Professional Documents
Culture Documents
Method Statement Street Lighting Installation
Method Statement Street Lighting Installation
METHOD STATEMENT
INSTALLATION OF STREET LIGHTING WORK
REVISION SUMMARY
Rev. No. Revision Details Rev. Date
Table of Contents
1.0 SCOPE OF WORK..............................................................................................................................3
1.1 GENERAL DESCRIPTION................................................................................................................3
1.2 MATERIALS...................................................................................................................................3
1.3 PLANT AND EQUIPMENT..............................................................................................................3
1.4 MANPOWER.................................................................................................................................4
1.5 CONSTRUCTION PROCEDURES.....................................................................................................4
2.0 SAFETY AND HEALTH.......................................................................................................................9
2.1 JOB SAFETY & HEALTH ANALYSIS..................................................................................................9
2.2 INFORMATION TO PERSONNEL....................................................................................................9
2.3 EMERGENCY ARRANGEMENTS...................................................................................................10
2.4 Permit Requirements................................................................................................................10
3.0 ENVIRONMENTAL ISSUES..............................................................................................................10
3.1 ENVIRONMENTAL ASPECTS, IMPACTS & CONTROL MEASURES.................................................10
4.0 QUALITY ASSURANCE & QUALITY CONTROL................................................................................12
4.1 CONTRACTUAL REQUIREMENTS.................................................................................................12
4.2 INSPECTION & TESTING..............................................................................................................12
4.3 FOLLOW UP & EVALUATION.......................................................................................................12
1.2 MATERIALS
No Description Purpose
Plate/Roller Compactor /
8 Compaction during backfilling
Monkey Jack
Insulation, Continuity and For various cable testing; continuity test &
11
Resistance Meter insulation resistance test.
1.4 MANPOWER
1.5.1.3 The condition, external protection, depth, size and type of all existing utilities on all
existing roads and any other locations where the existing utility/services cross the proposed railway
line or runs parallel to it and falls within the construction zone or as directed by the Supervising
Consultant (SC) shall be located and marked out by the Contractor.
1.5.1.5 The contractor will to the best of his ability not to cause disruption on the operation of
existing services and utilities. Contractor shall not disconnect any of the services and utilities without
written approval from TNB or other owners.
1.5.2.1 The traffic management plan (if required) will be submitted for approval prior to the
implementation of any work. The equipment need during traffic management plan may include NJB
barricades, flaggers and temporary signage’s depending on the area to be piloted.
1.5.2.2 Temporary road closure or diversion will be carried out as per approved TMP.
1.5.2.3 Temporary traffic signage will be placed at proposed location as indicated in the TMP
drawing. Flaggers are essential in controlling traffic when there is detour/alternate lane is
implemented. Additional requirement of flagger's arrangement may be necessary for utility work
other than traffic control to suit site condition.
1.5.2.4 Any type of road closures for piloting works should only be carried out upon issuance of
Traffic Announcement to the media/person in charge.
1.5.3.1 To confirm on the project schedules and provide utility contractor and utility owner
schedule date.
1.5.3.2 Give the utility contractor notice to proceed (NTP) once the site is clear and allowed the
contractor to carry out the work.
1.5.3.3 Each of utility contractors to give the work program in conjunction with the plan and
estimate. This shall be made a part of the overall project detail work program.
1.5.3.4 Piloting work at the area where intended utilities relocation will be carried out will be by
the same piloting method as describe in this work method statement.
a. The condition, alignment, external protection, depth, size and type of all existing
electrical line and cables services shall be confirmed onsite in the presence of
respective authority representative unless otherwise agreed.
b. The proposed alignment or new cable routes shall be pegged out as indicated in the
approved construction drawings.
c. Trial pits or pilot holes shall be made to ensure no existing services at the proposed
new alignment.
d. Trenching for underground utility services shall commence only after mapping is done
and the site pegs have been inspected.
e. The Contractor shall set out sight rails at every 10 meters interval and at all change of
grade and alignment of utility service and maintain the pegs until works are completed.
h. The Works will only be commenced after the MSA, MST and shop drawings are
approved.
Relocating of cables shall be carried out in accordance with approved shop drawings. No
ducting works for overhead cabling works except for riser at pole.
h. Bolt on a set of nuts onto the foundation bolts. Place pole's bottom pole flange-
base over the foundation bolts and sit the pole flange the foundation bolt nuts.
Screw on the locking nuts on to the foundation bolts at the top of the flange base.
Check and adjust the verticality of the pole with liquid level gauge before the nut
in place.
j. Check the underground loop in and out cable’s insulation with and earth
insulation test before terminating the cables into the light fitting ballast box
termination block.
k. Carry out the adjustment to the aiming of the light fitting according to approved
calculations and drawing and lock fitting into placed by tightening all the
adjustment bolt/screw.
I. Cut-out box will be installed inside the lamp pole.
m. Terminate the internal cable ends into the cut-out box.
Testing of cable shall be carried out before and after cables being terminated. The
purpose for testing is to make sure cable is in good condition and high insulated during
operation. The testing equipment will have a valid calibration certificate and this
The containment of drilling fluid slurry and other materials and consumables used on the work site
and for the equipment are properly controlled and monitored. Drill sites are left in a clean and original
state after completion of the drilling work. All the dumped and unused material to be cleaned and
tidied.
