Method of Underground Piping: Method Statement For Mechanical Work
Method of Underground Piping: Method Statement For Mechanical Work
APPROVED DATE
00 - DRAWING LIST
01 - SUPPORT FOR HORIZONTAL PIPE AND SLOPE OF PIPE / GIÁ ĐỠ VÀ ĐỘ DỐC CỦA ỐNG
04 - UNDER - ROAD SPG PIPE / ỐNG SẮT TRÁNG KẼM BĂNG ĐƯỜNG
PAGE:
METHOD STATEMENT FOR MECHANICAL WORK
REVISED (1) CLAUSE METHOD OF UNDERGROUND PIPING APPLICATION
REVISED (3) ITEM SUPPORT FOR HORIZONTAL PIPE AND SLOPE OF PIPE
APPROVED DATE
MAX 2000
FINISH
NATIVE SOIL
SANDING A HALF
RE-CHECK 200
LEVEL
COMPACTED
SAND LAYER
uPVC MAIN PIPE
50 50 uPVC MAIN PIPE
WORKING:
2. EXCAVATION AND THEN PUTTING DOWN LEAN CONCRETE AND CHECK HIGH-LEVEL
3. PUTTING PIPLINE ON THE LEAN CONCRETE AND FIX IT THEN CHECK HIGH-LEVEL PIPELINE
4. SANDING A HALF PIPELINE PLUS WATER AFTER THAT RE-CHECK LEVEL
SLOPE OF PIPELINE:
APPROVED DATE
MAX 2000
SLAB
WORKING:
1.FILL WATER INSIDE PIPELINE AND CHECK THE END PIPELINE UNTIL SEE WATER FLOW
2. BLIND END PIPELINE AND CONTINUED FILL WATER UNTILL OVER FLOW WATER
4. CHECK MARKING POINT AFTER ENOUGH TIME. IF WATER LEVEL DON'T GO DOWN. THIS IS GOOD
PAGE:
METHOD STATEMENT FOR MECHANICAL WORK
REVISED (1) CLAUSE METHOD OF UNDERGROUND PIPING APPLICATION
APPROVED DATE
WORKING:
2. TO ROLL FIBER SHEET 1ST AROUND PIPE (THE NEXT LAYER COVER 1/2 PREVIOUS LAYER)
APPROVED DATE
WORKING: