Professional Documents
Culture Documents
04 BSCM v4.1
04 BSCM v4.1
Session 4
6. 7. 8. 9. 10.
Bill of Material
– Define parent and component in the bill of material (BOM), and
explain their relationship.
– Perform a simple BOM explosion.
– Explain the use of the planning bill.
– Differentiate between where-used reports and pegging reports.
Session 4
Material
Requirements
Planning
Environment
Independent demand
Table
100
Dependent demand
Resource
Capacity planning
S&OP
Priority planning
planning
Rough-cut
Master scheduling capacity planning
(RCCP)
Capacity
MRP requirements
planning (CRP)
Execution
Execution
Input/output
Production activity control
control (PAC)
Order
sequencing
MPS data
Priority planning
BOMs
Net requirements
Inventory status
Planned order receipts
Manufacturing orders
Planning data To factory
(such as lead time) Planned order releases Purchase orders
To suppliers
Planning software
develops the priority plan for the release and receipt of
planned orders
advises planners of the need for actions to maintain the
priority plan
– releases planned orders
– takes action to maintain due dates affected by material
shortages, delayed production, and other events
Session 4
Bill of Material
Description:
Part number: 100
table
Quantity Unit of
Part number Description
required measure
300 Base 1 Ea
306 Legs 4 Ea
326 Leg bolts 8 Ea
357 Frame 1 Ea
311 Wooden sides 2 Ea
433 Wooden ends 2 Ea
025 Top 1 Ea
031 Boards 3 Ea
075 Glue 1 Ea
822 Hardware kit 1 Kit
4 12 © APICS CONFIDENTIAL AND PROPRIETARY
Indented Bill of Material
Description:
Part number: 100
table
Quantity Unit of
Part number Description
required measure
300 Base 1 Each
306 Legs 4 Each
326 Leg bolts 8 Each
357 Frame 1 Each
311 Wooden sides 2 Each
433 Wooden ends 2 Each
025 Top 1 Each
031 Boards 3 Each
075 Glue 1 Each
822 Hardware kit 1 Kit
Table
100 Level 0
Multilevel bill
Hardware
Base Top
kit Level 1
300 025
822
Hardware
Base Top
kit
300 025
822
Parent A B C E
Component B (2) E (2) G (2) G (4)
C (4) F (1) F (3)
D (3) H (2)
Number of Gs needed: 24
Purchased components: G, F, H, D
Family
Bicycle
Product definition
Engineering change control
Planning
Customer service
Manufacturing
Costing
Source: Arnold et al., Introduction to Materials Management , 7th ed.
Reprinted by Permission of Pearson Education
4 20 © APICS CONFIDENTIAL AND PROPRIETARY
Material Requirements Planning (MRP)
Session 4
Material Requirements
Planning Logic
MRP logic
– Exploding and offsetting requirements
– Calculating gross and net requirements
MPS data
Priority planning
Questions:
BOMs • What
Lead-time • How much
offsetting, • When
exploding, and
Inventory status netting of Planned order receipts
requirements
Planned order releases
Planning data
(lead time)
Lead time: In MRP, the span of time from the planned order receipt period back
to the planned order release period
Offsetting: Placing the requirements (planned order releases) in their proper time
periods based on lead time
Exploding: The process of calculating the demand for the components of a
parent item by multiplying the parent item requirements by the
component usage quantity specified in the bill of material
—APICS Dictionary
Wk = Week; LT = lead time
4 24 © APICS CONFIDENTIAL AND PROPRIETARY
Lead Time Offsetting and Exploding
Item Week
number Planned order 1 2 3 4 5
Receipt 50
B Release 50
Receipt
C Release
Receipt 50
D Release 50
Receipt
E Release
Receipt
F Release
Wk = Week; LT = lead time
4 25 © APICS CONFIDENTIAL AND PROPRIETARY
Problem 4.2
Item Week
number Planned order 1 2 3 4 5
Receipt 50
B Release 50
Receipt
C Release
Receipt 50
D Release 50
Receipt
E Release
Receipt
F Release
Wk = Week; LT = lead time
4 26 © APICS CONFIDENTIAL AND PROPRIETARY
Problem 4.2 Solution
Item Week
number Planned order 1 2 3 4 5
Receipt 50
