SA007-SC-MOM-Masafi-#13 - 25.05.22 HSE Reviewed
SA007-SC-MOM-Masafi-#13 - 25.05.22 HSE Reviewed
Attachments:
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 1 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
Entry to any Aramco Facilities shall not be allowed without full immune against Covid-19.
All remaining workers shall be Immune before the next meeting (20-Feb-2022)
All Workers must be vaccinated with 3 doses of vaccine. (27-Mar-2022) MASAFI 27/03/22
The presence of the HSE Supervisor from MASAFI in the Weekly Meeting is mandatory.
The MASAFI was reminded to ensure compliance with the below regulations & procedures:
Saudi Arabia Labor Law
Saudi Arabia General Environment Regulations
Saudi Aramco Construction Safety Manual
Saudi Aramco General Instructions
Saudi Aramco Schedule D
SICIM Contractor Site Safety Plan
SICIM Environment Management Program
Sicim INFO
SICIM Hazard Identification Plan
SICIM Emergency Response Plan
SICIM Permit to Work Procedure
SICIM Heat Stress and Prevention Plan
SICIM Fall Protection Plan
SICIM Journey Management Plan
MASAFI to carry out all relevant training related to the aforementioned requirements
MOS-10 Nos were received by Masafi and 8 Nos were approved by Aramco
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 2 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
SICIM informed MASAFI to send prior notification (HSE + Const.) for any material
transferring to BS-2.
No materials are to be transported from Agdah Road, the only approved traffic route for
material transportation to BS-2 is from Marabah Dam (as shown in SICIM Traffic and
Journey Management Plan).
Always complete the “JAPL-F-HE-024 Load Transportation Checklist” before starting any MASAFI INFO
material movement to BS-2. SICIM HSE Representative signature is compulsory for
validation of this checklist.
It was reminded to MASAFI to mobilize Boom Truck for Transportation of Material at BS-1 &
BS-2.
SICIM inform MASAFI to arrange the Ambulance along with Male Nurse at BS1 & BS2. (20
Mar-22)
Stated that all Heavy Equipment & operators are certified as per SA GI 7.025, following
documents shall be made available along with HE / Operators
All drivers and heavy equipment operators in mountainous areas shall be evaluated by
SICIM HSEM & CM before mobilization to site, authorization pass shall be given to
driver/operator after qualifying practical test. In addition, Vehicles and equipment are to be
ensured for suitability in the mountainous areas.
MASAFI INFO
1.7 Training
MASAFI to ensure all employees arriving at project sites shall be scheduled with HSE
training (Mandatory & Job-specific). Employees shall not be mobilized to perform any
activity without the mandatory HSE induction Course offered by SICIM. MASAFI CO Shall
conduct daily TBTs to discuss risks associated with the job and potential hazards.
Communication with Sicim only one focal person by email regarding training and schedules
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 3 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
Driver for BS2 shall go for assessment and test for driving in the mountain area.
SICIM informs MASAFI to take action to control traffic violations at BS2 and follow SICIM
Traffic Journey Plan.
The MASAFI confirmed Welfare facilities will be provided within one week. (8/12/2021).
MASAFI confirmed that the Waste Management agreement shall be finalized on or before
29-12-2021.
MASAFI 31/03/2022
MASAFI informed that Waste Management Facilities and office will be mobilized at BS-2
before the next weekly meeting. (30-01-2022) next Date 06-03-2022
MASAFI informed that Waste Management Contract not yet closed and Facilities & Office
for BS-2 will be mobilized before next weekly meeting (28-02-2022) ongoing negotiation
with RISAL
Certified First aider shall be provided by the MASAFI as per Saudi MOH requirement a ratio
of 10:1 shall be maintained. A Minimum of 36-Unit First Aid Cabinet shall be readily
available near the worksite.
Masafi informed that 3 people will get Certification before the next meeting (20-Feb-2022)
MASAFI OPEN
Agreement with the health facility/ hospital is already done and the MASAFI will provide a
copy of the agreement by 6/12/21.
The MASAFI has sent valid insurances, which are going to expire end of December 2021.
MASAFI informed that insurance auto-renewed before expiring one week. (Closed)
Aramco Accepted the Camp Facility of Masafi and advised to maintain the same
requirements at all times.
