CRF - VSB Mobilisation Plan - Ver.1.0
CRF - VSB Mobilisation Plan - Ver.1.0
Finish Predecessors Resource Names Jun 12, '22 Jun 19, '22 Jun 26, '22 Jul 3, '22
Mode T W T F S S M T W T F S S M T W T F S S M T W
1 Plan kick-off meeting 1 day Thu 6/16/22 Thu 6/16/22 DIMUTH
2 Remodeling of Asset List as per the SOW to the 2 days Fri 6/17/22 Sun 6/19/22 1 DIMUTH DIMUTH
FMM
3 Joint site visit to the VSB and inspection of the 1 day Mon Mon 2 DIMUTH/AK/HIA DIMUTH/AK/HIA
site with the current Contractor 6/20/22 6/20/22
4 Testing of Equipments and operation 1 day Tue 6/21/22 Tue 6/21/22 3 DIMUTH/AK/HIA DIMUTH/AK/HIA
5 Preparation of Deffect List of the VSB 1 day Thu 6/23/22 Thu 6/23/22 DIMUTH DIMUTH
6 Mobilisation meeting #1 - Presentaion of 1 day Fri 6/24/22 Fri 6/24/22 5 DIMUTH/JJ DIMUTH/JJ
GL-SYS-16 T1 Contract startup checklist
approved by CEO/MM
7 Initial Risk Assesment - HSE Challenges 2 days Wed 6/22/22Thu 6/23/22 4 HSEQ HSEQ
8 O & M Submission - VSB ( by MATAR) 1 day Tue 6/21/22 Tue 6/21/22 3 EMERSON / HASMY EMERSON / HASMY
9 As built Drawing in CAD format/ PDF 1 day Wed 6/22/22Wed 6/22/228 EMERSON / HASMY EMERSON / HASMY
10 Commissioning Data if any, 1 day Thu 6/23/22 Thu 6/23/22 9 EMERSON / HASMY EMERSON / HASMY
11 Parts identification & recommended spare 1 day Thu 6/23/22 Thu 6/23/22 10 EMERSON / HASMY EMERSON / HASMY
parts / list submission (by MATAR)
12 Maintenace Modifications submissions, if any 1 day Thu 6/23/22 Thu 6/23/22 11 AK/HIA AK/HIA
(ACTOR / MATAR)
13 QCDD - 1st Certificates for Life and Fire 1 day Thu 6/23/22 Thu 6/23/22 9 AK/HIA/EMERSON AK/HIA/EMERSON
Systems and QCDD Chesklists of the
maintenance activities performed.
14 1st and or Annual Certifications for LV/MV 1 day Thu 6/23/22 Thu 6/23/22 9 AK/HIA/EMERSON AK/HIA/EMERSON
done by KAHRAMA certified Company
15 3rd party inspections, Audit reports if any. 1 day Thu 6/23/22 Thu 6/23/22 9 AK/HIA/EMERSON AK/HIA/EMERSON
16 Specific Maintenance Recods, if any 1 day Thu 6/23/22 Thu 6/23/22 9 AK/HIA/EMERSON AK/HIA/EMERSON
19 Staff Deployment Plan 1 day Thu 6/23/22 Thu 6/23/22 9 DIMUTH/JJ DIMUTH/JJ
20 Supply of minimum required tools, materilas, 1 day Thu 6/23/22 Thu 6/23/22 DIMUTH/STORES DIMUTH/STORES
PPE
21 Prepare Operational Delivery Schedules 1 day Thu 6/23/22 Thu 6/23/22 9 DIMUTH/JJ DIMUTH/JJ
22 Access passes and authorisation to enter the 1 day Thu 6/23/22 Thu 6/23/22 9 ADMIN ADMIN
facility
23 Contract startup check list to be performed 1 day Thu 6/23/22 Thu 6/23/22 9 DIMUTH/JJ DIMUTH/JJ
24 Mobilisation checklist to be performed 2 days Fri 6/24/22 Mon 6/27/2223 DIMUTH DIMUTH