B Release 50
Receipt 50
C Release 50
Receipt 50
D Release 50
Receipt 50
E Release 50
Receipt 50
F Release 50
Wk = Week; LT = lead time
4 27 © APICS CONFIDENTIAL AND PROPRIETARY
Problem 4.3
Item Week
number Planned order 1 2 3 4 5
Receipt 200
X Release
Receipt
Y Release
Receipt
Z Release
Receipt
W Release
Receipt
V Release
Wk = Week; LT = lead time
4 28 © APICS CONFIDENTIAL AND PROPRIETARY
Problem 4.3 Solution
Item Week
number Planned order 1 2 3 4 5
Receipt 200
X Release 200
Receipt 200
Y Release 200
Receipt 200
Z Release 200
Receipt 200
W Release 200
Receipt 200
V Release 200
Wk = Week; LT = lead time
4 29 © APICS CONFIDENTIAL AND PROPRIETARY
Gross and Net Requirements
B Lead time =
1 week
Item Week
number 1 2 3 4 5
Gross requirements 35
Scheduled receipts 20
Projected available 10 10 30 30 30 0
Net requirements 5
Planned order receipt 5
Planned order release 5
Item Week
number 1 2 3 4 5
Gross requirements
Scheduled receipts
Projected available
J Net requirements
Planned order receipt
Planned order release
Gross requirements
Scheduled receipts
Projected available
K Net requirements
Planned order receipt
Planned order release
Gross requirements
Scheduled receipts
Projected available
L Net requirements
Planned order receipt
Planned order release
Gross requirements
Scheduled receipts
Projected available
M Net requirements
Planned order receipt
Planned order release
Gross requirements
Scheduled receipts
Projected available
N Net requirements
Planned order receipt
Planned order release
Item Week
number 1 2 3 4 5
Gross requirements 50
Scheduled receipts
Projected available 0
J Net requirements 50
Planned order receipt 50
Planned order release 50
Gross requirements 100
Scheduled receipts 50
Projected available 50 50 0
K Net requirements 50
Planned order receipt 50
Planned order release 50
Gross requirements 50
Scheduled receipts
Projected available 100 100 100 100 50 50
L Net requirements
Planned order receipt
Planned order release
Gross requirements 100
Scheduled receipts
Projected available 0
M Net requirements 100
Planned order receipt 100
Planned order release 100
Gross requirements 150
Scheduled receipts
Projected available 200 200 50 50 50 50
N Net requirements
Planned order receipt
Planned order release
Master
RCCP
scheduling
MRP CRP
PAC
Session 4
Using and
Managing
the Priority Plan
Item Week
number 1 2 3 4 5
Gross requirements 35 35
Scheduled receipts 20
Projected available 10 10 30 0 0 0
Net requirements 5 35
Planned order receipt 5 35
Planned order release 5 35F
Create/release
purchase orders
Allocate
components to
the order
Create/release
shop orders
Internal
Lower yields or higher scrap factors than planned
Late or early open order completions
Capacity or resource shortages
Material shortages caused by inventory record inaccuracies
Maintain priorities
Expedite orders
De-expedite orders
Change quantity requirements
Replanning
Changes in end-item due dates
Week
Part A
1 2 3 4
Gross requirements 70 60 50
Scheduled receipts 50
Projected available 20
Net requirement
Planned order receipt
Planned order release
Week
Part A
1 2 3 4
Gross requirements 70 60 50
Scheduled receipts 50
Projected available 20 20 0 0 0
Net requirement 0 60 50
Planned order receipt 60 50
Planned order release 60 50
Week
Part A
2 3 4
Gross requirements 70 60 50
Scheduled receipts
Projected available 20
Net requirement
Week
Part A
2 3 4
Gross requirements 70 60 50
Scheduled receipts 30
Net requirement 20 60 50
Session 4
Wrap-Up and
Homework
Bill of Material
– Define parent and component in the BOM, and explain their
relationship.
– Perform a simple BOM explosion.
– Explain the use of the planning bill.
– Differentiate between where-used reports and pegging reports.
1. d 7. k
2. i 8. h
3. g 9. b
4. a 10. f
5. c 11. j
6. e 12. l
C (2) D (1)