67,900.00 Rp 407,400.00
Tukang Kayu L.02 OH 18.000 Rp 83,200.00 Rp 1,497,600.00
Kepala Tukang L.03 OH 1.800 Rp 88,000.00 Rp 158,400.00
Mandor L.04 OH 0.300 Rp 90,000.00 Rp 27,000.00
JUMLAH TENAGA KERJA Rp 2,090,400.00
B BAHAN
Balok Kayu Kelas II M3 1.200 Rp 2,009,000.00 Rp 2,410,800.00
Paku 10 cm Kg 1.250 Rp 15,300.00 Rp 19,125.00
Lem Kayu Kg 1.000 25,850.00 Rp 25,850.00
JUMLAH HARGA BAHAN Rp 2,455,775.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,546,175.00
E Overhead & Profit ( 10 % ) 10% x D Rp 454,617.50
F Harga Satuan Pekerjaan (D+E) Rp 5,000,792.50
3 Pembuatan dan Pemasangan 1 M2 Pintu Klamp Standar, Kayu Kelas II
A TENAGA
Pekerja L.01 OH 0.350 Rp 67,900.00 Rp 23,765.000
Tukang Kayu L.02 OH 1.050 Rp 83,200.00 Rp 87,360.000
Kepala Tukang L.03 OH 0.105 Rp 88,000.00 Rp 9,240.000
Mandor L.04 OH 0.018 Rp 90,000.00 Rp 1,620.000
JUMLAH TENAGA KERJA Rp 121,985.00
B BAHAN
Papan Kayu Kelas II M3 0.040 Rp 2,009,000.00 Rp 80,360.00
Paku 5-7 cm Kg 0.050 Rp 15,300.00 Rp 765.00
JUMLAH HARGA BAHAN Rp 81,125.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 203,110.00
E Overhead & Profit ( 10 % ) 10% x D Rp 20,311.00
F Harga Satuan Pekerjaan (D+E) Rp 223,421.00
4 Pembuatan & Pemasangan 1 M2 Pintu Klamp Sederhana, Kayu Klam Kelas III
A TENAGA
Pekerja L.01 OH 0.350 Rp 67,900.00 Rp 23,765.000
Tukang Kayu L.02 OH 1.050 Rp 83,200.00 Rp 87,360.000
Kepala Tukang L.03 OH 0.105 Rp 88,000.00 Rp 9,240.000
Mandor L.04 OH 0.018 Rp 90,000.00 Rp 1,620.000
JUMLAH TENAGA KERJA Rp 121,985.00
B BAHAN
Papan Kayu Kayu Kelas III M3 0.040 Rp 1,809,000.00 Rp 72,360.00
Paku 5 - 7 cm Kg 0.050 Rp 15,300.00 Rp 765.00
JUMLAH HARGA BAHAN Rp 73,125.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 195,110.00
E Overhead & Profit ( 10 % ) 10% x D Rp 19,511.00
F Harga Satuan Pekerjaan (D+E) Rp 214,621.00
A TENAGA
Pekerja L.01 OH 1.000 Rp 67,900.00 Rp 67,900.00
Tukang Kayu L.02 OH 3.000 Rp 83,200.00 Rp 249,600.00
Kepala Tukang L.03 OH 0.300 Rp 88,000.00 Rp 26,400.00
Mandor L.04 OH 0.050 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 348,400.00
B BAHAN
Papan Kayu Kelas I M3 0.040 Rp 3,609,000.00 Rp 144,360.00
Lem Kayu Kg 0.500 Rp 25,850.00 Rp 12,925.00
JUMLAH HARGA BAHAN Rp 157,285.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 505,685.00
E Overhead & Profit ( 10 % ) 10% x D Rp 50,568.50
F Harga Satuan Pekerjaan (D+E) Rp 556,253.50
A TENAGA
Pekerja L.01 OH 0.800 Rp 67,900.00 Rp 54,320.000
Tukang Kayu L.02 OH 2.400 Rp 83,200.00 Rp 199,680.000
Kepala Tukang L.03 OH 0.240 Rp 88,000.00 Rp 21,120.000
Mandor L.04 OH 0.040 Rp 90,000.00 Rp 3,600.000
JUMLAH TENAGA KERJA Rp 278,720.00
B BAHAN
Papan Kayu Kelas II M3 0.024 Rp 2,009,000.00 Rp 48,216.00
Kaca Tebal 3 MM M2 1.000 Rp 85,200.00 Rp 85,200.00
Lem Kayu Kg 0.300 Rp 25,850.00 Rp 7,755.00
JUMLAH HARGA BAHAN Rp 141,171.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 419,891.00
E Overhead & Profit ( 10 % ) 10% x D Rp 41,989.10
F Harga Satuan Pekerjaan (D+E) Rp 461,880.10
7 Pembuatan & Pemasangan 1 M2 Jalusi Pintu/Jendela Kayu Kelas II
A TENAGA
Pekerja L.01 OH 1.000 Rp 67,900.00 Rp 67,900.00
Tukang Kayu L.02 OH 3.000 Rp 83,200.00 Rp 249,600.00
Kepala Tukang L.03 OH 0.300 Rp 88,000.00 Rp 26,400.00
Mandor L.04 OH 0.050 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 348,400.00
B BAHAN
Papan Kayu Kelas II M3 0.064 Rp 2,009,000.00 Rp 128,576.00
Lem Kayu Kg 0.500 Rp 25,850.00 Rp 12,925.00
JUMLAH HARGA BAHAN Rp 141,501.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 489,901.00
E Overhead & Profit ( 10 % ) 10% x D Rp 48,990.10
F Harga Satuan Pekerjaan (D+E) Rp 538,891.10
