Schedule

Num Of Total Qty 26-May 27-May 28-May 29-May 30-May 31-May 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul
Description of work Start Date End Date Labour Requirement
Days Unit
Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty

Tower-02 Pour-01
26-May-22 30-May-22 5 Dressing Sqm -
Floor PCC
31-May-22 31-May-22 1 Concrete Cum 190.00 190

4-Jun 15-Jun 12 Concrete Nos 154.00 12 13 13 13 13 13 13 13 13 13 13 12

Basement Column 1st lift 3-Jun 14-Jun 12 21 Shuttering Nos 154.00 10 15 13 13 13 13 13 13 13 13 13 12

2-Jun 13-Jun 12 13 Steel Nos 154.00 12 13 13 13 13 13 13 13 13 13 13 12

12-Jun 23-Jun 12 Concrete Nos 154.00 12 13 13 13 13 13 13 13 13 13 13 12


Basement Column 2nd
11-Jun 22-Jun 12 20 Shuttering Nos 154.00 10 15 13 13 13 13 13 13 13 13 13 12
lift
#DIV/0! Steel Nos -

6-Jun 9-Jun 4 Concrete RMT 60.00 30 30


R/W 1st Lift 4-Jun 8-Jun 5 19 Shuttering RMT 60.00 15 15 15 15

2-Jun 6-Jun 5 6 Steel RMT 60.00 15 15 15 15

14-Jun 17-Jun 4 Concrete RMT 60.00 30 30


R/W 2nd Lift 12-Jun 16-Jun 5 19 Shuttering RMT 60.00 15 15 15 15

10-Jun 14-Jun 5 6 Steel RMT 60.00 15 15 15 15

. Concrete Cum -
Stilt F Slab 23-Jun 12-Jul 20 0 Shuttering Sqm -

28-Jun 12-Jul 15 0 Steel MT -

Tower-02 Pour-02
26-May 6-Jun 12 Dressing Sqm -
Floor PCC
7-Jun 8-Jun 2 Concrete Cum 268.00 168 100

13-Jun 24-Jun 12 Concrete Nos 148.00 12 12 12 12 12 12 12 12 12 12 14 14

Basement Column 1st lift 12-Jun 23-Jun 12 20 Shuttering Nos 148.00 8 14 14 12 12 12 12 12 12 12 14 14

11-Jun 22-Jun 12 12 Steel Nos 148.00 12 12 12 12 12 12 12 12 12 12 14 14

18-Jun 29-Jun 12 Concrete Nos 96.00 12 12 12 12 12 12 12 12 12 12 14 14


Basement Column 2nd
17-Jun 28-Jun 12 6 Shuttering Nos 108.00 8 14 14 12 12 12 12 12 12 12 14 14
lift
1 36 Steel Nos -

0-Jan 0-Jan 1 Concrete Cum -


Stilt F Slab 23-Jun 12-Jul 20 0 Shuttering Sqm -

28-Jun 12-Jul 15 40 Steel MT -

Tower-02 Pour-03
3-Jun 16-Jun 14 Concrete Nos 84.00 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Footings 2-Jun 15-Jun 14 7 Shuttering Nos 84.00 6 6 6 6 6 6 6 6 6 6 6 6 6 6

