Professional Documents
Culture Documents
HKN-PLN-QA-0001 - Rev C
HKN-PLN-QA-0001 - Rev C
ib ~ I I {..---
V
D.Y. W~~ 17
\,V
c 30-Sep.-2015 Revise and Resubmit S.l. Kwon N.W${J g
Initial Release
A 31-0ct.-2013 S.Y. Yi S.Y. Yi J.W. Ko
( Issued for Approval )
Table of Contents
9.0 ATTACHMENT
APPENDIX
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
Reference /
No. Engineer's Comments Contractor's Reply
Page No.
@ DRR 1093 on 29-Sep-2014 _ Status C
Test certificates and assurances
are required:
Manufacturer's product conformity Page No. 26 &
1 Included.
certificates to the specification and 30
Testing equipment calibration test
reports from independent party.
Under 7.5.2.1 (page 23); following
to be included.
i. Obtaining approval for all
material before purchasing.
ii. Submitting product compliance
test report and comparison against
2 Included. Page No. 26
specification.
iii. Relevant checklist.
Refer the annotated document for
further comments.
Please re-submit with these
comments incorporated.
If quality policy and objectives are
changed this QMP shall be re-
3 Included. Page No. 10
issued to the Engineer for
approval.
Include section of all internal and
external auditing processes and
4 Included. Page No. 30
how the results will be conveyed to
the Engineer
State how often internal audits will
5 Included. Page No. 30
take place and to what extent.
State how often audits will be
carried out on Sub Contractors and
6 Included. Page No. 30
how this information will be
relayed.
All drawings used for construction
7 Included. Page No. 28
must be approved as “A” Status
State how your sub-contract labour
are informed of document status
8 approvals before site set up and Included. Page No. 14
works starting bearing in mind they
have no access to Aconex.
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
2.1.1 This Quality Management Plan and its supporting Quality System Procedures define the
quality system to be used by HYUNDAI-KEANGNAM-NAWALOKA Joint Venture (HKN JV)
for Waterfront Integrated Resort Project.
2.1.2 This plan complies also with the objectives and directives of quality policy and
requirements and prescription of BS EN IS0 9001. It also sets out specific quality practices,
description of organization, roles and responsibilities.
2.1.3 This plan is relevant to all quality affecting activities for Engineering, Procurement
Construction of HKN JV’s scope of works.
2.1.4 All quality affecting activities relates to other staff elements of HKN JV’s scope of works,
including shop drawing submittal, as-built drawings, revision of contract, etc., shall be
complied with Quality Management System. (Quality Management Plan and Quality
System Procedures)
2.1.5 The Quality Management Plan (QMP) and relating Quality System Procedures (QSP) shall
be given to subcontractor by the time of biding or kick-off meeting for accomplishing quality
control on the job site and off-site activities.
2.1.6 The detailed Inspection and Test Plan (ITP) shall be prepared and approved from the
Engineer to proceed the inspection and test on the job site prior to commencement of any
activity in accordance with Quality System Procedure for Field Inspection and Test.(QSP-
010)
2.2 PURPOSE
2.2.2 To describe how quality activities will be performed on the Waterfront Integrated
Resort Project.
2.2.4 This plan is not, however, intended to provide a complete detailed explanation of the all
works to be implemented during the execution of the project activities.
2.3 REFERENCE
2.4.1 The preparation of Quality Management Plan is performed by QA/QC Manager, the
verification and the approval is given by the Project Director.
2.4.2 This QMP shall be revised and resubmitted to the Engineer if the Quality Policy and
Objectives change.
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
The Quality Management Plan will be distributed by the Project Director to all members of
Project Team for implementation.
2.5.1 It is the responsibility of the managers of each project team to distribute the Quality
Management Plan.
2.5.2 All project teams are responsible for keeping their copy of the Quality Management Plan
up-to-date.
3.1 CLIENT ;
Waterfront Properties Ltd. that receives a product; Waterfront Integrated Resort
3.3 ORGANIZATION ;
Group of people and facilities with an arrangement of responsibilities, authorities and
relationships
3.12 PROCESS ; Set of interrelated or interacting activities which transforms inputs to outputs
4.1.1 Resources needed for the quality management system shall comply with Section 6.0,
Resource Management.
4.1.2 Improvement methods shall be established according to the process of corrective action,
preventive action or management review if any improvement is needed on the results of
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
4.2 DOCUMENTATION
4.2.2 Documentation for quality management system is shown on the Attachment 9.1, Hierarchy
of Quality Management System Documentation.
4.2.3 Quality policy and objectives shall be understood, implemented and maintained at all levels
of the organization
4.2.4 Core success factors and key performance indicators (CSF/KPI) shall be established.
4.2.5 Processes that need to be clearly understood, managed and improved in effectiveness as
well as efficiency shall be defined and identified by Process Control Procedure (QSP-
001).
4.3.1 Quality Management systems are described in the Quality Management Plan (QMP) and
supporting Quality System Procedures, Method Statements and Inspection & Test Plans
(ITP) etc.
4.3.2 In order to extend the control of activities to the subcontractor level, it shall be the
responsibility of the subcontractor to adhere to the requirements of this Quality
Management System. HKN JV shall verify compliance with the quality management
system by implementation of a quality audit program.
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
4.3.3 Those aspects of the quality management system of Sub-contractors’ and Vendor’s that
affect the service/product being procured for the project shall be monitored by HKN JV.
4.4.1 The elaborated Quality System Procedure Matrix of this Quality Management Plan is a
tabular document identifying quality activities and the controlling procedures to be used for
this project, but not limited to. (Refer to Attachment 9.3, List of Quality System Procedures)
4.5.1 Documents shall be controlled and maintained in accordance with Document and Data
Control Procedure (QSP-002).
4.5.2 Documents prior to issue shall be checked, reviewed and approved. Those documents
may be shop drawings, instructions, method statements, quality plan, ITP, purchase
orders, test procedures, design changes, etc.
4.5.3 Void documents shall be destroyed or discarded unless specific instructions for returning
them have been provided. If it is desirable to hold a void document for reference purpose, it
shall be immediately marked to indicate that it has been superseded (e.g. “VOID” or
“Superseded”).
4.5.4 Only the latest and approved documents shall be used for construction work.
4.5.5 Each document shall have the title and document number, the revision number, the
signature by an authorized person, the date and the description as a minimum.
4.5.6 On receiving revised documents, the document controller shall promptly destroy or discard
the obsolete documents after replacing them with new ones to assure that only the latest
documents are used for the construction work.
4.5.7 Documents status shall be informed to the Sub contractor via Aconex in accordance with
QSP-002.
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
4.6.1 Quality records are documents which provide a written evidence for the quality or quality
activities, such as various kinds of inspection or test records, qualification certificates, audit
records, calibration report, NCR, PCAR, reports of training, etc.
4.6.2 Quality records shall be controlled in accordance with Quality Record Control Procedure
(QSP-009).
4.6.4 Records shall be produced in accordance with the relevant procedure, specification, ITP,
etc.
4.6.5 QA/QC manager shall ensure that all quality records shall be properly filed and controlled
until hand-over to Client.
5.1.1 The following shall be reviewed to ensure that the Client’s requirements are met and
enhanced;
● To determine the requirements related to the project.
● To communicate effectively with Client.
● To monitor and measure the Client satisfaction or dissatisfaction through the
followings;
1) Measurement indicator
- Project schedule and material delivery status.
- HSE and quality matters
- Internal HKN JV management policy
5.2.1 The quality management representative (hereinafter QA/QC manager) shall distribute and
control the quality policy and objectives which are established by the project director.
5.2.2 The quality objectives shall be measurable and consistent with quality policy.
5.2.3 Development of core success factors that are necessary for achieving quality policy and
objectives shall be based on Company’s requirement, quality policy and objectives.
5.2.4 Quality policy and objectives would be revised in case of the followings.
● on change of quality policy and objectives by project director
● on generation of revision reason through management review
5.3.1 Set-up of core success factors and key performance indicator shall be established and
implemented in accordance with this plan.
5.3.2 The quality management system is covered under “Quality System Procedures” (Refer to
Attachment 9.3, List of Quality System Procedures)
5.4.1 The Responsibility and authority for HKN JV project organization are hereafter described in
terms of implementation of quality management system.
5.4.10 No QAQC personnel, either of HKN JV or his subcontractor shall take any direction from
the HKN JV Site team that works under the authority of the HKN JV Project Director. The
area responsibilities of HKN JV are shown on the attachment 9.2, Project QAQC
Organization Chart.
5.5.1 For project communication, meetings may be held by daily, weekly and monthly in order to
review the project status/progress/interference, identify the problem areas and establish
plans for corrective actions and preventive measure in future also.
5.5.2 Using the following media or communication, the common information may be
accomplished each other.
5.6.1 Management review meeting will be carried out annually (a half yearly if necessary) under
the direction of project manager/director. The following subjects should be included, but not
limited to, in the meeting of management review.
● Evaluating the degree of Client satisfaction.
● Status and results of project objectives and improvement activities.
● Results of audit or self-assessment of the organization.
● Results of Risk Management
● Analysis of quality trend (NCR, PCAR)
● Implementation of Core Success Factor & Key Performance Indicator
6.1.1 Each section manager shall identify and plan the essential resources needed for
implementation of quality management system.
Building, workspace,
Project Project
transport and Each Section
Control Director
Infrastructure communication
Project Project
Process equipment Each Section
Control Director
Project Project
Work environment Each Section
Control Director
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
6.2.1 Personnel performing work affecting product quality shall be competent on the basis of
appropriate education, training, skills and experience in accordance with this training
procedure and/or the relevant method statements.
6.2.2 Each section managers are responsible for providing the required job training to all levels
of personnel within his organization.
6.3 INFRASTRUCTURE
6.3.1 The infrastructure shall be properly planed and prepared. The plan shall be documented
and maintained with proper form.
6.4.1 Project work environment shall be determined and managed to meet health and safety
requirements and regulations, including following;
● Project work condition and environment
● Protective equipment
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
● Work facility
● Field work environment (sanitation, cleanliness, noise, vibration, lighting, temperature,
humidity, etc.
6.4.2 HSE planning and implementation shall be carried out in accordance with the relevant
procedures.
7.1.1 Required verification, validation, monitoring, inspection and test activities specific to the
product and the criteria for product acceptance shall be carried out in accordance with
section 8.0, Measurement, Analysis and Improvement.