8 Pembuatan 1 M2 Daun Pintu Plywood Rangkap, Rangka Kayu Kelas II Tertutup ( Lebar sampai 90 cm )
A TENAGA
Pekerja L.01 OH 0.700 Rp 67,900.00 Rp 47,530.000
Tukang Kayu L.02 OH 2.100 Rp 83,200.00 Rp 174,720.000
Kepala Tukang L.03 OH 0.210 Rp 88,000.00 Rp 18,480.000
Mandor L.04 OH 0.035 Rp 90,000.00 Rp 3,150.000
JUMLAH TENAGA KERJA Rp 243,880.00
B BAHAN
Papan Kayu Kelas II M3 0.025 Rp 2,009,000.00 Rp 50,225.00
Paku 1 cm - 2,5cm Kg 0.030 Rp 15,300.00 Rp 459.00
Lem Kayu Kg 0.500 Rp 25,850.00 Rp 12,925.00
Plywood tebal 4 mm Ukuran Lembar 1.000 Rp 67,200.00 Rp 67,200.00
JUMLAH HARGA BAHAN Rp 130,809.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 374,689.00
E Overhead & Profit ( 10 % ) 10% x D Rp 37,468.90
F Harga Satuan Pekerjaan (D+E) Rp 412,157.90
A TENAGA
Pekerja L.01 OH 0.670 Rp 67,900.00 Rp 45,493.000
Tukang Kayu L.02 OH 2.000 Rp 83,200.00 Rp 166,400.000
Kepala Tukang L.03 OH 0.200 Rp 88,000.00 Rp 17,600.000
Mandor L.04 OH 0.335 Rp 90,000.00 Rp 30,150.000
JUMLAH TENAGA KERJA Rp 259,643.00
B BAHAN
Papan Kayu Kelas II M3 0.060 Rp 2,009,000.00 Rp 120,540.00
Paku 1 cm - 2,5cm Kg 0.150 Rp 15,300.00 Rp 2,295.00
JUMLAH HARGA BAHAN Rp 122,835.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 382,478.00
E Overhead & Profit ( 10 % ) 10% x D Rp 38,247.80
F Harga Satuan Pekerjaan (D+E) Rp 420,725.80
10 Pembuatan & Pemasangan 1 M2 Teakwood Rangka Ekspos Kayu Kelas I
A TENAGA
Pekerja L.01 OH 0.800 Rp 67,900.00 Rp 54,320.000
Tukang Kayu L.02 OH 2.400 Rp 83,200.00 Rp 199,680.000
Kepala Tukang L.03 OH 0.240 Rp 88,000.00 Rp 21,120.000
Mandor L.04 OH 0.040 Rp 90,000.00 Rp 3,600.000
JUMLAH TENAGA KERJA Rp 278,720.00
B BAHAN
Papan Kayu Kelas I M3 0.025 Rp 3,609,000.00 Rp 90,225.00
Paku 1 cm - 2,5cm Kg 0.030 Rp 15,300.00 Rp 459.00
Lem Kayu Kg 0.300 Rp 25,850.00 Rp 7,755.00
Teakwood 3,60 mm Lembar 1.000 Rp 152,200.00 Rp 152,200.00
JUMLAH HARGA BAHAN Rp 250,639.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 529,359.00
E Overhead & Profit ( 10 % ) 10% x D Rp 52,935.90
F Harga Satuan Pekerjaan (D+E) Rp 582,294.90
A TENAGA
Pekerja L.01 OH 4.000 Rp 67,900.00 Rp 271,600.00
Tukang Kayu L.02 OH 12.000 Rp 83,200.00 Rp 998,400.00
Kepala Tukang L.03 OH 1.200 Rp 88,000.00 Rp 105,600.00
Mandor L.04 OH 0.200 Rp 90,000.00 Rp 18,000.00
JUMLAH TENAGA KERJA Rp 1,393,600.00
B BAHAN
Balok Kayu Kelas II M3 1.100 Rp 2,009,000.00 Rp 2,209,900.00
Besi strip tebal 5mm Kg 15.000 Rp 13,200.00 Rp 198,000.00
Paku 12 cm Kg 5.600 Rp 15,300.00 Rp 85,680.00
JUMLAH HARGA BAHAN Rp 2,493,580.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 3,887,180.00
E Overhead & Profit ( 10 % ) 10% x D Rp 388,718.00
F Harga Satuan Pekerjaan (D+E) Rp 4,275,898.00
12 Pemasangan 1 M3 Konstruksi Gordeng, Kayu Kelas II
A TENAGA
Pekerja L.01 OH 6.700 Rp 67,900.00 Rp 454,930.000
Tukang Kayu L.02 OH 20.100 Rp 83,200.00 Rp 1,672,320.000
Kepala Tukang L.03 OH 2.010 Rp 88,000.00 Rp 176,880.000
Mandor L.04 OH 0.335 Rp 90,000.00 Rp 30,150.000
JUMLAH TENAGA KERJA Rp 2,334,280.000
B BAHAN
Balok Kayu Kelas II M3 1.100 Rp 2,009,000.00Rp 2,209,900.00
Besi strip tebal 5mm Kg 15.000 Rp 13,200.00 Rp 198,000.00
Paku 12 cm Kg 3.000 Rp 15,300.00 Rp 45,900.00
JUMLAH HARGA BAHAN Rp 2,453,800.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,788,080.00
E Overhead & Profit ( 10 % ) 10% x D Rp 478,808.00
F Harga Satuan Pekerjaan (D+E) Rp 5,266,888.00
A TENAGA
Pekerja L.01 OH 0.200 Rp 67,900.00 Rp 13,580.000
Tukang Kayu L.02 OH 0.300 Rp 83,200.00 Rp 24,960.000
Kepala Tukang L.03 OH 0.030 Rp 88,000.00 Rp 2,640.000
Mandor L.04 OH 0.010 Rp 90,000.00 Rp 900.000
JUMLAH TENAGA KERJA Rp 42,080.00
B BAHAN
