Professional Documents
Culture Documents
CHAPTER 20 Water Distribution Systems
CHAPTER 20 Water Distribution Systems
CHAPTER 20 Water Distribution Systems
1
3/25/2022
Pipelines
The following types of pipes 2. steel
are use for water systems : a. threaded, black or galvanized
1.cast iron b. welded, plain or cement-lined
a. bell and spigot 3. reinforced concrete
b. mechanical joint a. prestressed
c. push –on joint, or b. nonprestressed
gasket –seal joint 4. brass and copper
d. threaded 5. lead
e. cement-lined 6. plastic
2
3/25/2022
3
3/25/2022
4
3/25/2022
Fire hydrants
Fire hydrants are specified by the type of
construction size of valve sizes and number of hose
connections size of hub for connection to the water
pipe and depth of bury it is good practice to install a
gate valve between each hydrant and the main
water pipe so that the water can be shut off in the
event repairs to the hydrant are necessary.
10
5
3/25/2022
11
12
6
3/25/2022
13
Each joint of pipe is lowered into the trench by hand or with an excavator crane tractor-mounted side
boom or other suitable equipment after the spigot end is forced into the bell to full depth two or more
strands of yarning which completely encircle the pipe are caulked into the bell to center the pipe and to
prevent molten lead from flowing into the pipe a runner is placed around the pipe against the bell with
an opening near the top to enable molten lead to be poured into the joint the lead for a joint should be
poured in one continuous operation without interruption after the lead cools to the temperature of the
pipe the runner is removed the lead is caulked by hand or with a pneumatic caulking hammer.
14
7
3/25/2022
15
16
8
3/25/2022
17
18
9
3/25/2022
A crew should lay five to seven joints per hour either pipe
or fittings the length of pipe laid will vary from 90 to to 136
ft/hr, with 100 ft/hr a fir average .
Table 23.6 gives representative labor-hours required to lay
cast-iron pipe with mechanical joints in trenches 3 to 6 ft
deep in firm soil with little or on shoring required and no
groundwater for pipe laid under other conditions the labor-
hours should be altered to fit the conditions of the
particular job if a crane is used to lower the pipe replace
the tractor operator with a crane operator .
19
20
10
3/25/2022
21
22
11
3/25/2022
23
o All directional method consist of drilling unit to form the borehole and a survey
system to locate the drill head . The drilling process us accomplished either by
mechanical cutting using a drill bit or by fluid cutting with high – pressure jets ,
or a combination of both . There are a variety of survey systems that have been
patented by different manufacturers . The choice of a particular system will
largely depend on the type of job , the site condition and accessibility , operator
skill , finances available ,etc.
24
12
3/25/2022
Classifications of HDD
25
26
13
3/25/2022
PRODUTION RATES
Most mini –HDD jobs are usually completed in a day or even a few
hours . It is common to complete a 200-ft job in a few hours . for midi-
HDD project , and for lengths of 1,000ft or longer , the job may take 10
or 15 days , including mobilization and setup of the rig and preparation
of the product pipe. For major river crossing using maxi- HDD , the
project may take several method to complete . It should be noted that
the duration of an HDD project is site – specific, and it is dependent on
many factor , such as experience of the operator and the contractor ,
project surface and subsurface condition , equipment used , type of
application , and the degrees of planning for the project .
27
14