7.1.2 Records needed to provide evidence that the realization processes and resulting product
meet requirements shall be carried out in accordance with Quality Record Control
Procedure (QSP-009).
7.2.1.1 Each section shall provide procedures, method statements, instruction, etc. needed for
performance of the specific job and/or quality affecting activities according to determined
requirement.
7.2.2.1 Each section manager shall review the requirements related the product. This review shall
be conducted prior to the commencement of the relevant works considering the following;
● Facilities, technology, material and resources to meet requirements
● Constructability
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
7.2.2.3 Any questionnaires and difference between the contract documents shall be resolved for
clarification. Each team manager can raise the item needed to be solved for important
matter at technical adjustment meeting which takes place biweekly.
7.2.2.4 Any change to the contract document shall be reviewed by the related party and QA/QC
section to evaluate any quality affected changes or amendment which is approved by the
Project Director.
7.3.1 The contract and relevant annexes will be reviewed by HKN JV in order to: Define basic
choices and operational strategies to meet the requirement; Provide guidelines for the
subsequent activities:
- Ensure everyone understanding of contract requirements
- Formally record any contract clarifications
7.4.1.1 Engineering Manager shall draw up plans that identify the assignment and responsibility for
each design and development activity in conjunction with the project controls and planning
departments.
7.4.1.2 Engineering Manager is responsible for maintaining the project design documents, and
controlling any changes.
7.4.2.1 Each Engineering Lead Engineer shall be kept fully updated on the planning of the design
and development inputs relating to project requirements based on the contract and feed
documents and drawings. These inputs shall be reviewed by Engineering Manager for
adequacy.
7.4.2.2 Design Engineer shall prepare detailed design drawings and analysis report which shall;
● Meet the design input requirements
● Contain or reference acceptance criteria
● Conform to appropriate regulatory requirements whether or not these have been stated
in the input information
● Identify those characteristics of the design that are crucial to the safe and proper
function of the product
7.4.3.1 Design documents shall be reviewed by competent design engineer other than those who
performed original design to verify the correctness of the original design documents.
7.4.3.2 Design and development verification shall be performed by means of one or more of
followings.
● Design review
● Carrying out alternative calculations in necessary
● Comparing new design with a similar proven design if available
7.4.3.3 The results of design and development verification shall be documented and maintained.
7.4.3.4 Any comment resulting from design and development verification activities shall be
resolved and updated with drawing revision.
7.4.3.6 Design and development change is carried out by originator or field design engineer.
7.4.3.7 Design and development change required by the site condition shall be reported to the
originated department.
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
7.4.3.8 Design and development change shall be reviewed and approved by the relevant
organization initiating original documents and by the Client if required. Field design change
will be submitted by field engineer or field design engineer and shall be approved by the
Client when required. Approved change shall be distributed as per applicable document
distribution matrix.
7.4.3.9 Engineering Manager or his designee is responsible for preparing as-built drawings. As-
built drawings shall show in detail the manner in which the works were actually constructed
and shall reflect all changes, additions, corrections or revisions made during construction.
7.5 PURCHASING
7.5.1 General
Procurement shall be implemented in accordance with the Procurement Control
Procedure (QSP-004). Preparation and submission of documents related to BOI (Board of
Investment of Sri Lanka) for all permanent materials and equipment supplied by HKN JV
and sub-contractors, vendors are required.
7.5.3.1 Purchasing information shall be made in accordance with the Procurement Control
Procedure (QSP-004).
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
7.5.3.2 Shop inspection and test requirements during manufacturing shall be prepared and
provided to Vendor.
7.5.3.3 Shop inspection and test requirements shall include the following as a minimum;
● Intended HKN JV’s witness and hold points
● Description and frequency of inspection and test
● References
● Quality records to be issued, etc.
7.5.3.4 The changes of the procurement specifications affecting quality shall be forwarded to
Vendors.
7.5.4.1 Kick-off meeting and pre-inspection meeting will be held at Vendor’s premise before
commencement of the relevant fabrication and/or work as required.
7.5.4.2 Inspection notice, verification and coordination between HKN JV, Client and Vendor will be
carried out.
7.5.4.4 HKN JV inspector shall inspect and witness the defined witness and hold points specified
in the approved Inspection and Test Plan (ITP).
7.5.4.6 Any non-conformance found during Vendor inspection or receiving inspection shall be
documented and controlled in accordance with Non-conformance Product Control
Procedure (QSP-006).
7.5.4.7 Handling, storing, packing and delivery shall be carried out in accordance with Material
Control Procedure and Shipping and Packing Instruction.
7.5.4.8 The requirements for handling, storage, packing and delivery specified in the applicable
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
7.5.4.9 Items shall be stored in the warehouse or in the segregated areas under condition as
recommended by the manufacturer to prevent any damage.
7.6.1 When procedures, ITP, method statement, etc. are required, the following shall be
considered to control production and service provision.
● Project specification requirements
● Construction method, procedure and resources and equipment to be used
● Extent of inspection and test
● Constructability
● Reporting forms, etc.
7.6.2.1 Special processes are those of which the quality is largely depend on the inherent skill of
the operator and cannot be completely assured only by the inspection on the completed
item, such as fresh/hardened concrete test, field density/plate load test, soil reinforcement
steel test, raw material test of concrete, etc. Those special processes shall be tested and
verified by approved third party.
7.6.2.2 Special processes shall be performed by approved third party’s personnel in accordance
with applicable code, standard, specification and other special requirement.
7.6.3.1 Receiving inspection shall be carried out in accordance with Material Control Procedure.
7.6.3.2 The receiving inspector shall check the condition of product, dimension, identification,
cleanness, covers, damages made during transportation.
7.6.4.1 All the construction work shall be conducted in accordance with the approved “Status A”
drawings, specifications, procedures, method statements and instructions.
7.6.4.2 QA/QC manager or his designee shall prepare inspection and test plans in accordance
with Field Inspection Procedure (QSP-010).
7.6.4.3 For the witness/hold points for Company, designated personnel shall notify and arrange for
inspection or test in advance.
7.6.4.4 The results of inspection and test shall be documented and controlled in accordance with
Quality Record Control Procedure (QSP-009).
7.6.5.1 Where appropriate, material which is required for identification and traceability shall be
identified.
7.6.5.2 The items shall be identified using color-coding or physical marking or tagging, signage on
the items from the initial receipt to the final installation.
7.6.6.1 Each section manager shall preserve the conformity of product during internal processing
and delivery to the intended destination. This preservation includes identification, handling,
packaging, storage and protection. Preservation also applies to the constituent parts of a
product.
7.6.6.3 The quality of materials shall be maintained from the receipt to the final destination.
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
7.7.1 Measuring and test equipment shall be calibrated in accordance with Monitoring and
Measurement Procedure (QSP-005).
7.7.2 The calibration records shall be traceable to the equipment and maintained at work site.
7.7.3 Testing equipment calibration test reports shall be obtained from an independent party.
7.7.4 QA/QC manager is responsible for preparing and maintaining the list of calibrated
measurement and test equipment.
8.1.1.1 Client’s complaints shall be collected, measured and analysed through the following
● Letters from Client
● Meeting with Client
● Instruction from Client
● Public grievance
● Quality Observation / NCR
8.1.1.2 Each section manager is responsible for feedback of corrective action and continual
improvement for Client’s complaint.
8.1.1.3 Outstanding correspondences and/or item to be feedback to Client shall be logged and
followed up.
8.1.2.1 The internal quality audit for project quality system shall be annually conducted by Quality
Assurance Team in HKN JV. The project internal audit will be performed annually by
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
independent QA Team from Head Office organization. The copy of audit result shall be
forwarded to the Engineer for information.
8.1.2.2 The detailed execution method for internal quality audit shall be complied with Internal
Quality Audit Procedure (QSP-008).
8.1.2.4 Audit personnel shall be qualified according to the qualification procedure of Head Office.
8.1.2.5 Records
● Corrective action shall be taken by responsible party and shall be verified the
adequacy of implementation by responsible audit personnel and recorded acceptance
of follow-up action in written.
● The audit records such as audit plans, audit reports and audit finding reports shall be
maintained and controlled.
8.1.3.1 Each section manager is responsible for monitoring and measuring for process based on
the planned core success process and achieved result of measurement of processes.
8.1.3.2 QA/QC manager is responsible for recommending and suggest the corrective action and
proper countermeasure for continual improvements.
8.1.3.3 Planned core process to be monitored shall be reviewed by once a year and reported to
project director.
8.1.4.1 Each section manager is responsible for supervising of notifying the designated inspection
points to Client in a timely manner.
8.1.4.2 QA/QC manager or his designee is responsible for performing or witnessing the inspection
and/or testing activities.
8.1.4.3 For site activities, witness of all inspections and tests shall be carried out in accordance
with Field Inspection Procedure (QSP-010).
8.1.4.4 Inspection and test requirements and acceptance criteria shall be based on the applicable
contract documents, specifications, codes or standards.
8.2.2 Each section manager shall ensure that product which does not conform to product
requirements is identified and controlled to prevent its unintended use or delivery.
8.3.2 The following activities will be mainly evaluated by using the statistical technique.
● Repair and performance rate per welder and trend of defect type for improving quality.
● Concrete compressive test, etc.
8.4 IMPROVEMENT
8.4.1.1 Each section manager shall continually improve the effectiveness of the quality
management system through the use of the quality policy, quality objectives, audit results,
analysis of data, corrective and preventive actions and management reviews.
8.4.1.2 Periodical improvement will be performed through the management review process.
8.4.1.3 Non-periodical improvement will be performed through the corrective action / preventive
action process.
8.4.2.1 Corrective action shall be controlled and recorded in accordance with Corrective and
Preventive Action Procedure (QSP-007).
8.4.2.2 In the case of a significant condition adverse to quality, the cause of the condition shall be
investigated and corrective or preventive actions shall be properly taken to preclude
recurrence.
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
8.4.2.3 All available information to detect, analyze and eliminate potential causes of nonconformity
shall be carefully managed and reported to project director for review and evaluation of
preventive action.
8.4.2.5 Corrective action is also determined on the trend analysis of the non-conformance report
(NCR) and repetitive deficiencies.
8.4.3.1 In case necessity of preventive action is required, it shall be controlled and recorded in
accordance with Corrective and Preventive Action Procedure (QSP-007).