MASAFI INFO
1.11 Scaffolding material
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 4 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
The contractor was informed to provide MTC load test reports and manuals before starting
of scaffolding activity.
SICIM Inform MASAFI for submitting the Scaffolding Plan before 3 Weeks to start
scaffolding activities.
Current Situation regarding Permit to Work System was created by Masafi So Masafi shall
arrange Work Permit Receiver and Permit from ARAMCO before starting any activity.
MASAFI INFO
NO PERMIT NO WORK
From instructions of Aramco Contractor will continue to issue the PTW for both BS1 & BS2.
RFI’s & NCR Status (MSAFI shall update the tabled info as of Thu 26-May-22)
RFI STATUS
Discipline
Reject Rate
Accept
Cancel
Reject
Open
Issue
%
Status
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 5 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
Construction 3
3 0
Subcontractor INCR
Construction 3
2 1
Total 6 0 0 1
5
The MASAFI is requested to provide the CV of the Qc Inspector per each discipline by
work schedule and needs 30 days in advance.
Civil QC: Sabir Ali refused to join Masafi that’s why his Aramco Interview was cancelled.
2nd QC Civil Syed Hammad Ullah CV submitted and waiting for an Interview.
3rd QC Civil Raja Saqlain CV received but his agreement not finalized with MASAFI once
will finish then SICIM Proceed for interview.
Plumbing & HVAC: The CV of the HVAC/plumbing inspector has been already approved
and mobilized by SICIM on behalf of Masafi.
RTR Laminator: Masafi shall organize Certification Program RTR Laminators shall be
provided by Future Pipe (RTR Manufacturer). The certification Process shall be started
immediately and Laminators shall be mobilized at the site before 25-02-2022.
Jawad will be sending the documents of the RTR laminator and supervisor to the Sicim Qc
manager
15/11/2021
E&I: CV will be submitted by mid of January 22. (OPEN) recommended CV provided by
SICIM. CV to be submitted by 27-Mar-2022.
Masafi shall provide enough QC inspectors to cover all the inspections at BS1 and
BS2
Each inspector must have a CBT card and previous experience with Saudi Aramco.
MASAFI to submit a list of tools, devices, and equipment to be calibrated. INFO 15/11/2021
MASAFI shall make sure of the on-time availability of RICI technicians for Testing required
at the site.
The contractor asked the MASAFI to provide an Excel log of testing equipment to monitor
expiry dates. (OPEN)
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 6 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
MASAFI shall have a Calibration Procedure and required to submit to SICIM for info
MASAFI shall attach Calibration log (share the controlled document through mail on
every Saturday with SICIM) updated revision – along with MOM.
2.3 Batching Plant and Concrete Mix design (CIVIL QCS to update)
The MASAFI is requested to provide all required documents to get Aramco’s approval for
the batching plant.
2nd Volumetric Batch Plant and Concrete Pump are mobilized at the site on 09-02-2022. MASAFI/
16/11/2021
SICIM
Masafi to Submit VALID Documents for Inspection and Approval ASAP of the 2 nd
Batching
Plant.
RAW MATERIAL for Concrete Shall be stored near to Building to avoid delay during
pouring.
Masafi to submit Inter-discipline Clearance form to Sicim for review and concurrence.
SICIM QAM informed MASAFI that the service provider is having a contract exceeding 6
months duration.
INFO
Hence, MASAFI will be monitored for quality deliverables compliant to Sch. Q, as applicable MASAFI
and will be subjected to internal quality audits as applicable and required by Sch.Q OPEN
requirements.
MASAF (Project Manager & Quality Lead) agreed and noted the deliverables to be
submitted.
MASAFI 20-Feb-22
1. MASAFI should submit a Site Quality Control Procedure for review and approval of
SICIM QA/QC.
The QCP shall address the brief scope of work, construction schedule, quality
planning, responsibilities & authorities clearly defined, quality documentation related
to work procedures / MOS, materials, preservation, resource planning, testing, and
inspection requirements. Informed and explained to the QC Lead related to the
required elements to be addressed and incorporated
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 7 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
iii. Service Contract Record Books retention and handing-over flow chart
3. Daily RFI schedule shall be e-mailed to MASAFI Project manager and keeping
SICIM (PM/CM/QCM/QCS) in the loop
7. MASAFI shall strictly comply with Aramco approved Project Quality Plan as
applicable to their scope of work.
