DATE : 3/6/2022

WBCU - Field Report WELL NO. : JLMN-47


RIG : SND-2002

Time Bit Depth Mud Flow Max SPP Mud In Weight Mud Out Max. Torque Max. WOB Max. Overpull Upweight Downweight
Date (24hr)
Operation in Progress
(Feet)
Std Number
(GPM) (Psi) (pcf) Weight (pcf)
Max. RPM
(lb.ft) (Klb) (Klb) (lbs) (lbs)
Remarks / Comments

3-Jun 18:00 ARRIVE LOCATION N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A ARRIVE TO SND-2002 MEET CO-MAN AND CHECK ON TOOL , DARTS

9:00 P/U TOOL N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A MU& PU 8.25" DAV MX AND RIH TO DRILL 12" ROTARY BHA
9-Jun
19:00 DRILLING 2,100 N/A 700 2000 90 90 130 20000 45 N/A N/A N/A START DRILL THIS SECTION

5:00 DRILLING N/A 700 2000 90 90 130 20000 45 N/A N/A N/A 17 Nov Took hanover from Sultan

10-Jun 9:00 Continue drilling 3,400 650 3000 90 90 130 3000 42 N/A N/A N/A
19:00 Continue drilling 7,200 500 3900 90 90 130 3000 42 N/A N/A N/A Decided to POOH to Casing Shoe

Start Reaming Open hole 2100 Start Reaming of open hole

11-Jun POOH to Casing Shoe


Reaming back 7200
DropGyro Tool N/A 700 4000 96 96 70 40000 40 N/A N/A N/A On loaction have 2 each 8 1/4'' dav mx

12-Jun 5:00 POOH to Casing Shoe 2100 & 2each 7'' DAV MX

L/D Extra Drill Collars


12-Jun 12:00 L/D CX 8 1/4'' DAVMX
Stand by for Next sectio
13-Jun 7'' DAV MX arrived at location
Running 9 5/8'' casing
TRS Operation in Progress
P/up Cement head Euip..
Start Cementing with SLB Unit
Waiting for cement
P/UP 8 3/8'' RIG C/O BHA
TIH to Shoe @ 7120
Drill Cment in 9 5/8'' section
Drill 9 5/8'' Shoe track
CHC Max RATE
POOH L/D C/O BHA