8.4.3.2 Preventive actions shall be appropriate to the effects of the potential problems.
9.0 ATTACHMENT
Project
Quality Plan
LEVEL I Quality
System Procedures
Engineering Manager
SI Kwon 01-Nov-13
Site Coordinator
Trevor
27-Jan-15
Cardigan
QA/QC Manager
DY Won 13-Jul-15
QA Engineer QC Inspector
WMS/NCR/ITP Piling 1
Gayan
Maheesha Amit 10-Jun-14 25-Jul-14
Kularathne
QA Engineer QC Inspector
Record Control Piling 2
TBA Kasun Jayalath 11-May-15
Document QC Inspector
Document control RC 1
Asanga
Jayani Perera 30-Feb-15 17-Jun-14
Fernando
QC Inspector
Str. Steel 2
TBA
QC Inspector
Finishing 1
TBA
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
Attached,
QSP-001 Process Control Procedure
Submitted for Approval
Attached,
QSP-008 Internal Quality Audit Procedure
Submitted for Approval
Building 6
Building 4 Office
Residential
Building 2
Hotel/Podi
Building
5
Building Building 1
3 Conference
Doc. No. QMP-001
Waterfront Integrated Resort
Rev. No C
Appendix
(QSPs included for Information)
~
Doc. No. QSP-001
Waterfront Integrated Resort
Rev. No c
W?te r ron i Proj Ect hlml - - - - - - - - - - - - - - - - + -- -+ - - - -- - 1
~ Al M0N0Is TuDI 0 HYUNDAI-KEANGNAM-NAWALOKA JV Sheet No. Sh. 1 of 9
J/,,..~
~ l ,; Trevor\ \
c 29-Sep.-2015 Revise and Resubmit D.Y. Wo~
/ 7 Card.1gan
-~
1~
I
B 9-Jul.-2014 Revise and Resubmit M.M . lm M.M. lm S.l. Kwon
Initial Release
A 31-0ct.-2013 S.Y. Yi S.Y. Yi J.W. Ko
( Issued for Approval )
TABLE of CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 DEFINITIONS
4.0 REFERENCE
5.0 RESPONSIBILITY
6.0 PROCEDURE
7.0 ATTACHMENT
Doc. No. QSP-001
Waterfront Integrated Resort
Rev. No C
Reference /
No. Engineer's Comments Contractor's Reply
Page No.
@ DRR 1113 on 10-Oct-2014 _ Status C
1.0 PURPOSE
This is to describe the preparation and control of processes to be used for quality
management system.
2.0 SCOPE
This procedure applies to processes to be established in accordance with HYUNDAI-
KEANGNAM-NAWALOKA (HKN JV) quality management plan.
3.0 DEFINITION
3.1 Process
Set of interrelated or interacting activities which transforms inputs into outputs
3.2 Product
Result of a process
3.3 HKN JV
HYUNDAI-KEANGNAM-NAWALOKA Joint Venture
3.4 ENG
Balmond-Studio
3.5 EMP
Waterfront Properties (PVT) Ltd.
4.0 REFERENCE
4.1 HDEC Corporate Quality Management Manual
4.2 HKN JV Project Quality Management Plan
4.3 Quality System Procedure QSP-002 Document and Data Control Procedure
4.4 Quality System Procedure QSP-009 Quality Record Control Procedure
4.5 Specification section B50
Doc. No. QSP-001
Waterfront Integrated Resort
Rev. No C
5.0 RESPONSIBILITY
5.1 Quality manager is responsible for definition of process to be mapped based on HKN JV
Quality Management Manual.
5.2 Each section manager is responsible for the preparation, review and approval for the
process maps to be controlled.
6.0 PROCEDURE
6.1 General
6.1.2 However in instances where the items are included in a procedure or method statement
which is already established, they don’t need to be established additionally.
6.1.3 Carrying out Process mapping allows Processes to be easily analysed and understood.
Gaps/ shortcomings in the process can be easily identified and amended.
6.1.4 Deficiencies in terms of QA/QC can be addressed and steps can be taken to improve the
process by introducing more testing or inspections where necessary.
Doc. No. QSP-001
Waterfront Integrated Resort
Rev. No C
1 2 3 4
1. Project Codes
2. Core Processes classification Codes
6.3 Revisions
6.3.1 Changes of the process mapping shall be implemented by the responsible personnel, and
reviewed and approved by the same organization that performed the original review and
approval.
6.3.2 Checklists shall be revised case by case depending on the changes that affect a process.
6.4 Distribution
6.4.1 All approved process mapping shall be distributed to relevant functions in accordance with
document and data control procedure (QSP-002).
7.0 ATTACHMENT
7.1.1 Form QSP-001-01 Process Mapping Sample
Document and Data Control Process
-
Revise Document
Use Approved
Create Document According to
Document
Comments
Subcontractor
Not Approved Forward to Sub through Aconex
not ok
Check Conformance
with Specification,
ok Prepare Document for ok Check Engineer's
Approved Circulate to relevant
Review Document
Standards (Codes and Submission Comments Departments
HKN
Testing), etc.
ok
Process Mapping(sample for reference)
Aconex
Quality System Procedure for Process Control
Document reviewed
Waterfront Integrated Resort
by the Engineer
Engineer
HYUNDAI-KEANGNAM-NAWALOKA JV
Notes:
Rev. No
Doc. No.
- The process depicted above is a general process, which mainly shows how the document process is used to cascade information within HKN, to Sub-contractors as well as to the Engineer.
Sheet No.
- "HKN" mentioned above refers to the relevant department within HKN (i.e. Construction, Mechanical, Electrical, QA/QC, Planning, etc.).
- "Document" mentioned above refers to all types of documents used on this project (i.e. Drawings, Method Statements, Material Approvals, etc.).
- The department in charge of the steps checking conformance, preparation and review depend on the type of document that is being prepared.
- All quality related documents will be reviewed by the QA/QC department.
C
- The final step of issuing a document "For Construction" only applies to shop drawings.
Sh. 9 of 9
QSP-001
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No c
Vi'a erfr ont Pr oj ect learn l--- - - - - - - - - - - - - - + - - - - - + - - -- - 1
BALMOND/ST UO fO HYUNDAI-KEANGNAM-NAWALOKAJV SheetNo. Sh.1of19
/ .d /(i?~
~
.<_ l:::::.. r- \-
c 6-Aug .-2015 Revise and Resubmit D.Y. ~ ~ T. Cardig1Fi S.l. Kwon
/
Initial Release
A 31-0ct.-2013 S.Y. Yi S.Y. Yi J.W. Ko
( Issued for Approval )
TABLE of CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 DEFINITIONS
4.0 REFERENCE
5.0 RESPONSIBILITY
6.0 PROCEDURE
7.0 ATTACHMENT
Reference /
No. Engineer's Comments Contractor's Reply
Page No.
@ DRR 1104 on 10-Oct-2014 _ Status C
State the process used to
cascade all this information to
Please refer to attached flow
1 your sub-contractors and any Page. 19
chart.
sub-contractors they deploy on
site.
Shop Drawings, Method
Statements etc...are required to
be checked by the Contractor's
relevant disciplinary section and
QA/QC section to verify the
accuracy and compliance. Then
Comment has been reflected in
2 such documents should be Page. 19
the flow chart.
submitted to the Engineer for
approval. The documents which
and approved to status „A‟ can
be issued for construction after
the Contractor's document
control procedures as stated.
There is a contractual
requirement not to transmit any
4 design documentation across Included. Page. 9
Sri Lanka borders in physical
form (has to be emailed, etc).
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
1.0 PURPOSE
This procedure is to describe HYUNDAI-KEANGNAM-NAWALOKA Joint Venture (HKN
JV) Document control system relevant to issuance, approval, distribution, revision and
filing of document and data.
2.0 SCOPE
2.2 All document control will be implemented in accordance with project administration
requirements.
3.0 DEFINITIONS
3.1 Document
Information and its support medium, such as HKN JV project quality plan, quality
procedure, method statement, quality plan for site activity, ITP, process map, record,
specification, drawing, report and standard, etc.
The medium may be paper, magnetic, electronic or optical computer disc, photograph or
master sample, or a combination thereof.
3.9 HKN JV
HYUNDAI-KEANGNAM-NAWALOKA Joint Venture
4.0 REFERENCE
4.1 HKN JV Project Quality Management Plan
4.2 Quality System Procedure QSP-006 Non Conformance Product Control
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
5.0 RESPONSIBILITY
5.1 The Project Director shall approve the HKN JV Project quality Management Plan.
5.4 The document generating section is responsible for distributing the documents to all
section where activities essential to the effective functioning of the quality system are
performed.
5.6 The Sub-Contractor is responsible for creating documents and submitting to HKN for
review. They are also responsible for ensuring that only approved documents are being
used on site.
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
6.1 General
6.1.1 The documents affecting quality to be controlled according to this procedure are as
follows, but not limited to;
● HKN JV Project Quality Management Plan, Quality System Procedure, Method
Statement, NCRs, ITP, checklists, etc.
● Contract Documents
● Drawings
● Contractor issued document, such as submittals, RFI, etc. thru ACONEX.
6.2 Identification
6.2.1 Each document shall have the title, the revision number and its date.
6.2.2 The documents to be controlled shall be identified with a unique document number on the
cover sheet.
6.2.3 Documents on the project shall be identified and numbered in accordance with HKN JV
numbering system and project numbering system established by EMP / ENG.
6.3.1 All quality affecting documents shall be reviewed, approved and issued in accordance
with the relevant project procedures (and this procedure as supplementary) by the
relevant departments.
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
Status A Approved
Status B Approved with Comments
Status C Revise and Resubmit
Status D Rejected
All documents used for construction purposes should be „Issued For Construction‟
Issued for Approval: Issuing documents that require approval from authorised project
participants.
Issued for Construction: Documents that are used for Construction purposes.
Issued for Information: Documents that are to be used for information purposes.
Issued for Review: Documents that require review by another project participant.
Issued for Tender: Documents that are to be used for tendering purposes.
6.4 Distribution
6.4.1 The approved documents and drawings shall be distributed to the relevant departments
within the HKN JV and Sub-contractors using the copy of transmittal (through Aconex)
and/or network (HKN JV Server) for application and use.
