Professional Documents
Culture Documents
2010 - 3Q10 ITM Analyst Presentation
2010 - 3Q10 ITM Analyst Presentation
Analyst Briefing
11 November 2010
DISCLAIMER
The views expressed here contain information derived from publicly available sources that have not been
independently verified. No representation or warranty is made as to the accuracy, completeness or reliability of the
information. Any forward looking information in this presentation has been prepared on the basis of a number of
assumptions which may prove to be incorrect. This presentation should not be relied upon as a recommendation or
forecast by PT. Indo Tambangraya Megah Tbk. Nothing in this release should be construed as either an offer to buy or
sell or a solicitation of an offer to buy or sell shares in any jurisdiction
Agenda
1. Introduction
2. Operational review
3. Commercial review
4. Financial review
1
Introduction
Highlights of 3Q10 & 9M10 – the figures
• Indominco East Block: • Completed construction of 2x7 • Achieve world class standards of
production will be ramped MW captive coal power plant management best practice:
up to 12mt by 2015 • ISO 9001:2000
• Reduced costs through logistics
• Kitadin Tandung Mayang: expansion and economies of • ISO 14001:2004
will resume its own mine scale • OHSAS 18001:1999
production by 2H 2011 • TPM 3 Excellence
• Chip seal hauling road at
• Bharinto operation will Trubaindo mine • National Environment Certificate
(PROPERNAS)
commence in 1H 2011
• Washing plant construction at • Environmental Management
• BoCT ship loading Trubaindo and further at East Award in Sep 2010 from Ministry
expansion to 18.5Mtpa Block of Energy and Mineral Resources
completed
• In-pit crusher study for East • Platinum Award in Oct 2010 for
• Pro-actively looking for Block community development program
potential coal assets
from the Coordinating Ministry of
acquisition
Social Welfare
• Gold Award in Oct 2010 from
International Innovation ICQCC
Agenda
2
Operational Review
ITM operations in 2010
ITM OPERATIONS & PROJECTS z Total coal output:
East ¾ 9M10 : 16.2Mt (72% achievement)
Kalimantan
¾ FY10 : 22.5Mt target
INDOMINCO Bontang Coal
14.7 Mt Terminal z Indominco - 9M10 output: 10.7Mt
- FY10 target: 14.7Mt
Bunyut Port - E.Block: production proportion will
Captive coal-
fired power
increase starting 2010 onwards
TRUBAINDO - W.Block UG: Project is terminated due to
5.5 Mt high cost to support geological condition
Samarinda
KITADIN
1.4 Mt z Trubaindo - 9M10 output: 4.1Mt
Central BHARINTO Balikpapan
Kalimantan - FY10 target: 5.5Mt
- Production was reduced due to severe
weather conditions during 2Q/3Q 2010
Palangkaraya
South z Bharinto - First production output by 1H 2011
Kalimantan
z Embalut - 9M10 output: 0.9Mt
Banjarmasin - FY10 target: 1.4Mt
JORONG - Utilize existing reserve
0.9 Mt
z Td. Mayang - Works as mining contractor at IMM area
Operation
Jorong Port
- Production from own mine will commence by
Project 2H 2011
Post
z 3Q10 production lower than expected due to bad weather
Santan River Port stock
yard Panamax z Additional mining equipment will be supplied from mining
95,000DWT contractor to produce additional coal in East Block
Inland
conveyor 4km z Power plant already in operation, supplying power to Bontang
port and East Block and currently under development to
supply power to West Block
z Bontang port already running at upgraded loading capacity of
20.5mtpa by shiploader and FTS
0 2 4 6 8 10 km z West Block UG: Decision to terminate the project due to high