Balok Kayu 4 x 6 cm Kayu Kelas II M3 0.0163 Rp 2,009,000.00 Rp 32,746.70
Paku 7 – 10 cm Kg 0.250 Rp 15,300.00 Rp 3,825.00
JUMLAH HARGA BAHAN Rp 36,571.70
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 78,651.70
E Overhead & Profit ( 10 % ) 10% x D Rp 7,865.17
F Harga Satuan Pekerjaan (D+E) Rp 86,516.87
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.000
Tukang Kayu L.02 OH 0.450 Rp 83,200.00 Rp 37,440.000
Kepala Tukang L.03 OH 0.045 Rp 88,000.00 Rp 3,960.000
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.000
JUMLAH TENAGA KERJA Rp 52,305.00
B BAHAN
Balok Kayu Kelas II M3 0.028 Rp 2,009,000.00 Rp 56,252.00
Paku 7 – 10 cm Kg 0.150 Rp 2,350.00 Rp 352.50
JUMLAH HARGA BAHAN Rp 56,604.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 108,909.50
E Overhead & Profit ( 10 % ) 10% x D Rp 10,890.95
F Harga Satuan Pekerjaan (D+E) Rp 119,800.45
15 Pemasangan 1 M2 Dinding Pemisah Plywood Rangkap Rangka Kayu Kelas II
A TENAGA
Pekerja L.01 OH 0.200 Rp 67,900.00 Rp 13,580.000
Tukang Kayu L.03 OH 0.600 Rp 83,200.00 Rp 49,920.000
Kepala Tukang L.03 OH 0.060 Rp 88,000.00 Rp 5,280.000
Mandor L.04 OH 0.010 Rp 90,000.00 Rp 900.000
JUMLAH TENAGA KERJA Rp 69,680.00
B BAHAN
Balok Kayu Kelas II M3 0.028 Rp 2,009,000.00 Rp 56,252.00
Paku 7 – 10 cm Kg 0.150 Rp 15,300.00 Rp 2,295.00
Plywood 4 MM, 120 x 240 Lembar 0.860 Rp 67,200.00 Rp 57,792.00
Lem Kayu Kg 0.560 Rp 25,850.00 Rp 14,476.00
JUMLAH HARGA BAHAN Rp 130,815.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 200,495.00
E Overhead & Profit ( 10 % ) 10% x D Rp 20,049.50
F Harga Satuan Pekerjaan (D+E) Rp 220,544.50
A TENAGA
Pekerja L.01 OH 0.100 Rp 67,900.00 Rp 6,790.000
Tukang Kayu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.000
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.000
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.000
JUMLAH TENAGA KERJA Rp 25,640.00
B BAHAN
Papan Kayu Kelas II M3 0.0108 Rp 2,009,000.00 Rp 21,697.20
Paku 5 dan 7 cm Kg 0.100 Rp 15,300.00 Rp 1,530.00
JUMLAH HARGA BAHAN Rp 23,227.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 48,867.20
E Overhead & Profit ( 10 % ) 10% x D Rp 4,886.72
F Harga Satuan Pekerjaan (D+E) Rp 53,753.92
A TENAGA
Pekerja L.01 OH 0.100 Rp 67,900.00 Rp 6,790.000
Tukang Kayu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.000
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.000
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.000
JUMLAH TENAGA KERJA Rp 25,640.00
B BAHAN
Papan Kayu Kelas II M3 0.011 Rp 2,009,000.00 Rp 22,099.00
Paku 5 dan 7 cm Kg 0.050 Rp 15,300.00 Rp 765.00
JUMLAH HARGA BAHAN Rp 22,864.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 48,504.00
E Overhead & Profit ( 10 % ) 10% x D Rp 4,850.40
F Harga Satuan Pekerjaan (D+E) Rp 53,354.40
XII. PEKERJAAN KUNCI DAN KACA
A TENAGA
Pekerja L.01 OH 0.060 Rp 67,900.00 Rp 4,074.00
Tukang Kayu L.02 OH 0.600 Rp 83,200.00 Rp 49,920.00
Kepala Tukang L.03 OH 0.060 Rp 88,000.00 Rp 5,280.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 59,544.00
B BAHAN
Kunci Tanam Antik Buah 1.000 Rp 200,350.00 Rp 200,350.00
JUMLAH HARGA BAHAN Rp 200,350.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 259,894.00
E Overhead & Profit ( 10 % ) 10% x D Rp 25,989.40
F Harga Satuan Pekerjaan (D+E) Rp 285,883.40
A TENAGA
Pekerja L.01 OH 0.010 Rp 67,900.00 Rp 679.00
Tukang Kayu L.02 OH 0.500 Rp 83,200.00 Rp 41,600.00
Kepala Tukang L.03 OH 0.050 Rp 88,000.00 Rp 4,400.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 47,129.00
B BAHAN
Kunci Tanam Biasa Bh 1.000 130,350.00 Rp 130,350.00