2.1.1 The Job Safety Analysis shall be prepared and discussed in Committee Meeting. No
work may commence until the Job Safety Analysis approved by Committee.
2.1.2 The toolbox meeting shall be conducted to site personnel involved in the activity prior
start of work. No work may commence until all the specified control measures are in place and
toolbox meeting has been conducted.
2.1.3 If any cable is found, excavation should be carried out alongside the cable position with
the present of competent personnel. If a TNB cable is struck, the driver should stay in Backhoe's
seat. If it is necessary to leave the seat, the driver should jump clear and not climb down, to avoid
possibility of being electrocuted. No one shall go down into the trench or touch the Backhoe or the
cable until TNB or relevant authority/services owner has the site is safe for the work to be continued.
2.2.1 All site personnel must be brief of the work scope and make known of all potential hazard
present at site prior of start work at site. Only the managers, engineers, supervisors and workers
who have are qualify allowed to be at site.
2.2.2 All workers and site personnel employed in the project site must have valid CIDB Green
Card.
2.2.3 All new workers and staff to attend the Safety Induction before commencing works at site
and attendances shall be recorded in an induction record.
2.2.4 All site personnel are required to attend pre-task talk and toolbox meeting. All site personnel
shall wear approved Personnel Protective Equipment (PPE) as per site requirement:
2.3.1 Flow chart for the potential emergency such as fire explosion, evacuation, structure
collapse, major injury or fatality from accidents, major chemical spillage, road Accident / vehicle
breakdown, flooding and heavy machinery breakdown, protest/riot, food poisoning and unstable
person has been specified in Emergency Response Plan.
2.3.3 The organization chart, list of emergency contact person and relevant authorities with
their contact numbers shall be posted on the Notice Board. These lists can be obtained from the
Emergency Response Plan.
2.3.4 In the event of emergency, the assigned emergency coordinator is responsible for co-
coordinating the response strategy and take immediate actions to reduce or eliminate the threats
of the emergency.
3.1.1 The Environmental Aspects & Impact Register will be identified and listed
following project/site/area specific.
3.2.1 The control for erosion and sedimentation shall be complied with the Project ESCP and
DEIA Approval Condition.
3.2.2 Site clearing works shall be limited to construction areas only. Earth stockpile areas shall
be located away from the surface runoff and protective with sheeting.
3.2.3 Temporary erosion protection for exposed slopes under construction shall be provided
until such time when the permanent measures are provided. Temporary earth slopes that are to be
exposed shall be covered with organic erosion control blanket (ECB).
3.2.4 Sediment control measures such as check dams/ temporary earth drains, silt
fences, turfing, silt traps, wheel washing facility and sediment ponds shall be constructed prior
to commencement of work and shall be maintained.
MUDAJAYA CORPORATION P a g e 10 |
TUN RAZAK EXCHANGE: CADANGAN PEMBANGUNAN SEBUAH JAMBATAN
BERTINGKAT METHOD STATEMENT FOR CABLE INSTALLATION
3.3.1 Air Quality control to be complied with Project EMP and DEIA Approval Condition.
3.3.1 Site clearance and earthwork shall be carried out in stages to minimize the exposed soil.
3.3.2 Vehicle washing facilities shall be provided at site exit. Public roads shall be kept clear of
soil and cleaned.
3.3.3 Traffic control such as speed limit and traffic volume restrictions to be implemented
especially at sensitive areas.
3.4.1 Noise and vibration control to be complied with Package EMP, DEIA Approval Condition
and General Specification Section 6.3
3.4.2 Movement of heavy vehicles shall be restricted to daytime working hours and minimized
during night time. Construction work during night time shall get the approval from PDP and local
authorities.
3.4.3 Noise generating equipment and machinery shall be inspected regularly and maintained in
good working condition. Noise and vibration emitting from equipment shall be placed away from
sensitive receptors.
3.5.1 Water pollution control to be complied with Package ESCP, Package EMP, DEIA Approval
Condition.
3.5.2 Surface run-off shall be treated prior discharged and shall not exceed the establish value or
quantity.
3.5.3 The earthworks activity will cease if the final silt discharge level exceeds the establish
value. The activities will only be resumed upon rectification and all the control measures are taken
care off.
3.6.1 All types of waste shall be segregated, stored and disposed of in accordance with Project
EMP, DEIA Approval Condition, Waste Management Plan.
3.6.3 Waste containers and storage areas shall be enough capacity to contain all waste
generated.
3.6.4 Scheduled waste shall be properly stored and disposed by licensed contractors at
approved facilities.
4.1.1 The general requirements for underground piloting work shall be in accordance
with project specification and requirement.
MUDAJAYA CORPORATION P a g e 11 |
TUN RAZAK EXCHANGE: CADANGAN PEMBANGUNAN SEBUAH JAMBATAN
BERTINGKAT METHOD STATEMENT FOR CABLE INSTALLATION
4.2.1 All inspection and testing involved shall be in accordance to the Inspection and
Test Plan and Inspection Checklist.
4.3.1 Detail implementations for checklist mentioned in the Inspection Checklist and Test
Plan attached.
MUDAJAYA CORPORATION P a g e 12 |