6.4.2 Upon receipt of documents, the recipient shall destroy the obsolete documents or keep
the documents with positive identification stamping (e.g. „VOID‟).
6.4.3 Only the latest documents Issued “For Construction” shall be used for construction work.
6.4.4 Design documentation shall not be transmitted across Sri Lankan boarders in physical
form (has to be emailed, etc.)
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
6.5.1 Changes to the documents shall be reviewed and approved by the same organizations
that performed the original review and approval unless specifically designated otherwise.
6.5.3 All obsolete copies shall be destroyed or suitably identified as per paragraph 6.4.2 of this
procedure by the recipient to assure that the use of outdated documents is precluded.
6.5.4 The revised documents shall be distributed in the same manner as the original.
6.6.1 All documents shall be clearly identified with the relevant code, revision and type of
issue.
6.6.2 Originals and copies of all project documentation (produced by the various parties) are
coded and filed according to the internal filing system which is established.
6.6.3 Records of correspondence and documentation are kept and timely updated.
6.6.4 The document issued for approval shall be maintained on a computerized database of
document numbers and identification, to avoid future duplications.
6.6.5 The respective document controller shall produce and maintain a document register in
accordance with the requirements of the contract.
7.0 ATTACHMENT
※ All drawings except for vendor drawing shall include HKN JV document numbering in the
following format:
HKN - □□□ - OO - XX – 0 0 0 0 0 - A
Doc. Type :
DWG : Drawing
SPD : Shop Drawing
ABD : As-Built Drawing
Etc.
Discipline :
ST – Structural
AR – Architectural
EL – Electrical
ME – Mechanical
PB – Plumbing
Etc.
Activity :
ER : Earth
DR : Door
WD : Window
DT : Duct
Etc.
Serial Number :
5(five) digit numbering
“0 0 0 0 0”
DWG Series
- 00 Substructure
- 01 General Plans
- 03 Sections
- 05 Details
Building No.
Revision :
A, B, C …. Z, AA, AB ….
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
QSP-011-01
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
※ All Documents except for vendor documents shall include HKN JV document numbering in the
following format:
Doc. Type :
MST : Method Statement
MSB : Material Approval Request
TRP : Test Report
NCR: Non-Conformance Report
Etc.
Discipline :
ST – Structural
AR – Architectural
EL – Electrical
ME – Mechanical
PB – Plumbing
CN – Construction
Etc.
Serial Number :
4(four) digit numbering
0001, 0002, 0003, ……
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
Year
Department Code :
AD – Administration
CNST – Construction
EL – Electrical
ME – Mechanical
ENGR – Engineering
HS – Safety
PLAN – Planning
Etc.
Doc. Type :
MST : Method Statement
MSB : Material Approval Request
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
This Version
Authored by:
Name: Sub-Contractor
Role: *Initiator
(Field Engineer or
Signed:
QA/QC Engineer)
Date:
Name: HKN JV
Role: *Manager
(QA/QC Manager)
Signed:
Date:
Version History
Version Date Status Changes Overview
Table of Contents
Form @ QSP-002
Doc. No. QSP-002
Waterfront Integrated Resort
Rev. No C
Revise Document
Use Approved
Create Document According to
Document
Comments
Check Conformance
ok ok Approved
HKN
ok
Aconex
Document reviewed
by the Engineer
Notes:
- The process depicted above is a general process, which mainly shows how the document process is used to cascade information within HKN, to Sub-contractors as well as to the Engineer.
- "HKN" mentioned above refers to the relevant department within HKN (i.e. Construction, Mechanical, Electrical, QA/QC, Planning, etc.).
- "Document" mentioned above refers to all types of documents used on this project (i.e. Drawings, Method Statements, Material Approvals, etc.).
- The department in charge of the steps checking conformance, preparation and review depend on the type of document that is being prepared.
- All quality related documents will be reviewed by the QA/QC department.
- The final step of issuing a document "For Construction" only applies to shop drawings.
~
Doc. No. QSP-003
Waterfront Integrated Resort
Rev. No c
Wa !H ron t Proj ect lc.Jml -- - - - - -- -- - - - - --+-----+----- - --1
BA LMoN n1sT uo1o HvuNoAI-KEANGNAM-NAWALoKA Jv Sheet No. Sh. 1 of 11
~....._ lfi ~
'-~
c 22-Sep.-2015 Revise and Resubmit D.Y . W~ ~
/ Trevot-\J
"" Cardigan
s\~Kwon
B 9-JuJ.-2014 Revise and Resubmit M.M.Im M.M.Im S.l. Kwon
Initial Release
A 31-0ct.-20 13 S.Y. Yi S.Y. Yi J.W. Ko
( Issued for Approval )
TABLE of CONTENTS
1.0 PURPOSE
2.0 DEFINITIONS
3.0 REFERENCE
4.0 RESPONSIBILITY
5.0 PROCEDURE
6.0 ATTACHMENT
Doc. No. QSP-003
Waterfront Integrated Resort
Rev. No C
Reference /
No. Engineer's Comments Contractor's Reply
Page No.
@ DRR 1105 on 10-Oct-2014 _ Status C
Sub-contractor’s responsibilities
Page No. 6
Include a procedure of how included.
HKN JV will assess the training Training procedure has been
1 requirements of Sub amended to include Method
Contractors and implement it on statement workshops (main
site. process) for Sub contractors
Page No. 7
prior to carrying out work on site.
2.0 DEFINITIONS
2.2 HKN JV
HYUNDAI-KEANGNAM-NAWALOKA Joint Venture
2.3 ENG
Balmond-Studio
2.4 EMP
Waterfront Properties (Pvt) Ltd
3.0 REFERENCE
4.0 RESPONSIBILITY
5.0 PROCEDURE
5.1 General
5.1.1 Training shall be implemented in accordance with project Quality Management Plan.
5.1.2 Appropriate records of training shall be maintained in accordance with quality system
procedure QSP-009 Quality Record Control Procedure.
Doc. No. QSP-003
Waterfront Integrated Resort
Rev. No C
5.2.1 Annual Training Schedule (This procedure QSP-003, QSP-003-01) shall be established
based on the following.
● Increase of individual responsibility/ job engagement.
● Implementation of new regulations/ policies.
● Commencement of new main process on site.
● Major changes are introduced into the Quality Systems.
● New Technology, Machinery/Equipment are introduced.
● New Recruitment.
● Request from Owner, if necessary.
5.3 Training
5.3.1 QC Personnel responsible for inspection, examination and testing shall be sufficiently trained
in the following areas to assure their competence in performing the assigned works.
● Quality elements that are to be employed.
● Technical objectives of the project and code & standards that are to be used.
● On-the-job experience through actual performance of processes and inspection.
● General employee training.
● Document control and records management.
● Measuring and test equipment.
● Cleanliness and housekeeping inspection.
● Certification, that required training has been completed, will be provided for
each QC staff.
5.3.2 The work Method Statement, Quality System Procedures and Project Quality Management
Plan shall be used during the orientation as a training manual.
Doc. No. QSP-003
Waterfront Integrated Resort
Rev. No C
5.3.3 Sub-Contractors’ Management and Engineers as well as HKN Engineers shall attend a
Method Statement Workshop (for Main processes) prior to beginning work on site. Refresher
workshops shall be organised (if required) according to project needs.
5.4 Documentation
5.4.1 All the records related to the training of all staff and workers shall be documented and
maintained on file at respective office. They shall be reviewed case by case and the next
stage of training shall be decided accordingly.
5.4.2 All records related to the workshops (e.g. Workshop material, checklists, attendance record,
etc.) shall be maintained in an updated manner.
5.4.3 Training Attendance Roster (This procedure QSP-003, QSP-003-02) will be used whenever
the training is performed.
5.5.1 Persons performing the specific tasks affecting quality (e.g. Quality Auditor, Welders) shall be
qualified in accordance with the requirements specified in the relevant project specification
and procedures.
5.5.2 All records shall be maintained by the Main contractor in accordance with QSP-009.
5.5.3 The relevant Qualification documents shall be submitted to the Engineer for information.
6.0 ATTACHMENT
ATTENDANCE ROSTER
Presented by &
Place
Signature
Form QSP-003-02
Doc. No. QSP-003
Waterfront Integrated Resort
Rev. No C
Training Report
Item
Lecturer
Date Time
Relevant No of
Organization Attendees
Method of
□ Textbook, □ Lecture, □ Video, □ Practice, □ Others( )
Training
Attachment
Training
Contents
Form QSP-003-03
e Waterfront Integrated Resort
Doc. No.
Rev. No
QSP-00~
Initial Release
A 31-0ct.-2013 S.Y. Yi S.Y. Yi J.W. Ko
( Issued for Approval )
TABLE of CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 DEFINITIONS
4.0 REFERENCE
5.0 RESPONSIBILITY
6.0 PROCEDURE
7.0 ATTACHMENT
Doc. No. QSP-005
Waterfront Integrated Resort
Rev. No C
Reference /
No. Engineer's Comments Contractor's Reply
Page No.
1.0 PURPOSE
This procedure defines the procedure for the monitoring and measurement relevant to
inspection, testing, special process control and calibration of M&TE (Measuring and Testing
Equipment) to demonstrate conformity of product.
2.0 SCOPE
This procedure applies to the materials and works that are in HKN JV scope of works in final
Contract.
All activities relevant to inspection and testing shall be implemented in accordance with the
relevant procedures.
3.0 DEFINITION
3.3. Inspection
Conformity evaluation by observation and judgement accompanied as appropriate by
measurement, testing or gauging.
3.4. Test
Determination of one or more characteristics according to a procedure.
3.5. Review
Activity undertaken to determine the suitability, adequacy and effectiveness of the subject
matter to achieve established objectives.
3.6. HKN JV
HYUNDAI-KEANGNAM-NAWALOKA Joint Venture
Doc. No. QSP-005
Waterfront Integrated Resort
Rev. No C
4.0 REFERENCE
4.4. Quality System Procedure QSP-007 Corrective and Preventive Action Procedure
5.0 RESPONSIBILITY
5.1.2. Training the personnel to meet the specified requirements and practices.
5.1.3. Preparing and arranging the inspection and testing for the witness/hold points
designated in Inspection and Test plans (ITP) and or other documents to be
followed.
5.2.2. Ensuring that special process procedures have been prepared and approved.
Doc. No. QSP-005
Waterfront Integrated Resort
Rev. No C
5.2.4. Performing of inspections and tests as per the requirements specified in the
relevant documents.