JUMLAH HARGA BAHAN Rp 130,350.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 177,479.00
E Overhead & Profit ( 10 % ) 10% x D Rp 17,747.90
F Harga Satuan Pekerjaan (D+E) Rp 195,226.90
A TENAGA
Pekerja L.01 OH 0.005 Rp 67,900.00 Rp 339.50
Tukang Kayu L.02 OH 0.500 Rp 83,200.00 Rp 41,600.00
Kepala Tukang L.03 OH 0.050 Rp 88,000.00 Rp 4,400.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 46,609.50
B BAHAN
Kunci Tanam KM Bh 1.000 Rp 50,350.00 Rp 50,350.00
JUMLAH HARGA BAHAN Rp 50,350.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 96,959.50
E Overhead & Profit ( 10 % ) 10% x D Rp 9,695.95
F Harga Satuan Pekerjaan (D+E) Rp 106,655.45
A TENAGA
Pekerja L.01 OH 0.005 Rp 67,900.00 Rp 339.50
Tukang Kayu L.02 OH 0.500 Rp 83,200.00 Rp 41,600.00
Kepala Tukang L.03 OH 0.050 Rp 88,000.00 Rp 4,400.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 46,609.50
B BAHAN
Kunci Silinder Buah 1.000 50,350.00 Rp 50,350.00
JUMLAH HARGA BAHAN Rp 50,350.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 96,959.50
E Overhead & Profit ( 10 % ) 10% x D Rp 9,695.95
F Harga Satuan Pekerjaan (D+E) Rp 106,655.45
A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.0008 Rp 90,000.00 Rp 72.00
JUMLAH TENAGA KERJA Rp 14,890.50
B BAHAN
Engsel pintu Buah 1.000 Rp 7,850.00 Rp 7,850.00
JUMLAH HARGA BAHAN Rp 7,850.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 22,740.50
E Overhead & Profit ( 10 % ) 10% x D Rp 2,274.05
F Harga Satuan Pekerjaan (D+E) Rp 25,014.55
A TENAGA
Pekerja L.01 OH 0.010 Rp 67,900.00 Rp 679.00
Tukang Kayu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.0005 Rp 90,000.00 Rp 45.00
JUMLAH TENAGA KERJA Rp 9,924.00
B BAHAN
Engsel kupu-kupu Buah 1.000 Rp 5,350.00 Rp 5,350.00
JUMLAH HARGA BAHAN Rp 5,350.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 15,274.00
E Overhead & Profit ( 10 % ) 10% x D Rp 1,527.40
F Harga Satuan Pekerjaan (D+E) Rp 16,801.40
A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 15,538.50
B BAHAN
Kait angin Buah 1.000 Rp 6,850.00 Rp 6,850.00
JUMLAH HARGA BAHAN Rp 6,850.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 22,388.50
E Overhead & Profit ( 10 % ) 10% x D Rp 2,238.85
F Harga Satuan Pekerjaan (D+E) Rp 24,627.35
A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 15,538.50
B BAHAN
Handle Jendela Buah 1.000 Rp 7,850.00 Rp 7,850.00
JUMLAH HARGA BAHAN Rp 7,850.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 23,388.50
E Overhead & Profit ( 10 % ) 10% x D Rp 2,338.85
F Harga Satuan Pekerjaan (D+E) Rp 25,727.35
A TENAGA
Pekerja L.01 OH 0.020 Rp 67,900.00 Rp 1,358.00
Tukang Kayu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.001 Rp 90,000.00 Rp 90.00
JUMLAH TENAGA KERJA Rp 19,848.00
B BAHAN
Grendel Jendela Buah 1.000 Rp 8,850.00 Rp 8,850.00
JUMLAH HARGA BAHAN Rp 8,850.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 28,698.00
E Overhead & Profit ( 10 % ) 10% x D Rp 2,869.80
F Harga Satuan Pekerjaan (D+E) Rp 31,567.80
A TENAGA
Pekerja L.01 OH 0.050 Rp 67,900.00 Rp 3,395.00
Tukang Kayu L.02 OH 0.500 Rp 83,200.00 Rp 41,600.00
Kepala Tukang L.03 OH 0.050 Rp 88,000.00 Rp 4,400.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 49,665.00
B BAHAN
Door Closer Buah 1.000 Rp 390,350.00 Rp 390,350.00
JUMLAH HARGA BAHAN Rp 390,350.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 440,015.00
E Overhead & Profit ( 10 % ) 10% x D Rp 44,001.50
F Harga Satuan Pekerjaan (D+E) Rp 484,016.50
A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.0008 Rp 90,000.00 Rp 72.00
JUMLAH TENAGA KERJA Rp 14,890.50
B BAHAN
Kaca tebal 3mm m2 1.100 Rp 85,200.00 Rp 93,720.00
Sealant Kg 0.050 Rp 12,550.00 Rp 627.50
