Professional Documents
Culture Documents
2022 Avon Beach Nourishment: Construction Progress
2022 Avon Beach Nourishment: Construction Progress
2022 Avon Beach Nourishment: Construction Progress
Construction Progress
After two and half years of planning,
designing, permitting, and selecting
contractors, construction of the Avon
Village beach nourishment commenced
on schedule this summer. Great Lakes
Dredge & Dock Company (GLDD) used
America's largest hopper dredge, the
Ellis Island, to deliver the first load on
Cape Hatteras National Seashore in
front of the Village of Avon at 1:40 p.m.
on Sunday, June 19, 2022. Throughout
the rest of afternoon, Dare County
Commissioner Danny Couch along with
other members of the general public
watched the dredge as she was setting
up and pumping slurry through the
submerged pipeline.
The Ellis Island, America’s largest hopper dredge, arrived on June 19 and delivered her first
load around 1:40 p.m. at approximately 1 mile south of the Avon Pier.
The discharge point is located between Ocean View Drive and Greenwood Place (approximately 1 mile south of the
Avon Pier). Construction will proceed south for ~3,200 ft to the end of the village (just north of ORV Ramp #38).
GLDD estimates it will take 10–15 days to complete this section.
After the southernmost section of the project is completed, GLDD will return to the discharge point between Ocean
View Drive and Greenwood Place to begin pumping north for ~3,300 ft toward the Avon Pier to Yucca Street.
Afterward, the dredge will use another subline located north of the Avon Pier to complete the rest of the project.
There are generally two types of solutions in defense against coastal erosion: hard solutions (ie – shore-protection
structures such as seawalls, revetments, jetties, or groins) and soft solutions (ie – placing sediment through beach
nourishment, beach scraping, dune restoration, etc.). As the dominant soft solution, beach nourishment is the only
solution that adds sand to the beach system, preserves the recreational beach, and protects upland development.
Sand placed on the beach will further enhance natural dune growth through wind-generated sediment transport
and will increase the level of storm protection. The primary purpose and goal of the Avon nourishment is to protect
N.C. Highway 12 and state and federal infrastructure. Other crucial benefits include increased storm protection,
enhanced coastal resiliency, and the creation of additional habitats for wildlife.
Beginning in Coney Island (NY) nearly 100 years ago, beach nourishment has become a dominant method of
domestic shore protection. During the last century, the beaches of over 475 communities in the United States
have been restored with over 1.5 billion cubic yards of nourished sand. Many project sites have been nourished
multiple times for a total of about 3,200 distinct events throughout the nation.
Amphipod Coquina
Cape Hatteras National Seashore Ramp #38 and its parking lot have been
designated as the project's staging area and beach access. Visitors with
beach driving permits can expect some intermittent, short-term
delays entering and exiting the ramp while beach nourishment
equipment is moved safely to and from the beach.
There will be a very wide beach immediately after nourishment, and the beach face will initially be steeper than the
natural slope. These results are intentional and are part of the construction process, designed to take advantage of
natural forces, such as waves and currents, to move sand offshore. Following nourishment, it is typical for the newly
constructed dry-sand beach to become narrower and for the beach face to adjust to its natural slope.
The second hopper dredge, Liberty Island, is scheduled to arrive at the job site in early July. She will take over the
Avon project while the Ellis Island moves downshore to begin beach nourishment in Buxton. The Avon project
calls for the placement of 1 million cy of sand along approximately 2.5 miles of shoreline from 4,000 ft north of
Avon Pier at Due East Road to the southern limit of Avon. GLDD estimates that, on average, approximately 30,000
cy can be pumped each day onto the beach, and it will take 40–60 days to complete the project under normal
weather conditions. GLDD currently anticipates the Avon project will be completed by August.