MASAFI shall strictly comply with Aramco approved (SICIM) NCR Procedure
2.6 Pro-active Approach to face Upcoming 60% Construction Quality Audit: OPEN
SICIM informed that MASAFI should conduct internal assessment (with the support of
SICIM QCS) and identify the quality findings related to ongoing construction works on 15-Jun
their SOW, on or before 15-Jun-22
SICIM requested MASAFI to determine the root cause of all deficiencies found during
internal assessment and apply proper corrective actions to resolve on or before 25-Jun- 25-Jun
22
MASAFI
SICIM informed that Aramco approved 3rd party Lead Auditor will conduct quality audit
on construction scope of work (on SICIM & service providers) around 25-Jun-22 and Action
hence the above actions need to be completed to minimize external Needed
FINDINGS/CARs/NCRs during the audit.
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 8 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
3.1 MASAFI shall send BOQ to Contractor PQS for material verification approval with
relevant 9 COM. (OPEN)
Material List not yet submitted MASAFI promised for this week (02/12/21)
The MASAFI is reminded about the different steps of inspection regarding Vendor and
Project inspections.
Approval of Project Materials (Bill of Material) shall be the BOQ with applicable 9COM
number to verify the vendor inspection requirements, any RVL controlled materials, if you
have in procurement, shall be prepared dedicated material requisition (MR), with Sicim MASAFI 17/11/2021
Format. For contractor and company’s VID review and approval. Before placing the order,
you shall get NO Objection from VID to place the order.
All project material shall follow the procurement process for each level of inspection as per
SAEP-1150 and 1051.
MASAFI to provide Procurement plan and Schedule level III by 28/11/21. (OPEN)
The Contractor points out that the MASAFI didn’t send any updates on the Procurement to
date.
Concrete Repair to be submitted with attached Approved Vendor, Material Name & Material MASAFI/
INFO
DATA Sheet. For Approval. SICIM
3.4 Transmittal
The attachment Issue shall be discussed and solved with Mr. Riyaz IT Engineer of Sicim.
INFO
The contractor warned that all files sent by Masafi cannot be opened due to the internal
system protection policy, so Masafi is asked to use another platform.
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 9 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
MASAFI 11/11/2021
Precast drawings / Shop Drawings
MASAFI shall submit Shop Drawings of Penetration/Openings in Slabs or Walls for MEP in
3weeks up to 13-03-2022.
MASAFI shall compare BBS and Rebar arrangement details for Foundations and Concrete MASAFI Info
Structure, if any discrepancies Red Mark drawing to be submitted and approved before
inspection and pouring.
The contractor mentioned mobilizing separate Manpower to cover upcoming activities for
BS-2 and also the Contractor informed Masafi to increase the manpower to start work MASAFI 30-01-2022
parallel at both locations BS1 and BS2.
MASAFI to comply with Manpower as per Histogram by end of this week. 17-Feb-2022
The Contractor informs the MASAFI that the material resulting from the excavations in
progress must be transported to the appropriate landfills as indicated in Attachment I item
3.1 & 3.2.
MASAFI INFO
MASAFI will be responsible for the disposal of extra soil from the project location.
The MASAFI will use the excavated material for Backfilling (after Screening) and Extra
Material Shall be disposed of from the Site by MASAFI.
MASAFI INFO
4.5 DRAWING
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 10 of 11
Relocate Jazan-Abha Refined Products Pipeline Project
BI#10-00875 Contract# 6600045122
Weekly Coordination Meeting Masafi
MASAFI is reminded to use Latest Drawing at the site to avoid any mistake or rework.
5.2 Masafi Management shall attend Weekly meetings at the Ad-Darb office. once in a
month (Middle of Month) 12th jun-22
MASAFI
6. AOB
6.2 CONTRACTOR informs that no activity will be allowed without Approval of equipment,
MASAFI INFO
material, QC Personal, and all relevant documents.
Notwithstanding the MOM, nothing stated in this document shall relieve MASAFI from any contractual obligations Page 11 of 11