GLS340 Survey Project Exercise: Control Network Calculations & Adjustment Question 1: Levelling
GLS340 Survey Project Exercise: Control Network Calculations & Adjustment Question 1: Levelling
GLS340 Survey Project Exercise: Control Network Calculations & Adjustment Question 1: Levelling
SURVEY PROJECT
Question 1: Levelling
Figure 1 illustrates the levelling carried out started at BM J11 and BM J12. Observations are made in
sequence from instrument stations I1, I2 and I3. Given that Reduced Level of BM J1111 is 36.565 m and
BM J1110 is 39.630 m.
B 1.439 m
P 1.232 m
BM J112
1.324 m 2.111 m
BM J11 I2 F 1.119 m
C
1.666 m
1.557 m 1.545 m
1.656 m D 1.701 m
A I1 S I3
1.341 m G
P
S
Figure 1
Question 2: Traverse
MS AN/AP/GLS340/JUN 2021 1
Bearing / Angle Line Final
Vertical Distance
Stn From To Distance
Final angle
Face Left Face Right Mean (m)
Bearing (m)
3 243°33’50” 63°33’50”
4 43°32’20” 223°32’30”
5 62°55’35” 242°55’35”
1 179°52’00” 359°52’00”
MS AN/AP/GLS340/JUN 2021 2
2 259°59’35” 259°59’25”
Line 1 – 2 observed =
Line 1 – 2 actual =
Through
Misclose in =
stn
MS AN/AP/GLS340/JUN 2021 3