JUMLAH HARGA BAHAN Rp 94,347.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 109,238.00
E Overhead & Profit ( 10 % ) 10% x D Rp 10,923.80
F Harga Satuan Pekerjaan (D+E) Rp 120,161.80
12 Pemasangan 1 m2 Kaca Polos tebal 5mm
A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.0008 Rp 90,000.00 Rp 72.00
JUMLAH TENAGA KERJA Rp 14,890.50
B BAHAN
Kaca tebal 5 mm m2 1.100 Rp 95,700.00 Rp 105,270.00
Sealant Kg 0.050 Rp 12,550.00 Rp 627.50
JUMLAH HARGA BAHAN Rp 105,897.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 120,788.00
E Overhead & Profit ( 10 % ) 10% x D Rp 12,078.80
F Harga Satuan Pekerjaan (D+E) Rp 132,866.80
A TENAGA
Pekerja L.01 OH 0.017 Rp 67,900.00 Rp 1,154.30
Tukang Kayu L.02 OH 0.170 Rp 83,200.00 Rp 14,144.00
Kepala Tukang L.03 OH 0.017 Rp 88,000.00 Rp 1,496.00
Mandor L.04 OH 0.0009 Rp 90,000.00 Rp 81.00
JUMLAH TENAGA KERJA Rp 16,875.30
B BAHAN
Kaca tebal 8 mm m2 1.100 Rp 368,900.00 Rp 405,790.00
Sealant Kg 0.0009 Rp 12,550.00 Rp 11.30
JUMLAH HARGA BAHAN Rp 405,801.30
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 422,676.60
E Overhead & Profit ( 10 % ) 10% x D Rp 42,267.66
F Harga Satuan Pekerjaan (D+E) Rp 464,944.25
14 Pemasangan 1 m2 Kaca Polos tebal 12mm
A TENAGA
Pekerja L.01 OH 0.025 Rp 67,900.00 Rp 1,697.50
Tukang Kayu L.02 OH 0.250 Rp 83,200.00 Rp 20,800.00
Kepala Tukang L.03 OH 0.025 Rp 88,000.00 Rp 2,200.00
Mandor L.04 OH 0.0013 Rp 90,000.00 Rp 117.00
JUMLAH TENAGA KERJA Rp 24,814.50
B BAHAN
Kaca tebal 12 mm m2 1.100 Rp 513,100.00 Rp 564,410.00
Sealant Kg 0.070 Rp 12,550.00 Rp 878.50
JUMLAH HARGA BAHAN Rp 565,288.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 590,103.00
E Overhead & Profit ( 10 % ) 10% x D Rp 59,010.30
F Harga Satuan Pekerjaan (D+E) Rp 649,113.30
A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 15,538.50
B BAHAN
Kaca Cermin Tebal 5 MM m2 1.100 Rp 14,750.00 Rp 16,225.00
JUMLAH HARGA BAHAN Rp 16,225.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 31,763.50
E Overhead & Profit ( 10 % ) 10% x D Rp 3,176.35
F Harga Satuan Pekerjaan (D+E) Rp 34,939.85
XIII. PEKERJAAN PENGECATAN
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 10,455.00
B BAHAN
Soda api Kg 0.050 Rp 12,150.00 Rp 607.50
JUMLAH HARGA BAHAN Rp 607.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 11,062.50
E Overhead & Profit ( 10 % ) 10% x D Rp 1,106.25
F Harga Satuan Pekerjaan (D+E) Rp 12,168.75
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 10,455.00
B BAHAN
Sabun Kg 0.050 Rp 31,300.00 Rp 1,565.00
JUMLAH HARGA BAHAN Rp 1,565.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 12,020.00
E Overhead & Profit ( 10 % ) 10% x D Rp 1,202.00
F Harga Satuan Pekerjaan (D+E) Rp 13,222.00
3 Pengecatan 1 M2 Bidang Kayu Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
A TENAGA
Pekerja L.01 OH 0.070 Rp 67,900.00 Rp 4,753.00
Tukang Cat L. 02 OH 0.009 Rp 83,200.00 Rp 748.80
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 6,299.80
B BAHAN
Cat menie Kg 0.200 Rp 30,550.00 Rp 6,110.00
Plamir Kg 0.150 Rp 27,750.00 Rp 4,162.50
Cat dasar Kg 0.170 Rp 30,550.00 Rp 5,193.50
Cat penutup Kg 0.260 Rp 58,550.00 Rp 15,223.00
Kuas Buah 0.010 Rp 17,550.00 Rp 175.50
Pengencer Kg 0.030 Rp 36,900.00 Rp 1,107.00
Ampelas Lbr 0.200 Rp 6,350.00 Rp 1,270.00
JUMLAH HARGA BAHAN Rp 33,241.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 39,541.30
E Overhead & Profit ( 10 % ) 10% x D Rp 3,954.13
F Harga Satuan Pekerjaan (D+E) Rp 43,495.43
A TENAGA
Pekerja L.01 OH 0.070 Rp 63,000.00 Rp 4,410.00
Tukang Cat L. 02 OH 0.009 Rp 75,000.00 Rp 675.00
Kepala Tukang L.03 OH 0.006 Rp 76,000.00 Rp 456.00
