Opex' HDD - Pipelaying of 250Mm (Rail Road Crossing)
Opex' HDD - Pipelaying of 250Mm (Rail Road Crossing)
OPEX'
HDD - PIPELAYING OF 250MM (RAIL ROAD CROSSING)
I/N DESCRIPTION QTY UNIT
1 HDD - PARK 45.00 LM
2 MOBILIZATION (PARK) 1.00 LS
3 CIVIL WORKS (ENTRY EXIT) 1.00 LS
3 MOBILIZATION 1.00 LS
TOTAL OPEX
BID COST
BID COST (LESS VAT)
PROFIT
UNIT COST TOTAL COST
5,000.00 225,000.00
22,500.00 22,500.00
TOTAL OPEX 247,500.00
BID COST 450,000.00
BID COST (LESS VAT) 396,000.00
PROFIT 148,500.00
DED IN OPEX
PIPELAYING (UPVC) 3'' 0.05 0.075 0.1 0.15 0.2 0.25 0.3
0.9
I/N DESCRIPTION TOTAL
L W H/D UNIT WT OBSTR (QTY) L (ACTUAL)
1 CONCRETE/ASPHALT CUTTING 1.5 1.5 12 1 12.00
2 CONCRETE BREAKING 1.5 1.5 0.3 1.35 1 1.35
3 EXCAVATION 1.5 1.5 1.5 6.75 1 6.75
4 SAND BEDDING 1.5 1.5 1.2 5.4 1 5.40
5 BACKFILLING AND DISPOSAL 1.5 1.5 1.5 0.0490875 6.651825 1 6.65
6 MARKER TAPE 1.5 3 1 3.00
7 BASE COARSE 1.5 1.5 0.15 0.675 1 0.68
8 SUB - BASE COARSE 1.5 1.5 0.15 0.675 1 0.68
9 CONCRETING 1.5 1.5 0.3 1.35 1 1.35
TOTAL
DESCRIPTION
PIPELAYING TO RESTORATION 3''
INTERCONNECTION / MISC
OPEX
TIP
PROFIT
PROFIT - (OPEX +12%)
DIRECT COST/LM DIRECT COST/UNIT