1-Jun 14-Jun 14 5 Steel Nos 84.00 6 6 6 6 6 6 6 6 6 6 6 6 6 6

8-Jun 16-Jun 9 Concrete Nos 90.00 10 10 10 10 10 10 10 10 10


Pedastal 7-Jun 15-Jun 9 8 Shuttering Nos 90.00 10 10 10 10 10 10 10 10 10

6-Jun 14-Jun 9 4 Steel Nos 90.00 10 10 10 10 10 10 10 10 10

7-Jun 11-Jun 5 Concrete Nos 120.00 40 40 40


R/W Footing 5-Jun 10-Jun 6 4 Shuttering Nos 120.00 20 20 20 20 20 20

4-Jun 9-Jun 6 4 Steel Nos 120.00 20 20 20 20 20 20

15-Jun 24-Jun 10 Concrete Nos 120.00 30 30 30 30


R/W 13-Jun 23-Jun 11 9 Shuttering Nos 120.00 15 15 15 15 15 15 15 15

11-Jun 21-Jun 11 2.727272727 Steel Nos 120.00 15 15 15 15 15 15 15 15

14-Jun 29-Jun 16 Backfilling & Dressing Sqm -


Floor PCC
30-Jun 30-Jun 1 Concrete Cum - 168
Num Of Total Qty 26-May 27-May 28-May 29-May 30-May 31-May 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun 27-Jun 28-Jun 29-Jun 30-Jun 1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul
Description of work Start Date End Date
Days Unit
Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty Qty

Tower-01 Pour-03
26-May-22 1-Jun-22 7 Dressing Sqm -
Footing PCC
26-May-22 2-Jun-22 8 Concrete Cum 120.00 15 15 15 15 15 15 15 15

29-May 9-Jun 12 Concrete Nos 175.00 15 15 15 15 15 15 15 15 15 15 15 10


Footings 28-May 8-Jun 12 13 Shuttering Nos 175.00 15 15 15 15 15 15 15 15 15 15 15 10

27-May 7-Jun 12 11 Steel Nos 175.00 15 15 15 15 15 15 15 15 15 15 15 10

30-May 13-Jun 15 Concrete Nos 220.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10

Col upto Grade slab 29-May 12-Jun 15 4 Shuttering Nos 220.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10

28-May 11-Jun 15 6 Steel Nos 220.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10

1-Jun 10-Jun 10 Concrete Nos 110.00 30 30 30 20


R/W 1st lift 30-May 9-Jun 11 8 Shuttering Nos 110.00 15 15 15 15 15 15 10 10

28-May 7-Jun 11 3 Steel Nos 110.00 15 15 15 15 15 15 10 10

28-May 14-Jun 18 Dressing Sqm -


Floor PCC
7-Jun 15-Jun 9 Concrete Cum 320.00 40 40 40 40 40 40 40 20 20

16-Jun 25-Jun 10 Concrete Nos 110.00 30 30 30 20


R/W 2nd lift 14-Jun 24-Jun 11 8 Shuttering Nos 110.00 15 15 15 15 15 15 10 10

12-Jun 22-Jun 11 3 Steel Nos 110.00 15 15 15 15 15 15 10 10

10-Jun 24-Jun 15 Concrete Nos 220.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10

Basement Column 1st lift 9-Jun 23-Jun 15 0 Shuttering Nos 220.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10

8-Jun 22-Jun 15 0 Steel Nos 220.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10

13-Jun 27-Jun 15 Concrete Nos 195.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10


Basement Column 2nd
12-Jun 26-Jun 15 0 Shuttering Nos 210.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 10
lift
1 0 Steel Nos -

16-Jun 8-Jul 23 Concrete Cum 620.00 200 200 220


Stilt F Slab 20-Jun 8-Jul 19 0 Shuttering Sqm 4,700.00 100 150 150 200 200 200 200 200 200 250 250 300 300 300 300 250 250 200 200 200 100 100 100

10-Jul 12-Jul 3 0 Steel MT 101.00 3 4 4 4 6 6 6 8 8 8 8 8 8 5 4 4 3 2 2

Tower-01 Pour-01 & 2


26-May-22 4-Jul-22 40 Dressing Sqm -
Footing PCC
3-Jun-22 5-Jul-22 33 Concrete Cum 495.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15

10-Jun 10-Jul 31 Concrete Nos 465.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15


Footings 9-Jun 9-Jul 31 0 Shuttering Nos 465.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15

8-Jun 8-Jul 31 0 Steel Nos 465.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15

13-Jun 10-Jul 28 Concrete Nos 420.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15

Col upto Grade slab 12-Jun 9-Jul 28 0 Shuttering Nos 420.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15

11-Jun 8-Jul 28 0 Steel Nos 420.00 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15