Mandor L.04 OH 0.003 Rp 81,000.00 Rp 243.00
JUMLAH TENAGA KERJA Rp 5,784.00
B BAHAN
Cat penutup Kg 0.260 Rp 58,550.00 Rp 15,223.00
Kuas Buah 0.010 Rp 17,550.00 Rp 175.50
Pengencer Kg 0.030 Rp 36,900.00 Rp 1,107.00
Ampelas Lbr 0.200 Rp 6,350.00 Rp 1,270.00
JUMLAH HARGA BAHAN Rp 17,775.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 23,559.50
E Overhead & Profit ( 10 % ) 10% x D Rp 2,355.95
F Harga Satuan Pekerjaan (D+E) Rp 25,915.45
5 Pengecatan 1 M2 Tembok Baru ( 1 Lapis Plamuur, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
A TENAGA
Pekerja L.01 OH 0.020 Rp 67,900.00 Rp 1,358.00
Tukang Cat L.02 OH 0.063 Rp 83,200.00 Rp 5,241.60
Kepala Tukang L.03 OH 0.0063 Rp 88,000.00 Rp 554.40
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 7,424.00
B BAHAN
Plamuur Kg 0.200 Rp 27,750.00 Rp 5,550.00
Cat dasar Kg 0.150 Rp 8,550.00 Rp 1,282.50
Cat Penutup Kg 0.170 Rp 12,550.00 Rp 2,133.50
JUMLAH HARGA BAHAN Rp 8,966.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 16,390.00
E Overhead & Profit ( 10 % ) 10% x D Rp 1,639.00
F Harga Satuan Pekerjaan (D+E) Rp 18,029.00
6 Pengecatan 1 M2 Tembok Lama ( 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )
A TENAGA
Pekerja L.01 OH 0.028 Rp 67,900.00 Rp 1,901.20
Tukang Cat L.02 OH 0.042 Rp 83,200.00 Rp 3,494.40
Kepala Tukang L.03 OH 0.0042 Rp 88,000.00 Rp 369.60
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 6,035.20
B BAHAN
Cat dasar Kg 0.120 Rp 8,550.00 Rp 1,026.00
Cat Penutup Kg 0.180 Rp 12,550.00 Rp 2,259.00
JUMLAH HARGA BAHAN Rp 3,285.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 9,320.20
E Overhead & Profit ( 10 % ) 10% x D Rp 932.02
F Harga Satuan Pekerjaan (D+E) Rp 10,252.22
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Cat L.02 OH 0.001 Rp 83,200.00 Rp 83.20
Kepala Tukang L.03 OH 0.0001 Rp 88,000.00 Rp 8.80
Mandor L.04 OH 0.0025 Rp 90,000.00 Rp 225.00
JUMLAH TENAGA KERJA Rp 10,502.00
B BAHAN
Kapur Sirih Kg 0.150 Rp 4,800.00 Rp 720.00
Ampelas Lbr 0.100 Rp 6,350.00 Rp 635.00
Alang - Alang Ikat 0.250 Rp 20,700.00 Rp 5,175.00
JUMLAH HARGA BAHAN Rp 6,530.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 17,032.00
E Overhead & Profit ( 10 % ) 10% x D Rp 1,703.20
F Harga Satuan Pekerjaan (D+E) Rp 18,735.20
A TENAGA
Pekerja L.01 OH 0.040 Rp 67,900.00 Rp 2,716.00
Tukang Cat L.02 OH 0.005 Rp 83,200.00 Rp 416.00
Kepala Tukang L.03 OH 0.0005 Rp 88,000.00 Rp 44.00
Mandor L.04 OH 0.0025 Rp 90,000.00 Rp 225.00
JUMLAH TENAGA KERJA Rp 3,401.00
B BAHAN
Kapur Sirih Kg 0.300 Rp 4,800.00 Rp 1,440.00
Ampelas Lbr 0.200 Rp 6,350.00 Rp 1,270.00
Alang - Alang Ikat 0.250 Rp 20,700.00 Rp 5,175.00
JUMLAH HARGA BAHAN Rp 7,885.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 11,286.00
E Overhead & Profit ( 10 % ) 10% x D Rp 1,128.60
F Harga Satuan Pekerjaan (D+E) Rp 12,414.60
9 Pengecatan 1 M2 Permukaan Baja Dengan Menie Besi
A TENAGA
Pekerja L.01 OH 0.020 Rp 67,900.00 Rp 1,358.00
Tukang Cat L. 02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.0025 Rp 90,000.00 Rp 225.00
JUMLAH TENAGA KERJA Rp 19,983.00
B BAHAN
Menie besi Kg 0.100 Rp 17,000.00 Rp 1,700.00
Kuas Buah 0.010 Rp 17,550.00 Rp 175.50
JUMLAH HARGA BAHAN Rp 1,875.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 21,858.50
E Overhead & Profit ( 10 % ) 10% x D Rp 2,185.85
F Harga Satuan Pekerjaan (D+E) Rp 24,044.35
10 Pengecatan 1 M2 Permukaan Baja Galvanis secara semprot Sistem 3 Lapis Cat Mutakhir
A TENAGA
Pekerja L.01 OH 0.040 Rp 67,900.00 Rp 2,716.00
Tukang Cat L. 02 OH 0.700 Rp 83,200.00 Rp 58,240.00
Kepala Tukang L.03 OH 0.070 Rp 88,000.00 Rp 6,160.00
Mandor L.04 OH 0.020 Rp 90,000.00 Rp 1,800.00
