ID Task Task Name Duration Start Finish Predecessors Resource Names Jun 12, '22 Jun 19, '22

Finish Predecessors Resource Names Jun 12, '22 Jun 19, '22 Jun 26, '22 Jul 3, '22
Mode T W T F S S M T W T F S S M T W T F S S M T W
1 Plan kick-off meeting 1 day Thu 6/16/22 Thu 6/16/22 DIMUTH
2 Remodeling of Asset List as per the SOW to the 2 days Fri 6/17/22 Sun 6/19/22 1 DIMUTH DIMUTH
FMM
3 Joint site visit to the VSB and inspection of the 1 day Mon Mon 2 DIMUTH/AK/HIA DIMUTH/AK/HIA
site with the current Contractor 6/20/22 6/20/22
4 Testing of Equipments and operation 1 day Tue 6/21/22 Tue 6/21/22 3 DIMUTH/AK/HIA DIMUTH/AK/HIA

5 Preparation of Deffect List of the VSB 1 day Thu 6/23/22 Thu 6/23/22 DIMUTH DIMUTH

6 Mobilisation meeting #1 - Presentaion of 1 day Fri 6/24/22 Fri 6/24/22 5 DIMUTH/JJ DIMUTH/JJ
GL-SYS-16 T1 Contract startup checklist
approved by CEO/MM

7 Initial Risk Assesment - HSE Challenges 2 days Wed 6/22/22Thu 6/23/22 4 HSEQ HSEQ

8 O & M Submission - VSB ( by MATAR) 1 day Tue 6/21/22 Tue 6/21/22 3 EMERSON / HASMY EMERSON / HASMY

9 As built Drawing in CAD format/ PDF 1 day Wed 6/22/22Wed 6/22/228 EMERSON / HASMY EMERSON / HASMY

10 Commissioning Data if any, 1 day Thu 6/23/22 Thu 6/23/22 9 EMERSON / HASMY EMERSON / HASMY

11 Parts identification & recommended spare 1 day Thu 6/23/22 Thu 6/23/22 10 EMERSON / HASMY EMERSON / HASMY
parts / list submission (by MATAR)
12 Maintenace Modifications submissions, if any 1 day Thu 6/23/22 Thu 6/23/22 11 AK/HIA AK/HIA
(ACTOR / MATAR)
13 QCDD - 1st Certificates for Life and Fire 1 day Thu 6/23/22 Thu 6/23/22 9 AK/HIA/EMERSON AK/HIA/EMERSON
Systems and QCDD Chesklists of the
maintenance activities performed.

14 1st and or Annual Certifications for LV/MV 1 day Thu 6/23/22 Thu 6/23/22 9 AK/HIA/EMERSON AK/HIA/EMERSON
done by KAHRAMA certified Company
15 3rd party inspections, Audit reports if any. 1 day Thu 6/23/22 Thu 6/23/22 9 AK/HIA/EMERSON AK/HIA/EMERSON

16 Specific Maintenance Recods, if any 1 day Thu 6/23/22 Thu 6/23/22 9 AK/HIA/EMERSON AK/HIA/EMERSON

17 Disposals if any 1 day Thu 6/23/22 Thu 6/23/22 9 AK/HIA/EMERSON AK/HIA/EMERSON

18 Preparation of tools 1 day Thu 6/23/22 Thu 6/23/22 DIMUTH DIMUTH

19 Staff Deployment Plan 1 day Thu 6/23/22 Thu 6/23/22 9 DIMUTH/JJ DIMUTH/JJ

20 Supply of minimum required tools, materilas, 1 day Thu 6/23/22 Thu 6/23/22 DIMUTH/STORES DIMUTH/STORES
PPE
21 Prepare Operational Delivery Schedules 1 day Thu 6/23/22 Thu 6/23/22 9 DIMUTH/JJ DIMUTH/JJ

22 Access passes and authorisation to enter the 1 day Thu 6/23/22 Thu 6/23/22 9 ADMIN ADMIN
facility
23 Contract startup check list to be performed 1 day Thu 6/23/22 Thu 6/23/22 9 DIMUTH/JJ DIMUTH/JJ

24 Mobilisation checklist to be performed 2 days Fri 6/24/22 Mon 6/27/2223 DIMUTH DIMUTH

25 Handing/Taking over 1 day Tue 6/28/22 Tue 6/28/22 24 JJ/HIA/AK JJ/HIA/AK

26 Staff engagement 1 day Fri 7/1/22 Fri 7/1/22

Task Project Summary Manual Task Start-only Deadline

Project: Mob Plan Split Inactive Task Duration-only Finish-only Progress