5.2.6. Maintaining inspection status and the relevant inspection and test records.
5.2.7. Ensuring that M&TE used on site have valid calibration certificates and
maintaining the records in an updated condition.
5.3.2. Ensuring work is completed on time for field inspections to take place, and
ensuring work is in compliance with approved shop drawings, method statement,
specification, etc.
5.3.3. Submitting relevant documents to the Contractor prior to use of new equipment on
site, and ensuring M&TE certificates are maintained in an updated condition.
6.0 PROCEDURE
6.1.1. Special processes are those of which the quality is largely depend on the inherent
skill of the operator and/or personnel, and cannot be completely assured by
inspection of the completed item only, such as welding or non-destructive
examination.
6.1.2. Special process shall be implemented by the qualified personnel under the
approved procedure.
6.1.3. M&TE’s to be used for the special processes shall be tested, calibrated and
Doc. No. QSP-005
Waterfront Integrated Resort
Rev. No C
6.1.4. Documentation shall be maintained for the qualified personnel, processes and
equipment in accordance with QSP-009 Quality Record Control Procedure.
6.2.1. Material receiving inspection shall be carried out in accordance with project
administration requirements.
6.2.2. The receiving inspector shall check the condition of product, shelf life, dimension,
identification, cleanness, covers, damages made during transportation.
6.2.3. Any non-conformity during the receiving inspection shall be recorded on NCR in
accordance with QSP-006 Non-conformance Product Control Procedure.
6.2.4. Sample testing of received materials will be carried out according to the project
specification.
6.2.5. The results of the sample test will be submitted to the Engineer prior to using the
materials on site.
6.4. In-process inspection and testing at Factory shall be implemented by the responsible
personnel for the related items and documents in order to verify the compliance in accordance
with Applicable code and standard. The result shall be recorded in the Factory inspection report
(QSP-005-02 Factory Inspection checklist.
6.4.1. The calibration status of measuring and test equipment to be used during
inspection and test shall be verified by inspector, and calibration report shall be
submitted to the Engineer for information prior to use on site.
6.4.2. In-process inspection and testing at site shall be carried out in accordance with
project Quality Management Plan.
Doc. No. QSP-005
Waterfront Integrated Resort
Rev. No C
The responsible department personnel (Delivery / Hand-over) shall ensure the works is
inspected as planned and in accordance with project Quality Management Plan.
6.6.1. The status following inspection and test shall be maintained based on the test
code number given in quality control plan. Also all inspection and test reports shall
be collected and filed by test code number accordingly.
6.7.1. If the materials / products fail to meet the specified requirements, It shall be
controlled in accordance with QSP-006 Non-conforming Product Control
Procedure.
7.0 ATTACHMENT
8
Waterfront Integrated Resort
9
HYUNDAI-KEANGNAM-NAWALOKA JV
10
Quality System Procedure for Monitoring and Measurement
Rev. No
Doc. No.
Sheet No.
QSP-005-01
C
QSP-005
Sh. 10 of 11
Doc. No. QSP-005
Waterfront Integrated Resort
Rev. No C
Note:
Initial Release
~ ~. ~
A 31-0ct.-2013 S.Y. Yi S.Y. Yi J.W. Ko
( Issued for Approval )
TABLE of CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 DEFINITIONS
4.0 REFERENCE
5.0 RESPONSIBILITY
6.0 PROCEDURE
7.0 ATTACHMENT
Doc. No. QSP-007
Waterfront Integrated Resort
Rev. No B
2.0 SCOPE
This procedure applies to all departments and quality affecting activities.
3.0 DEFINITION
3.3 HKN JV
HYUNDAI-KEANGNAM-NAWALOKA Joint Venture
3.4 ENG
Balmond-Studio
3.5 EMP
Waterfront Properties (pvt) Ltd.
4.0 REFERENCE
4.1 HKN JV Project Quality Management Plan
4.2 Quality System Procedure QSP-006 Non-conformance Product Control Procedure
4.3 Quality System Procedure QSP-008 Internal and External Quality Audit Procedure
4.4 Specification section B50
Doc. No. QSP-007
Waterfront Integrated Resort
Rev. No B
5.1 Quality Manager is responsible for assuring that condition adverse to quality or
nonconformity are promptly identified and corrected.
6.0 PROCEDURE
6.1.1 QC Engineer shall determine the necessity of a PCAR after a problem has been identified.
6.1.2 Source for identification of necessity for Preventive / Corrective Action Request
• Result of trend analysis of the Non-conformance Report (NCR) and repetitive
deficiencies
• Processes and operations affecting to quality
• Audit results
• Quality records, inspection and surveillance data
• Concerns of Customer or other involved organizations etc.
Doc. No. QSP-007
Waterfront Integrated Resort
Rev. No B
6.1.3 If the problem has been determined, the QC Engineer shall prepare the "Preventive /
Corrective Action Request (QSP-007-01)" identifying the condition adverse to quality,
recommended action to eliminate the cause, due date, signature and date and shall assign
the number.
Doc. Type :
PAR : Preventive Action Request
CAR : Corrective Action Request
Discipline :
ST – Structural
AR – Architectural
EL – Electrical
ME – Mechanical
PB – Plumbing
Etc.
Serial Number :
4(four) digit numbering
0001, 0002, 0003, ……
6.1.5 QC Engineer shall issue the original PCAR to the responsible organization with one copy
and register in PCAR Log (QSP-007-02).
6.2.1 Responsible organization shall determine the problem cause and implement the required
corrective action and provide a prompt response within the PCAR reply due date specified.
6.2.2 After completion of "Action Taken to Preventive Recurrence" on the PCAR, responsible
organization shall sign and date on the PCAR and return it to the Originator.
Doc. No. QSP-007
Waterfront Integrated Resort
Rev. No B
6.3.1 On the receipt of completed PCAR, QC Engineer shall determine whether the proposed or
implemented corrective action and/or preventive action is adequate and sufficient to
preclude recurrence of the problem originally identified.
6.3.2 If the corrective action response is satisfactory, QC Engineer shall verify the
implementation of corrective action.
6.3.3 If the corrective action response is not satisfactory, QC Engineer shall return the PCAR
with “Reason for Rejection”. In that case, the reply request date shall be recorded on
PCAR.
6.3.4 When the extension of response due date is required, responsible organization shall notify
the extended response due date to the QC department by use of formal correspondence
justifying the reason(s) why additional time is required.
6.3.5 PCAR Log (QSP-007-02) shall be utilized to allocate the PCAR numbers and track the
status of PCAR implementation.
6.4.1 On the completion of corrective action, QC Engineer shall sign and date on PCAR and close-
out the PCAR.
6.5 Record
6.5.1 PCAR shall be filed and maintained as QA Record according to QSP-009, Quality Record
Control Procedure.
6.6.1 Quality Manager should review the corrective /preventive actions taken on a annual basis
to identify the cases of any further recurrence/occurrence thereafter. He shall evaluate the
effectiveness of the relevant processes for those corrective actions from thereafter.
Doc. No. QSP-007
Waterfront Integrated Resort
Rev. No B
Description of Nonconformity
□ Accept
□ Reject / / / /
Form QSP-007-02
Remarks
Status
Response Close-out
Date Date
Recommended Action
to be Taken
NON-CONFORMANCE REPORT LOG
Item/Description
Non-conformity
Lacation
Organization
Responsible
Issued By
Issued
Date
PCAR No.
Serial
No.
1t
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No c
Wate1· rant Proj ect Team
BALMONDISTUOIO HYUNDAI-KEANGNAM-NAWALOKA JV Sheet No. Sh. 1 of 18
' V T~
( /11 (}__,_ .;-syv'
D.Y.~ ~ Cardigan
.P 1...7
revorV
c 29-Sep.-2015 Revise and Resubmit S.l. Kwon
Initial Release
A 31-0ct.-2013 S.Y. Yi S.Y. Yi J.W. Ko
( Issued for Approval )
TABLE of CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 DEFINITIONS
4.0 REFERENCE
5.0 RESPONSIBILITY
6.0 PROCEDURE
8.0 DOCUMENT
9.0 ATTACHMENT
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No C
Reference /
No. Engineer's Comments Contractor's Reply
Page No.
@ DRR 1110 on 14-Oct-2014 _ Status C
This QSP applies only to internal
Quality Audits carried out by HKN JV
QA department and HDEC Head
Include procedures for external / third Office.
1 party Quality Audits to be carried out External or Third party Quality Audits Page No. 5
by the Engineer. shall be carried out by a relevant and
qualified third party Auditor, in
accordance with a Third Party
Procedure.
1.0 PURPOSE
This QSP is to provide procedures for the effective planning and implementation of
internal quality audits on the quality management system.
2.0 SCOPE
This procedure is applicable to internal quality audits performed by HKN JV QA
department and HDEC Head office.
External or Third party Quality Audits shall be carried out by a relevant and qualified third
party Auditor, in accordance with a Third Party Procedure.
3.0 DEFINITIONS
3.1 Audit
Systematic, independent and documented process for obtaining evidence and evaluating
it objectively to determine the extent to which audit criteria are fulfilled.
3.4 Auditee
Organization being audited.
3.6 Auditor
A Person qualified and competent to conduct audits.
3.8 HKN JV
HYUNDAI-KEANGNAM-NAWALOKA Joint Venture
4.0 REFERENCE
4.1 HKN JV Project Quality Management Plan
4.2 Quality System Procedure QSP-003: Training Procedure
4.3 Quality System Procedure QSP-006: Non-conformance Product Control Procedure
4.4 Quality System Procedure QSP-007: Corrective and Preventive Action Procedure
4.5 Quality System Procedure QSP-009: Quality Record Control Procedure
4.6 Specification section B50
5.0 RESPONSIBILITY
necessary.
Improvement of Project Quality Management System in accordance with Quality
Audit.
6.0 PROCEDURE
6.1 General
6.1.1 Form and document numbering system relevant to audit shall be carried out in
accordance with paragraph 8.0 DOCUMENT in this procedure.
6.1.2 A numbering for the Internal Audit is not required, if they have their own numbering
system.
6.1.3 The Internal Audits shall be carried out annually (or more frequently if required) by QA
personnel from HKN JV and/or HDEC Head office (who is not forming part of the Site
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No C
organization that is involved in the Project). Internal audits are annually performed with
qualified personnel who were designated by Hyundai head office QA Director.