JUMLAH TENAGA KERJA Rp 68,916.00
B BAHAN
Cat Dasar Kg 0.30 Rp 30,550.00 Rp 9,165.00
Pengencer Liter 0.01 Rp 36,900.00 Rp 369.00
JUMLAH HARGA BAHAN Rp 9,534.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 78,450.00
E Overhead & Profit ( 15 % ) 15% x D Rp 7,845.00
F Harga Satuan Pekerjaan (D+E) Rp 86,295.00
XIV. PEKERJAAN SANITASI DALAM GEDUNG
A TENAGA
Pekerja L.01 OH 3.30 Rp 67,900.00 Rp 224,070.00
Tukang Batu L.02 OH 1.10 Rp 83,200.00 Rp 91,520.00
Kepala Tukang L.03 OH 0.01 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.16 Rp 90,000.00 Rp 14,400.00
JUMLAH TENAGA KERJA Rp 330,870.00
B BAHAN
Closet duduk Unit 1.00 Rp 1,786,800.00 Rp 1,786,800.00
A TENAGA
Pekerja L.01 OH 1.00 Rp 67,900.00 Rp 67,900.00
Tukang Batu L.02 OH 1.50 Rp 83,200.00 Rp 124,800.00
Kepala Tukang L.03 OH 0.15 Rp 88,000.00 Rp 13,200.00
Mandor L.04 OH 0.16 Rp 90,000.00 Rp 14,400.00
JUMLAH TENAGA KERJA Rp 220,300.00
B BAHAN
Closet jongkok Unit 1.00 Rp 286,800.00 Rp 286,800.00
Semen Portland Kg 6.00 Rp 1,650.00 Rp 9,900.00
Pasir Pasang M3 0.01 Rp 142,800.00 Rp 1,428.00
JUMLAH HARGA BAHAN Rp 298,128.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 518,428.00
E Overhead & Profit ( 10 % ) 10% x D Rp 51,842.80
F Harga Satuan Pekerjaan (D+E) Rp 570,270.80
3 Pemasangan 1 Buah urinoir
A TENAGA
Pekerja L.01 OH 1.000 Rp 67,900.00 Rp 67,900.00
Tukang Batu L.02 OH 1.000 Rp 83,200.00 Rp 83,200.00
Kepala Tukang L.03 OH 0.100 Rp 88,000.00 Rp 8,800.00
Mandor L.04 OH 0.050 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 164,400.00
B BAHAN
Urinoir Unit 1.000 Rp 1,336,800.00 Rp 1,336,800.00
Semen Portland Kg 6.000 Rp 1,650.00 Rp 9,900.00
Pasir pasang M3 0.010 Rp 142,800.00 Rp 1,428.00
Perlengkapan % 30.000 Rp 404,438.40 Rp 404,438.40
JUMLAH HARGA BAHAN Rp 1,752,566.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,916,966.40
E Overhead & Profit ( 10 % ) 10% x D Rp 191,696.64
F Harga Satuan Pekerjaan (D+E) Rp 2,108,663.04
A TENAGA
Pekerja L.01 OH 1.200 Rp 67,900.00 Rp 81,480.00
Tukang Batu L.02 OH 1.450 Rp 83,200.00 Rp 120,640.00
Kepala Tukang L.03 OH 0.150 Rp 88,000.00 Rp 13,200.00
Mandor L.04 OH 0.060 Rp 90,000.00 Rp 5,400.00
JUMLAH TENAGA KERJA Rp 220,720.00
B BAHAN
Wastafel Unit 1.200 Rp 486,800.00 Rp 584,160.00
Semen Portland Kg 6.000 Rp 1,650.00 Rp 9,900.00
Pasir pasang M3 0.010 Rp 142,800.00 Rp 1,428.00
Perlengkapan % 12.000 Rp 71,458.56 Rp 71,458.56
JUMLAH HARGA BAHAN Rp 666,946.56
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 887,666.56
E Overhead & Profit ( 10 % ) 10% x D Rp 88,766.66
F Harga Satuan Pekerjaan (D+E) Rp 976,433.22
A TENAGA
Pekerja L.01 OH 0.036 Rp 67,900.00 Rp 2,444.40
Tukang Batu L.02 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 8,144.40
B BAHAN
Pipa PVC Diameter 1/2 Inchi M1 1.200 Rp 4,350.00 Rp 5,220.00
Perlengkapan % 35.000 Rp 1,827.00 Rp 1,827.00
JUMLAH HARGA BAHAN Rp 7,047.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 15,191.40
E Overhead & Profit ( 10 % ) 10% x D Rp 1,519.14
F Harga Satuan Pekerjaan (D+E) Rp 16,710.54
A TENAGA
Pekerja L.01 OH 0.036 Rp 67,900.00 Rp 2,444.40
Tukang Batu L.02 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 8,144.40
B BAHAN
Pipa PVC Diameter 3/4 Inchi M1 1.200 Rp 4,650.00 Rp 5,580.00
Perlengkapan % 35.000 Rp 1,953.00 Rp 1,953.00
JUMLAH HARGA BAHAN Rp 7,533.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 15,677.40
E Overhead & Profit ( 10 % ) 10% x D Rp 1,567.74
F Harga Satuan Pekerjaan (D+E) Rp 17,245.14
A TENAGA
Pekerja L.01 OH 0.036 Rp 67,900.00 Rp 2,444.40
Tukang Batu L.02 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 8,144.40