cost to support geological condition
Trubaindo and Bharinto
0 2 4 6 8 10 km
Jorong
Haul road
2010e 0.4 0..0 0.1 0.4 0.9 Mt
1Q 2Q 3Q 4Q
20km
MAJOR QUARTERLY UPDATES
3Q10 production lower than planned due to starting of
production in mid August
Jorong
Overall production target will be lower than original
plan due to operation stoppage and severe weather
Operations Coal conditions
terminal
Barge Port
Pacific Ocean
Hauling
Stockpile
Bontang Power Plant focus: profile
Profile
Total capacity : 2 x 7 MW
20-30% diesel
Port Substation
• Lower operating costs and increase reliability 10 kV Line
of fuel supply ~ 1 km
1
• Opportunities to promote local employment 2
6.5 MW port and port
70 kV Line ~23 km
• Second 7 MW will be used for West Block stockyard substation
extension
• Surplus for future electrification projects or Port Stockyard Substation
third party sales East Block Substation
1.0 MW approximate load
Extension plan:
2x7 MW Bontang
power plant
• Extension of the 20 kV Line ~4 km
Commercial Review
Long term coal market quality trends
RUSSIA
CHINA
Minor recovery due
weakened Ruble but rising Faster import pace reverses
ATLANTIC domestic demand and rail until 4Q. Imports much higher
Bottoming out? Slow limits than 2009. Exports drop EAST ASIA
recovery encouraging Japan minor recovery, but
steel mills strong so far;
Korea &Taiwan strong
USA recovery
Thermal supply
remains very low, some
LCV to Korea REST OF ASIA
Continued growth
COLOMBIA
Diverts coal to Asia, +/- 10mt
already sold but heavy rains INDONESIA
depress output. Signs of More rain through 4Q
growing regional demand depresses output
Coal
Coal sales
sales contract
contract and
and pricing
pricing status
status Comment
ASP up 5% in 2009
TARGET SALES 2010: Approx. 23 Mt
Coalsales
Coal salesby
bygeographic
geographicdestination
destination (ITM and Thai)
Coal sales 9M10 CHINA 2010 HONG KONG 2010 S.KOREA 2010 JAPAN 2010
3.6Mt
4.2Mt
(Total 16.4Mt) 2.6Mt
1.3 Mt
1.0Mt 2.3Mt
4.0Mt 3.5Mt
1.7Mt 0.0Mt
1.2Mt
2008 2009 9M10
0.6Mt
ITALY 2010
2.2Mt
1.4Mt
0.8Mt
1.0Mt THAILAND 2010 INDONESIA 2010 PHILIPPINES 2010
2.8Mt
2008 2009 9M10
Financial Review
ITM sales revenue
3Q09
3Q09 4Q09
4Q09 1Q10
1Q10 2Q10
2Q10 3Q10
3Q10
Kitadin
Jorong
Trubaindo
3Q09
3Q09 4Q09
4Q09 1Q10
1Q10 2Q10
2Q10 3Q10
3Q10
Indominco
Average gross margin
Units: USD millions
414 Total
397 Revenue
370 GPM* (%)
355
326
275
114 137
36% 102
35%
43%
28% 27%
32% 51
49
32% 31% 31 31
41% 1
28% 0
19% 27% 23% 27% 54%
-59%
3Q09 2Q10 3Q10 3Q09 2Q10 3Q10 3Q09 2Q10 3Q10 3Q09 2Q10 3Q10 3Q09 2Q10 3Q10
Lowersales
Lower salesvolume
volumeby
by Higher
Higher
4% 4% demurrage
demurrage
MINE BY MINE
87.7
78.9
70.8
30. 31.2
25.5
3 13.2 12.0 11.7
4.2
(9.8) (4.0)
3Q09 2Q10 3Q10 3Q09 2Q10 3Q10 3Q09 2Q10 3Q10 3Q09 2Q10 3Q10
Indominco Trubaindo Kitadin Jorong
Net income
Units: USD million CONSOLIDATED
UG exploration
cost
MINE BY MINE
61.5
52.2
28.9
20. 17.0 20.9
2
7.6
6.8
4.2 4.5
(8.1) (7.1)
3Q09 2Q10 3Q10 3Q09 2Q10 3Q10 3Q09 2Q10 3Q10 3Q09 2Q10 3Q10
Indominco Trubaindo Kitadin Jorong
Balance sheet
CASH POSITION
429
(Units: USD million)
355
Net gearing (%)
258
222 Net D/E (times)
54 1.11
2.4
Indominco East Block Realized up to Sep 2010
7.5
2010 major Capex plan
4.6
Bontang Power Plant
5.3
6.0
Trubaindo Infrastructure
20.4
3.4
Td.Mayang Equipment
10.5
Note: The capital expenditure figures shown above do not include estimates for maintenance or sustaining capital expenditure
Questions & Answers
Agenda
Appendices
Income Statement
Unit: US$ thousand 3Q10 2Q10 3Q09 QoQ% YoY%