Professional Documents
Culture Documents
Problems in Unit I
Problems in Unit I
Problems in Unit I
Degree B.Tech-IT
Earned Value Analysis in Project Cost Management: Calculate Cost Performance Index
(CPI) and Schedule Performance Index (SPI)
Earned Value (EV) Analysis leverages the Earned Value Fundamental Formula to determine the
project performance indices pertaining to project cost and schedule. Earned Value is part of the
Control Costs process group in Project Cost Management. Earned Value Performance formula
consists of:
Cost Performance Index (CPI): Represents the amount of work being completed on a
project for every unit of cost spent. CPI is computed by Earned Value / Actual Cost. A
value of above 1 means that the project is doing well against the budget.
Schedule Performance Index (SPI): Represents how close actual work is being completed
compared to the schedule. SPI is computed by Earned Value / Planned Value. A value of
above one means that the project is doing well against the schedule.
Abbreviations
Formulas
The following formulas will be used for the following examples.
SPI = EV/PV
We will see how healthy the project is by computing the CPI and SPI.
BAC = $900,000
AC = $100,000
The Planned Value (PV) and Earned Value (EV) can then be computed as follows:
Cost Performance Index (CPI) = EV / AC = $90,000 / $100,000 = 0.90. This means for every $1
spent, the project is producing only 90 cents in work.
Schedule Performance Index (SPI) = EV / PV = $90,000 / $135,000 = 0.67. This means for every
estimated hour of work, the project team is completing only 0.67 hours (approximately 40
minutes).
Interpretation: Since both Cost Performance Index (CPI index) and Schedule Performance
Index (SPI index) are less than 1, it means that the project is over budget and behind schedule.
This example project is in major trouble and corrective action needs to be taken. Risks
management needs to kick-in.
Interpretation: Since Cost Performance Index (CPI) is less than one, this means the project is
over budget. For every dollar spent we are getting 60 cents' worth of performance. Since
Schedule Performance Index (SPI) is more than one, the project is ahead of schedule. However,
this has come at a cost of going over budget. If work is continued at this rate, the project will be
delivered ahead of schedule and over budget. Therefore, corrective action should be taken.
Apart from computing the Cost Performance Index (CPI) and Schedule Performance Index
(SPI), we can calculate the earned value cost and schedule variance.
Measuring against a baseline gives you a variance. In projects, the cost variance and schedule
variance tell us whether our project is on-budget and on-time. we will see how Earned Value
Management aids in project cost variance and schedule variance computations.
Earned Value Management Variance Formulae leverage the Earned Value Management
Fundamental Formulae (BAC, AC, PV, and EV) to determine the variances pertaining to project
cost and schedule. Earned Value Management Variance formulae consist of:
Cost Variance (CV): This is the completed work cost when compared to the planned cost. Cost
Variance is computed by calculating the difference between the earned value and the actual cost,
i.e. EV – AC. As you can deduce from the formula, Cost Variance will be negative for projects
that are over-budget. Monitoring project cost variance is critical to ensuring the project is
delivered on budget. Using realistic project estimations is a good start to ensuring there isn't
significant cost variance.
Schedule Variance (SV): This is the completed work when compared to the planned
schedule. Schedule Variance is computed by calculating the difference between the
earned value and the planned value, i.e. EV – PV. A positive Schedule Variance tells you
that the project is ahead of schedule, while a negative Schedule Variance tells us the
project is behind schedule. Monitoring Schedule Variance is critical to delivering the
project on-time.
Earned value cost and schedule variances are part of the Control Costs process group.
Example 1
Interpretation: Since the Project Cost Variance is negative, this means the project is over-
budget. Since Schedule Variance is negative, the project is behind schedule. This example
project is in major trouble and corrective action needs to be taken to get it back on track. Earned
Value Management cost variance and schedule variance will help you identify a project in
trouble. To fix the problem areas is a different ball game. You will need to use effective risk
management. In this case, the project schedule variance can be controlled by using the critical
path method.
Example 2
Earned Value is the percentage of work covered by the PV, or planned value.
For example, if the PV is $1,000 and the project is 20% complete, the EV would be calculated
as,
For example, in addition to the values stated in the previous example, if the Actual Costs on
project completion for that phase is 20%, or $800, then the performance ratio would be:
If the Performance Ratio is more than 100%, it means the project exceeds the budget (negative
expenditure), and if it is equal to 100%, it means that it is alongside the planned budget. In this
case, it is well below 100%, at 80% and gives room for positive expenditure.