B BAHAN
Pipa PVC Diameter 1 Inchi M1 1.200 Rp 6,250.00 Rp 7,500.00
Perlengkapan % 35.000 Rp 2,625.00 Rp 2,625.00
JUMLAH HARGA BAHAN Rp 10,125.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 18,269.40
E Overhead & Profit ( 10 % ) 10% x D Rp 1,826.94
F Harga Satuan Pekerjaan (D+E) Rp 20,096.34
A TENAGA
Pekerja L.01 OH 0.054 Rp 67,900.00 Rp 3,666.60
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 12,216.60
B BAHAN
Pipa PVC Diameter 2 Inchi M1 1.200 Rp 15,450.00 Rp 18,540.00
Perlengkapan % 35.000 Rp 6,489.00 Rp 6,489.00
JUMLAH HARGA BAHAN Rp 25,029.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 37,245.60
E Overhead & Profit ( 10 % ) 10% x D Rp 3,724.56
F Harga Satuan Pekerjaan (D+E) Rp 40,970.16
A TENAGA
Pekerja L.01 OH 0.081 Rp 67,900.00 Rp 5,499.90
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.0135 Rp 88,000.00 Rp 1,188.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 18,279.90
B BAHAN
Pipa PVC Diameter 2,50 Inchi M1 1.200 Rp 17,950.00 Rp 21,540.00
Perlengkapan % 35.000 Rp 7,539.00 Rp 7,539.00
JUMLAH HARGA BAHAN Rp 29,079.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 47,358.90
E Overhead & Profit ( 10 % ) 10% x D Rp 4,735.89
F Harga Satuan Pekerjaan (D+E) Rp 52,094.79
10 Pemasangan 1 M' Pipa PVC Diameter 3 Inchi
A TENAGA
Pekerja L.01 OH 0.081 Rp 67,900.00 Rp 5,499.90
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.0135 Rp 88,000.00 Rp 1,188.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 18,279.90
B BAHAN
Pipa PVC Diameter 3,0 Inchi M1 1.200 Rp 25,450.00 Rp 30,540.00
Perlengkapan % 35.000 Rp 10,689.00 Rp 10,689.00
JUMLAH HARGA BAHAN Rp 41,229.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 59,508.90
E Overhead & Profit ( 10 % ) 10% x D Rp 5,950.89
F Harga Satuan Pekerjaan (D+E) Rp 65,459.79
A TENAGA
Pekerja L.01 OH 0.081 Rp 67,900.00 Rp 5,499.90
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.0135 Rp 88,000.00 Rp 1,188.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 18,279.90
B BAHAN
Pipa PVC Diameter 4,0 Inchi M1 1.200 Rp 30,450.00 Rp 36,540.00
Perlengkapan % 35.000 Rp 12,789.00 Rp 12,789.00
JUMLAH HARGA BAHAN Rp 49,329.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 67,608.90
E Overhead & Profit ( 10 % ) 10% x D Rp 6,760.89
F Harga Satuan Pekerjaan (D+E) Rp 74,369.79
XV. PEKERJAAN LAIN - LAIN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 0.020 Rp 67,900.00 Rp 1,358.00
Mandor L.02 OH 0.001 Rp 90,000.00 Rp 90.00
JUMLAH TENAGA KERJA Rp 1,448.00
B BAHAN
Pasir Beton (PB) M3 0.010 Rp 142,800.00 Rp 1,428.00
JUMLAH HARGA BAHAN Rp 1,428.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 2,876.00
E Overhead & Profit ( 10 % ) 10% x D Rp 287.60
F Harga Satuan Pekerjaan (D+E) Rp 3,163.60
A TENAGA
Pekerja L.01 OH 0.040 Rp 67,900.00 Rp 2,716.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 3,076.00
B BAHAN
Pupuk Kandang Krg 0.040 26,300.00 Rp 1,052.00
Rumput Gajah Mini M2 1.050 42,750.00 Rp 44,887.50
JUMLAH HARGA BAHAN Rp 45,939.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 49,015.50
E Overhead & Profit ( 10 % ) 10% x D Rp 4,901.55
F Harga Satuan Pekerjaan (D+E) Rp 53,917.05
A TENAGA
Pekerja L.01 OH 0.080 Rp 67,900.00 Rp 5,432.00
Tukang L.03 OH 0.800 Rp 83,200.00 Rp 66,560.00
Kepala Tukang L.03 OH 0.080 Rp 88,000.00 Rp 7,040.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 79,392.00
B BAHAN
Sunscreeen Alluminium M2 1.000 204,000.00 Rp 204,000.00
JUMLAH HARGA BAHAN Rp 204,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 283,392.00
E Overhead & Profit ( 10 % ) 10% x D Rp 28,339.20
F Harga Satuan Pekerjaan (D+E) Rp 311,731.20