6.1.4 The Quality Audit may be performed in accordance with a plan and written checklists.
Audit checklist is intended for use as a guide and should not restrict the audit
investigation when findings raise further questions that are not specifically included in
checklist.
6.1.5 If findings of previous audits are reviewed prior to performing audit, verification for those
findings shall be performed during audit performance.
6.2 Planning the Audit based on the Pre-established Quality Audit Schedule
6.2.1 Finalized Quality Audit schedule shall be given to all the parties for QA/Internal Audit
prior to commencement of auditing.
6.2.2 Quality Manager assigns the auditor from his organization for QA Audit.
6.2.3 The notification of Quality Audit and check list prepared by the audit team shall be
forwarded to the Quality Manager for his review and approval prior to performing audit.
6.2.4 Lead auditor of QA/Internal Audit shall issue notification of quality audit, including such
information as the scope and schedule of the audit and name of auditors, to audited
organization.
6.2.5 Auditor shall prepare the check list based on the Contract requirements, applicable QA
program and the related codes and standards, which shall be reviewed and improved
on a case by case basis.
6.3.1 Prior to the Quality Audit, lead auditor opens pre-audit meeting with audit team and
auditee to confirm the audit scope, present audit plan, introduce the audit member, meet
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No C
the counteract, discuss the audit sequence and plan for the post-audit meeting, and
establish channel of communication.
6.3.2 The auditor shall ensure that the audit is conducted using the checklists in an objective
manner.
6.3.3 Upon detecting a non-compliance or deficiency, the auditor shall bring this to the
attention of the auditee.
6.3.4 The Quality Audit scope should be adequately covered before the post-audit meeting is
held.
6.3.5 The auditee shall ensure that full cooperation is granted throughout the audit.
6.4.1 Each auditor shall compile any audit findings and recommendations on an audit report
at the end of the Quality Audit.
6.4.3 Lead auditor conducts the post-audit meeting and discusses the audit findings based on
the audit report.
6.4.4 Lead auditor will provide a recommendation for the corrective action as necessary.
6.4.5 Prior to distribution, Quality Manager reviews and approves the audit report.
6.4.7 The Quality Audit report including NCR, CAR, PAR, etc., shall be submitted to Owner.
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No C
6.5.1 Auditee receives the audit report including PCAR and takes the corrective action as
required.
6.5.2 PCAR shall be implemented in accordance with QSP-007, Corrective and Preventive
Action Procedure.
6.6 Record
6.6.1 Audit records and reports are maintained and controlled in accordance with QSP-009,
Quality Record Control Procedure.
7.1 QA/QC Manager is responsible for managing the administration, scheduling, planning
and performing of vendor/sub-contractor audit activities.
7.2 QA/QC Manager is responsible for preparing audit schedule and audit plan on the basis
of vendor/sub-contractor qualification date and the schedule of production and
procurement for each vendor/sub-contractor audit at least on an annual basis, but not
limited to. In case of first qualification, Procurement procedure (refer to QSP-008-01,02)
may be substituted for Vendor /Sub-contractor Audit procedure.
7.3 The vendor audit shall be performed to verify compliance with all aspects of vendor’s
Quality System Program to supply item and services.
7.4 Unless otherwise specified in paragraph 7.0 of this procedure, all procedures of
scheduling, planning, performance, reporting, and follow-up action for vendor audit
activities shall be in the same manner as internal audit of this procedure.
7.5 Terms of audited organization of other paragraph in this procedure shall be considered
to the representative of vendor to be audited.
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No C
8.0 DOCUMENT
8.1 Audit records and reports are maintained and controlled in accordance with QSP-009,
Quality Record Control Procedure.
IA : QA/Internal Audit
VE : Vendor ( If required)
SC : Sub-contractor( If required) etc.
9.0 ATTACHMENT
9.1 Form QSP-008-01 Meeting Attendance Memorandum
9.2 Form QSP-008-02 Quality Audit Schedule
9.3 Form QSP-008-03 Audit Plan
9.4 Form Audit Report_SAMPLE
9.5 Form QSP-008-04 Audit Finding Report
9.6 Form QSP-008-05 Audit check list
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No C
□ Pre-audit □ Post-audit
3. DATE: 4. TIME:
5. PARTICIPANTS
ORGANIZATION
NO. NAME SIGNATURE REMARK
& JOB TITLE
1
10
11
12
13
14
15
Form QSP-008-01
9.2
Waterfront Integreated Resort Project HYUNDAI-KEANGNAM-NAWALOKA Joint Venture
Week 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Form QSP-008-02 Quality Audit Schedule
Quality System Procedure for Internal Quality Audit
Waterfront Integrated Resort
HYUNDAI-KEANGNAM-NAWALOKA JV
Sheet No.
Form QSP-008-02
C
QSP-008
Sh. 13 of 18
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No C
ISSUE DATE:
LEAD AUDITOR:
AUDITOR(S):
AUDIT SCOPE
1)
2)
APLICABLE DOCUMENTS
1)
2)
AUDIT SCHEDULE
1)
2)
Form QSP-008-03
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No C
TABLE of CONTENTS
I General
II Audit Summary
V Attachments
8. DOCUMENT
REQUIREMENT :
/ /
AUDIT TEAM LEADER / DATE A/QC MANAGER / DATE
RESPONSE BY AUDITED ORGANIZATION
/
AUDITOR / DATE
VERIFICATION
/ /
AUDIT TEAM LEADER / DATE QA/QC MANAGER / DATE
Form QSP-008-04
Doc. No. QSP-008
Waterfront Integrated Resort
Rev. No C
AUDIT CHECKLIST
Audit Description: Audited Organization / Person: Date:
10
Prepared by : Approved by :
Rev. No
QSP-009
c
1'.'2 erfr om Proj ect lnam l - - - - - - - - - - - - - - - - + - - - - + - - - -- - - t
eALMoN o1sT un o 1 HvuNDAI-KEANGNAM-NAWALoKA Jv Sheet No. Sh. 1 of 9
V", ~
IL/"
c 9-Sep .-2015 Revise and Resubmit D.Y. W~~ /_ -~ ~
7 T. Card1g , S.l. Kwon
/
Initial Release
A 31-0ct.-2013 S.Y. Yi S.Y. Yi J.W. Ko
( Issued for Approval )
TABLE of CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 DEFINITIONS
4.0 REFERENCE
5.0 RESPONSIBILITY
6.0 PROCEDURE
7.0 ATTACHMENT
Doc. No. QSP-009
Waterfront Integrated Resort
Rev. No C
Reference /
No. Engineer's Comments Contractor's Reply
Page No.
@ DRR 1111 on 13-Oct-2014 _ Status C
Please resubmit taking into
account the full requirements of
this unique project (e.g. the
Control procedure for Sub-
primary document control
1 contractor, vendor and BOI Page No. 7
system is Aconex). Please also
included.
define procedures for controlling
sub-contractor, vendor, BOI
procedures, etc.
1.0 Purpose
This procedure is to provide for identification, filing, retention time and disposition of quality
records.
2.0 Scope
This procedure applies to all quality records generated through the quality management
system operation as defined in the project quality management plan and the supporting
quality system procedures.
3.0 DEFINITION
3.1 Record
Document stating results achieved or providing evidence of activities performed
3.2 HKN JV
HYUNDAI-KEANGNAM-NAWALOKA Joint Venture
4.0 REFERENCE
4.1 HKN JV Project Quality Management Plan
4.2 Quality System Procedure QSP-002 Document and Data Control Procedure
4.3 Specification section B50
4.4 Aconex Project Configuration HDEC-PRC-PM-0001
Doc. No. QSP-009
Waterfront Integrated Resort
Rev. No C
5.2 Each Section Manager shall retain quality records generated in his section in
accordance with the project requirements until hand-over to ENG/EMP.
5.3 The person in charge of preparing quality records shall carry out the identification,
collection, indexing, filing, accessing, storage, maintenance and disposition of
quality records.
5.4 The Sub-contractor shall ensure that all completed original quality records are
handed over to the HKN QA/QC department (or relevant HKN department) for
record keeping. Copies of all quality records shall be maintained by the sub-
contractor.
6.0 PROCEDURE
6.1 General
6.1.1 Quality records shall be created and retained as written evidence for the quality
activities such as inspection and test reports, qualification certificates, audit
records, calibration reports, NCR, PCAR, checklists and reports of
training/education, etc.
6.1.2 Quality records shall be legible, readily identifiable and retrievable. They shall be
reviewed and improved case by case.
Doc. No. QSP-009
Waterfront Integrated Resort
Rev. No C
6.1.4 The control and filing of inspection and testing documents for purchased items will
be carried out in accordance with project specification.
6.1.5 Quality records shall be kept for historical purpose and every alternation on the
quality record shall be stuck through and counter-signed by the originator or
authorized person
6.2.1 Sub-Contractors shall be assessed for their suitability for this project by their pre-
qualification information. If they are found to be sufficiently qualified, the following
information will be submitted to the Engineer for Approval.
6.2.2 Vendors shall be assessed for their suitability for this project by their pre-
qualification information. If they (and their product) are found to be sufficiently
qualified/ suitable, the following information will be submitted to the Engineer for
Approval in the form of an MSB (Ref Quality System Procedure QSP-002
Document and Data Control Procedure).
6.2.3 Documents submitted for BOI approval shall consist of the following:
BOI Application letter
Commercial Invoice
Doc. No. QSP-009
Waterfront Integrated Resort
Rev. No C
Packing list
All above mentioned documents shall be maintained until Completion of Project.
6.3 Identification, Retrieval, Retention time and Disposition
6.3.1 Quality records shall be available at all time as a provision of proof of compliance in
full with all contract requirements.
6.3.2 The records listed in the appendix 1 shall be controlled and maintained until hand-
over to ENG/EMP is completed.
6.3.3 Quality records shall be maintained in such a way that they are readily retrievable.
6.4.1 Quality records shall be firmly filed in binders or placed in folders or envelopes for
storage in safe place or on shelves of each section or department as well as stored
in the Aconex document register.
6.4.2 Hard copies of records shall be labelled according to the HKN Company Document
filing classification system (which is revised regularly to meet current needs).
6.4.3 Soft copies of records are also securely stored on the HKN server for easy
reference.
