METHOD STATEMENT FOR MECHANICAL WORK


REVISED (1) CLAUSE METHOD OF UNDERGROUND PIPING APPLICATION

REVISED (2) OUTSIDE

REVISED (3) ITEM DRAWING LIST

APPROVED DATE

METHOD OF UNDERGROUND PIPING

00 - DRAWING LIST

01 - SUPPORT FOR HORIZONTAL PIPE AND SLOPE OF PIPE / GIÁ ĐỠ VÀ ĐỘ DỐC CỦA ỐNG

02 - UNDERGROUND PVC TESTING / THỬ NƯỚC ỐNG PVC

03 - UNDERGROUND SPG PIPE / ỐNG SẮT TRÁNG KẼM ÂM

04 - UNDER - ROAD SPG PIPE / ỐNG SẮT TRÁNG KẼM BĂNG ĐƯỜNG
PAGE:
METHOD STATEMENT FOR MECHANICAL WORK
REVISED (1) CLAUSE METHOD OF UNDERGROUND PIPING APPLICATION

REVISED (2) OUTSIDE

REVISED (3) ITEM SUPPORT FOR HORIZONTAL PIPE AND SLOPE OF PIPE

APPROVED DATE

MAX 2000

FINISH

LEAN CONCRETE uPVC PIPE LEAN CONCRETE

NATIVE SOIL
SANDING A HALF

RE-CHECK 200
LEVEL
COMPACTED
SAND LAYER
uPVC MAIN PIPE
50 50 uPVC MAIN PIPE

LEAN CONCRETE LEAN CONCRETE


BEDDING LAYER BEDDING LAYER

WORKING:

1. DETERMINATION LOCATE PIPELINE FOLLOW SHOP DRAWING

2. EXCAVATION AND THEN PUTTING DOWN LEAN CONCRETE AND CHECK HIGH-LEVEL

3. PUTTING PIPLINE ON THE LEAN CONCRETE AND FIX IT THEN CHECK HIGH-LEVEL PIPELINE
4. SANDING A HALF PIPELINE PLUS WATER AFTER THAT RE-CHECK LEVEL

5. BACK FILLING AND COMPACTION

SLOPE OF PIPELINE:

uPVC PIPE SLOPE REMARK


DN48 1/50
DN60 1/60
DN90 1/90
DN110 1/100
DN125 1/100 - 1/125
DN140 1/100 - 1/140
DN160 1/100 - 1/160
DN200 1/100 - 1/200
PAGE:
METHOD STATEMENT FOR MECHANICAL WORK
REVISED (1) CLAUSE METHOD OF UNDERGROUND PIPING APPLICATION

REVISED (2) OUTSIDE

REVISED (3) ITEM UNDERGROUND PVC TESTING

APPROVED DATE

CLOSE END POINT MARKING POINT WATER

MAX 2000
SLAB

CONCRETE SUPPORT uPVC PIPE CONCRETE SUPPORT

WORKING:

1.FILL WATER INSIDE PIPELINE AND CHECK THE END PIPELINE UNTIL SEE WATER FLOW

2. BLIND END PIPELINE AND CONTINUED FILL WATER UNTILL OVER FLOW WATER

3. MARKING AND HOLDING 24 HOURS

4. CHECK MARKING POINT AFTER ENOUGH TIME. IF WATER LEVEL DON'T GO DOWN. THIS IS GOOD
PAGE:
METHOD STATEMENT FOR MECHANICAL WORK
REVISED (1) CLAUSE METHOD OF UNDERGROUND PIPING APPLICATION

REVISED (2) OUTSIDE

REVISED (3) ITEM UNDERGROUND SPG PIPE

APPROVED DATE

WORKING:

1. PRE-PAINT BITUM ON CLEAN SPG PIPE

2. TO ROLL FIBER SHEET 1ST AROUND PIPE (THE NEXT LAYER COVER 1/2 PREVIOUS LAYER)

3. PAINT BITUM ON 1ST FIBER SHEET


4. TO ROLL FIBER SHEET 2ND AROUND PIPE

5. PAINT BITUM ON 2ND FIBER SHEET


PAGE:
METHOD STATEMENT FOR MECHANICAL WORK
REVISED (1) CLAUSE METHOD OF UNDERGROUND PIPING APPLICATION

REVISED (2) OUTSIDE

REVISED (3) ITEM UNDER - ROAD SPG PIPE

APPROVED DATE

WORKING:

1. COMPACT SAND BY MACHINE BEFORE SETTING U/G PIPE

2. SETTING CONCRETE SUPPORT (DISTANCE MAX 1500MM)

3. SETTING STEEL FRAME D10@150


4. CONCRETE COVER PIPE, THICKNESS FROM BOTTOM PIPE MAX 80MM, FROM TOP PIPE 150MM

5. AFTER CONCRETE DRY, BACKFILL AND COMPACT BY MACHINE