Professional Documents
Culture Documents
Chapter 2 Lesson 2
Chapter 2 Lesson 2
Overview/Introduction
Learning Outcome/Objective
Learning Content/Topic
Solution
Goal
Find between the two alternatives will cost less for the production of jet engine part.
Given
Aluminum Cast
Weight of aluminum casting = 1.2kg
Cost of making aluminum casting = ₱80/kg
Cost of machining aluminum cast = ₱150
Excess weight = 0
Penalty of excess weight = 0 (did not exceed 1.25kg)
Steel Cast
Weight of steel casting = 1.35kg
Cost of making steel casting = ₱35/kg
Cost of machining steel cast = ₱100
Excess weight =0.1kg
Penalty of excess weight = ₱1300/kg
Comparison
Total cost of aluminum cast
Total Cost =Cost of casting +Cost of machining+ Penalty
Total Cost =(₱ 80
kg )
∗1.2 kg + ₱ 150+ 0
Solution
Goal
Come up with the best design alternative and its economic advantage.
Given
Design A
Lathe time / 1000 units = 16 hours
Grinding time / 1000 units = 4.5 hours
Design B
Lathe time / 1000 units = 7 hours
Grinding time / 1000 units = 12 hours
Cost Labor for both Designs
Cost of lathe operation = ₱200/hour
Cost of grinder operation = ₱150/hour
Comparison
Total cost of design A
Total Cost =Cost of lathe operation+ Cost of grinding
Total Cost =(₱ 200
hr )(
∗16 hrs +
₱ 150
hr
∗4.5 hrs )
Total Cost =₱ 3,875
Total cost of design B
Total Cost =Cost of lathe operation+ Cost of grinding
Total Cost =(₱ 200
hr )(
∗7 hrs +
₱ 150
hr
∗12 hrs)
Total Cost =₱ 3,200
Decision
The total cost of design A is less than that of design B. Hence, for the production of
tapered fastening pin, Design A should be adopted with an economic advantage of
₱675/1000units.
Solution
Sequence A
Cost of Operation=Cost of operation per minute∗Duration∈minute
₱4
Cost of Turning= ∗5 mins=₱ 20
min
₱7
Cost of Milling= ∗8 mins=₱ 56
min
₱6
Cost of Shaping= ∗10 mins=₱ 60
min
₱5
Cost of Drilling= ∗3 mins=₱ 15
min
Total Cost =₱ 20+ ₱ 56+ ₱ 60+ ₱ 15=₱ 151
Sequence B
Cost of Operation=Cost of operation per minute∗Duration∈minute
₱4
Cost of Turning= ∗5 mins=₱ 20
min
₱7
Cost of Milling= ∗14 mins=₱ 98
min
₱5
Cost of Drilling= ∗3 mins=₱ 15
min
Total Cost =₱ 20+ ₱ 98+ ₱ 15=₱ 133
Sequence C
Cost of Operation=Cost of operation per minute∗Duration∈minute
₱ 17
Cost of CNC Operation = ∗8 mins=₱ 136
min
Decision
Sequence B has the least total cost of operation. Therefore, it should be selected for
manufacturing the product.
Problem Set
A Construction Company is Manila will bid in the digging of an
irrigation canal in a nearby province which measure 2 meters wide, 1 meter
deep, and 2 km long. Twenty laborers will be employed at P120.00 each per
day, and they can dig, on the average, ½ cu. m. per hour. In addition, 2
foremen will also be employed at P250.00 each per day.
Allowing P20, 000 for profit and contingencies, determine the lowest bid price of
the company.
Chapter Quiz