6.4.4 Documents stored on Aconex shall be named and controlled in accordance with
QSP 002 Quality System Procedure for Document and Data control.
7.0 ATTACHMENT
7.1 Appendix 1 List of Quality Records
Doc. No. QSP-009
Waterfront Integrated Resort
Rev. No C
Management Responsibilities
Until COP
● Quality management review etc.
Resource Management
● Training Programme Until COP
● Training Attendance Roster
● Personnel Training Record
● etc.
Project Realization
● Document Master list (incl. Drawing) / Engineering Document Until COP
● Document Transmittal
● Site Query and Clarification Request
● Design Verification (Deviation, Concession) / Change Records
● Punch-lists
● Calibration & Verification Record for Measuring Devices
● Contract Review Checklist
● Contract Document (incl. Sub-contract)
● Tender Summary List
● Tender document (Award)
● Variation Order
● Approved Vendor / Sub-con. List
● Vendor / Sub-con. Survey Report
● Vendor / Subcontract Pre-qualification & Evaluation Record
● Material Requisition & Purchase Order
● Servicing Record etc.
Rev. No
QSP-()10
D
Wata rfron" Proj ect ·re amt - - - - - - - - - - - - - - - - - t - - - - + - - - -- - 1
eALMoN o1sr uo1o HvuNDAI-KEANGNAM-NAWALoKA Jv Sheet No. Sh. 1 of 26
Quality System Procedure for Field Inspection and Test
L~ /1/
D 09-Jun-2015 .
Incorporating · <"
Trevor Car~llgan
• ~·4ha 6.1. Kwon
Eng1neer's comments
Trevor
C 24-Apr-2015 Revise and Resubmit M.M.Im S.l. Kwon
Cardigan
TABLE of CONTENTS
1. PURPOSE
2. SCOPE
3. DEFINITIONS
4. REFERENCE
5. RESPONSIBILITY
6. PROCEDURE
8. ATTACHMENT
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
@ DRR-1251 on 13-May-2015
Shall provide a set of hard copies of only latest approved shop drawings along with the
checklist for Engineer review at the time of inspection.
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
1.0 PURPOSE
The purpose of the procedure is to describe the procedure for inspection and testing on
the Waterfront Integrated Resort project, which will meet the requirements of ISO
9001:2008, legal and regulatory requirements and other requirements which may be
relevant.
To ensure that work is carried out to the latest approved construction drawings,
Specifications, ITP‟s and other documents. In addition, mechanisms for rectification of
defective work are to be referenced to ensure that this work is approved and carried out
correctly.
To increase the awareness of all employees and subcontractors by communicating the
importance of effective inspection and testing and the responsibilities of all parties in
conducting these activities.
2.0 SCOPE
This procedure is applicable to field inspection performed by HKN JV (HYUNDAI-
KEANGNAM-NAWALOKA Joint Venture) at Waterfront Integrated Resort Project.
This procedure addresses all or part of the following clauses within the respective
management systems: ISO 9001:2008 Clauses 7; 8
3.0 DEFINITIONS
3.6 HKN JV
HYUNDAI-KEANGNAM-NAWALOKA Joint Venture
4.0 REFERENCES
4.1 HKN JV Project Quality Management Plan
4.2 Quality System Procedure QSP-004 : Procurement Control Procedure
4.3 Quality System Procedure QSP-006 : Non-conformance Product Control Procedure
4.4 Quality System Procedure QSP-007 : Corrective and Preventive Action Procedure
4.5 Quality System Procedure QSP-009 : Quality Record Control Procedure
4.6 Project Specification(Tender)
5.0 RESPONSIBILITY
5.1 Quality Manager is responsible for;
- Controlling the overall inspection activities including field inspection.
- Reviewing of ITP including designating of Witness / Hold points.
- Assigning the trained QC Engineers to QC inspection activities.
- Maintaining and up-dating the approved ITP and its master files
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
6.0 PROCEDURE
6.1 General
Prior to carrying out any inspection, an approved method statement (see Section 6.3
which describes the Coding process) which includes the ITP for the work being carried
out must be in place. The ITP must include the following information:
Approved Shop drawings relevant to the inspection, including layout plans and other
documents must be attached to each IR.
Also to be attached to the IR are the relevant checklists showing that inspections have
been performed and accepted by HKN
The person submitting the IR should ensure that the drawing provided is the latest
approved drawing on Aconex (see Section 3.3 – Coding). The only exception to this
process is where a Code „B‟ drawing has been resubmitted For Approval incorporating
the comments made on the Coded „B‟ submission into Aconex. Resubmission for Code
„A‟ FOR CONSTRUCTION allows the submission of the IR to take place; the resubmitted
drawing is to be attached to the IR.
A coding system has been developed which clearly identifies the status of drawings and
other documents:
Code A Approved
Code B Approved with Comments
Code C Revise and Resubmit
Code D Rejected
All documents used for construction purposes should be „Issued For Construction‟,
however, inspections may proceed if the following conditions are met:
The document/drawing has been coded „B‟ and the comments have been
incorporated and the drawing/document resubmitted into Aconex for approval
FOR CONSTRUCTION.
The inspection process is described below and a separate flowchart is available for
reference:
Inspection List will be submitted with all relevant attachments to enable the
Engineer to review prior to the submission of the IR.
Work is to be inspected by the Subcontractor and HKN (Construction and
QA/QC) before the submission of the IR to the Engineer (note that any minor
changes observed that differ from the „For Construction‟ drawing are to be
marked up on the drawing and submitted through Aconex at time of close-out).
The Engineer will attend Hold Point inspections and will attend Witness
inspections as necessary.
IR‟s are to be submitted 1 hour prior to inspection taking place
If, as a result of the inspection, work is defective and remedial work can be
completed within 1 hour then the Engineer will be advised and attend re-
inspection. If remedial work cannot be completed within 1 hour a resubmission
of the IR is required giving 1 hour notice and if work cannot be completed within
the 1 hour, the inspection is to be included on the next day‟s IR and
resubmitted.
There will be no cut-off time if the area to be inspected is not ready at the
requested time in the submitted IR (considering Section 3.3)
NCR‟s are raised for work that is defective (see Section 3.5.6 for more
information).
An inspection may only proceed at HKN risk without the necessary documents in
place providing that:
The work will not be covered up prior to the Engineer being afforded the
opportunity to inspect using drawings and documents that have been approved
subsequent to the work being done.
The Engineer has no objection providing that any abortive work will not be
detrimental to the Permanent Works and an NCR is raised to ensure that
rectification proposals are acceptable to the Engineer and in addition, the
following documents are in place:
All drawings must be „For Construction‟ or Code „B‟ submitted For Construction
on Aconex.
Method Statement must be at least Code „B‟
Material Submittals are to be Code „A‟
Approved Lifting Plans are in place
Calibration Certificates (if relevant) must be in date
6.5 Aconex
6.5.1 General
Aconex is an online project management software tool and has four main functions:
To control workflows to ensure tasks are completed and recorded (in most
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
cases, this may also assign a code to the document showing its
acceptability).
To assign a revision status against documents and drawings so that only
the latest revisions are displayed and used.
To allow audits of tasks, processes and completion of activities.
To be a document repository function with search facilities to enable
location of documentation.
In order that the inspection process can be tracked via Aconex, each inspection
request submission should result in the uploading of the completed checklist so that
a record exists of acceptance of the Works. This can be used as part of the
handover process to confirm that all inspections are complete and acceptable. This
will become more important once the snagging and testing and commissioning
phase begins and will enable full closure of all quality activities and evidence of
completion.
The Construction Department is responsible for compiling the list of inspections for
the following day. This list is forwarded to QA/QC who carry out a check to confirm
that it is likely that the Engineer‟s inspection will take place at the proposed time.
Factors that QA/QC should take account of before confirmation are:
The progress of the work and probability for completion before the
inspection is due
Access for the inspection
Availability of resources
Availability of materials e.g. concrete
Availability of plant and equipment
Conflict with other inspections (these should be rescheduled where possible
and discussed with construction to ensure priorities are met).
QA/QC will amend the list and submit to the Engineer with all attachments
necessary for the inspection (excluding checklists which will be attached to the IR,
but including the required supporting documents) before 10.00am of the previous
day.
The Engineer will review the list and decide internally which witness points they
wish to attend. Confirmation will be via the submitted IR (1 hour in advance of the
inspection taking place).
The following day, the inspection list is amended with any changes after a physical
check to confirm status. The updated inspection list is sent to the Engineer via
Aconex by 10.00am
6.5.3 Inspection
The Contractor is responsible for ensuring that the work complies with
requirements; to meet the proposed time for the Engineer‟s inspection, this should
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
be timed to allow sufficient time for all relevant checks to be completed. Checklists
for each activity are designed so that the result of the Contractor inspection is
recorded and the same checklist used for subsequent inspection by all other parties
involved in the inspection process.
HKN Construction Department are to ensure that the works are acceptable and the
result of this inspection is to be recorded on the relevant checklist for the activity
being performed.
HKN QA/QC Department will also utilise the same checklist and record their
observations on the form. At any point in this sequential process, the work can be
rejected if not compliant. An NCR may be raised if the remedial work is complex.
The Engineer should be informed of the outcome and rescheduled if rejected, once
remedial works are likely to be complete.
Inspection by the Engineer will only take place once HKN are satisfied that the work
is acceptable.
6.5.4 Submission of IR
Once the inspections by HKN are complete and acceptable, the IR Form QSP-010-
01 – a standard format within Aconex, can be submitted to the Engineer. The IR is
numbered in accordance with Attachment 8.1. The following information should be
attached to the IR:
The Engineer
Other relevant Balmond Studio personnel
CSEC
Green Tech
Mechanical Consultant (Kapila)
HKN Construction
HKN QA/QC
The attributes that are to be set within Aconex are dependent on the item for
inspection but will always include the location (either Project Wide or a specific
building) and the category i.e. ST- Structural (note multiple attributes can be
added).
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
The Engineer will respond to the IR indicating whether or not they will attend.
The Engineer will attend the inspection at the designated time. If the Engineer does
not attend witness points then the inspection can be deemed to be accepted. For
Hold Points, the Engineer will attend the inspection within a reasonable time in
accordance with the Contract. There will be no cut-off time if the inspection cannot
be carried out at the designated time due to incomplete works and the Engineer will
be entitled to reject it as incomplete for inspection. Acceptance (or rejection) will be
indicated on the checklist. In the case of failed inspections that can be rectified
within 1 hour, there is no need to resubmit the IR – the Engineer is informed of the
new inspection time (if the proposed new inspection time is in conflict with another
inspection then it will be rescheduled where possible). A second rejection will result
in the addition to the next inspection list (providing remedial work can be completed)
and a resubmission of the IR. The IR will automatically be closed out if HKN does
not contact the Engineer for re-inspection within the stipulated 1 hour from the
original inspection time.
Rejections where the remedial work will take longer than one hour, may result in the
issue of an NCR – this process is explained in Section 6.5.6. All rejections that will
take longer than one hour will result in a resubmission of the IR (giving 1 hour
notice).
The checklist confirming that the work has been accepted will be loaded on to
Aconex as IR correspondence linked to the original IR so that a full history of
information is available. A rejected checklist will be marked up with a note of the
new IR number before submitting into Aconex as evidence of rejection.
6.5.7 Close-out of IR
7.0 DOCUMENTATION
7.1 The inspection results shall be documented on the related reports / checklists.
7.2 The inspection records shall be retained in QA/QC Department.
8.0 ATTACHMENT
8.1 Inspection Report Numbering System
8.2 Form QSP-010-01 Inspection Request Form (IRF)_ACONEX Embedded format
8.3 Form QSP-010-02 Field Inspection and Test Plan
8.4 Form QSP-010-03 Check List for Construction Package/General
8.5 Form QSP-010-04 Weekly Inspection Schedule sheet
8.6 Inspection Flowchart
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
• All Inspection report except for vendor report shall include HKN JV(HYUNDAI-KEANGNAM-
NAWALOKA Joint Venture) document numbering in the following format:
HKN :
HKN JV
IRF :
Inspection Request Form
Discipline :
ST – Structural
AR – Architectural
EL – Electrical
ME – Mechanical
Serial Number :
5(five) digit numbering
00001, 00002, 00003, ……
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
To : Balmond Studio
To Engineer,
We hereby request for inspection as below;
• Discpline : STRUCTURAL
• Note :
• Comment :
Confirmed by : / Date :
Form QSP-010-01
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
0 10th May 2014 All Pages Initial Release (Issued for Approval)
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
CONTENTS
B. INSPECTION LEVEL
1. Submittals.
2. Preparatory Works.
3. Installation / Inspection.
- Hold Point (H) : A designated point during or following a specific activity. Work may
not proceed beyond this point until the inspection has taken place and been
witnessed by the required parties.
- Witness Point (W) : A designated point during of following an important activity at
which inspection or examination is required in accordance with the relative
procedure. Work may proceed through the designated witness point if the inspector
is not present for the previously established activity.
- Spot Witness Point (SW) : A designated point during or following an activity at
which spot inspection or spot examination is required in accordance with the relative
procedure. Work may proceed through the designated witness point if the inspector
is not present for the previously established activity.
- Review Point (R) : It is processed through reviewing any results of inspection or test
as a method of ensuring that the inspection or test is performed in accordance with
any approved drawing, procedure, specifications or acceptance criteria.
- Surveillance (S) : It is processed through the routine act of monitoring or observing
to verify an item or activity conforms to specified requirements.
- N/A : Not applicable.
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
B. INSPECTION LEVEL
Generally, Inspection Checklist will be signed by the inspector who is involved the
inspection activity only. (In case Category A, B and C items signature column for
Company shall be made “N/A”.
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
Type Symbol
Contractor‟s Surveillance CS
Contractor‟s Review CR
Contractor‟s Witness CW
Contractor‟s Hold Point CH
Engineer‟s Witness EW
Engineer‟s Hold Point EH
Sheet No.
Sh. 22 of 26
Form QSP-010-02
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
■ DISCIPLINE : ■ SUBCON :
■ LOCATION :
■ MANUFACTURER :
Date :
Name :
Signature :
Form QSP-010-03
Doc. No. QSP-010
Waterfront Integrated Resort
Rev. No D
HYUNDAI-KEANGNAM-NAWALOKA JV
Check List for OOO OOOOOOO OOOOOOOOOO
REPORT NO.: DATE:
DISCIPLINE: SUBCON:
LOCATION DESCRIPTION:
REF.DOC.NO.:
ACCEPTED BY
NO. DESCRIPTION OF INSPECTION / TEST REMARKS
SUB HKN ENG
PREPARATION
1.
EXECUTION
2.
3.
4.
5.
6.
7.
8.
9.
NOTE:
Date :
Name :
Signature :
Form No. QSP-010-03
■ Weekly Inspection Schedule Sheet
Inspection Inspection Attendance
No. Description of Inspection Sub-Cons Remarks
Date Time SUB HKN JV ENG
Inspection for Pile Setting-out Nawaloka
1 30-Jun-14 10:00 √ √ √
@ Building No. 5 (Pile No. 5-100, 5-109, 5-79, 5-13) Piling
Inspection for Setting-out of Sewer Pump
2 30-Jun-14 13:00 √ √ √ Samku
@ Building 3
Inspection for Waterstop Application
3 30-Jun-14 15:00 √ √ √ Samku
@ Building 3
Inspection for Pile Setting-out Nawaloka
4 01-Jul-14 10:00 √ √ √
@ Building No. 5 (Pile No. 5-57, 5-35, 5-16, 5-25) Piling
Inspection for Pile Setting-out Nawaloka
5 01-Jul-14 11:00 √ √ √
@ Building No. 2 (Pile No. 2-312, 2-507, 2-506) Piling
Inspection for Pile Setting-out Nawaloka
6 02-Jul-14 10:00 √ √ √
@ Building No. 5 (Pile No. 5-94, 5-97, 5-54, 5-70) Piling
Inspection for Pile Setting-out Nawaloka
7 02-Jul-14 11:00 √ √ √
@ Building No. 2 (Pile No. 2-148, 2-147, 2-57, 2-55) Piling
Inspection for Rebar Checking & Concreting Nawaloka
8 03-Jul-14 14:00 √ √ √
@ Building No. 5 (Pile No. 5-39, 5-87, 5-47) Piling
Inspection for Rebar Checking & Concreting Nawaloka
9 04-Jul-14 15:00 √ √ √
@ Building No. 5 (Pile No. 5-79, 5-16, 5-35) Piling
Inspection for Rebar Checking & Concreting Nawaloka
10 05-Jul-14 15:00 √ √ √
@ Building No. 2 (Pile No. 2-151, 2-154) Piling
Waterfront Integrated Resort
Sheet No.
Sh. 25 of 26
Inspection Request Process
1 day before raising IR Within same day of raising IR < 1 hour after carrying out inspection
Subcontractor
Inspection List for next Inspection List HKN Construction
day raised by updated by carries out Inspection For resubmissions,
Construction Construction and completes
HKN
note the previous IR
Manager/ Engineer Manager/Engineer checklist
No. on new IR
Construction
Attachment 8.6. Inspection Flowchart
HKN QA/QC
not ok
Aconex
Aconex by 10.00 10.00 inspection
If rejected by HKN,
Attend inspection at Accept or reject
Waterfront Integrated Resort
Engineer
attendance
HYUNDAI-KEANGNAM-NAWALOKA JV
NOTES
Documents necessary for the inspection to take place are to be attached to the Notification list and IR and must either be Code 'A' or Code 'B' (resubmitted for Code 'A' through
#
Rev. No
Doc. No.
Sh. 26 of 26
~
Doc. No. QSP-01 1
Waterfront Integrated Resort
Rev. No B
Wate rfr on t Project Team
Sh . 1 of 6
DA LM0N0/STU 0I 0 HYUNDAI-KEAN GNAM-NAWALOKA JV Sheet No.
,,
\~ ~~
--r
..T. Car ... .(\~ <:.JIIj
B 29-Jul-20 15 Changes to QSP-011-01
~~ ;
gan J . ~' Lee Nam Won Kang
~
Initial Release
A 25-Jul. -2015 T. Cardigan J.M. Lee Nam Won Kang
( Issued for Approval )
Sh. 2 of 6
HYUNDAI-KEANGNAM-NAWALOKA JV Sheet No.
Sh. 3 of 6
HYUNDAI-KEANGNAM-NAWALOKA JV Sheet No.
TABLE of CONTENTS
1. PURPOSE
2. SCOPE
3. DEFINITIONS
4. REFERENCE
5. RESPONSIBILITY
6. PROCEDURE
7. ATTACHMENT
Doc. No. QSP-011
Waterfront Integrated Resort
Rev. No B
Sh. 4 of 6
HYUNDAI-KEANGNAM-NAWALOKA JV Sheet No.
1.0 PURPOSE
This procedure establishes the format and numbering protocol for drawings issued by
HKN related to Waterfront Integrated Resort Project.
2.0 SCOPE
This procedure is applicable to shop drawings, field inspection performed by HKN JV
(HYUNDAI-KEANGNAM-NAWALOKA Joint Venture) at Waterfront Integrated Resort
Project.
3.0 DEFINITIONS
4.0 REFERENCE
4.1 HKN JV Project Quality Management Plan
4.2 Aconex Project Configuration HDEC-PRC-PM-0001
4.3 Aconex Information Management Policy HDEC-PRC-PM-0002
5.0 RESPONSIBILITY
5.1 The Site Coordinator is responsible for:
● Maintenance and update of the HKN Drawing Numbering System.
Sh. 5 of 6
HYUNDAI-KEANGNAM-NAWALOKA JV Sheet No.
6.0 PROCEDURE
6.1 General:
6.1.1 All drawings shall be prepared using the format shown in QSP-011-01 (attached as
Appendix A).
6.1.2 When uploading drawings to Aconex, it may be necessary to input additional data
relevant to the drawing into Aconex (for example level or multiple levels) – this must be
done carefully so that the search process is not compromised.
6.1.3 Examples are available in QSP-011-01 to show the correct formatting – no deviation from
this format is allowed without informing the Design Manager.
7.0 ATTACHMENT
7.1 Appendix A - Form QSP-011-01 HKN Shop Drawing Numbering System
Doc. No. QSP-011
Waterfront Integrated Resort
Rev. No B
Sh. 6 of 6
HYUNDAI-KEANGNAM-NAWALOKA JV Sheet No.
Form QSP-011-01