Rcdplate3 Basilio Cubillan Leynes Mutiangpili Rivera
Rcdplate3 Basilio Cubillan Leynes Mutiangpili Rivera
3
GRAVITY LOADS
A laboratory plate submitted in partial
fulfillment of the requirements for the
course
Principles of Reinforced/Prestressed
Concrete (Lab)
CE0037L
Submitted by:
Basilio, Aaron C.
Cubillan, Ariella Sofia D.
Leynes, Jan Rvin V.
Mutiangpili, Marc Andre C.
Rivera, John Carlo S.
Submitted to:
Engr. Godofredo M. Mendoza
FEU Tech
A. LOCATION
BRGY. BAYONGON SAMPALOC, QUEZON
BEAM SIZE
MAIN BEAM 250 MM X 500 MM = 23.6 KN/M3 (0.25 X 0.5) =
2.95KN/M
JOIST 200 MM X 400 MM = 23.6 KN/M3 (0.2 X 0.4) =
1.888KN/M
HEIGHT OF WALL
C. MATERIALS
MISCELLANEOUS
➔ ELECTROMECHANICAL 0.10 KPA
➔ CEILING
GYPSUM BOARD X THICKNESS(12MM) – 0.008 KPA/MM X 12MM = 0.096
KPA
➔ SLAB FINISHING
CEMENT FINISH, 25MM 1.53 KPA
➔ EXTERIOR WALL
◆ CONCRETE MASONRY THICKNESS (200MM), 19.6 KN/M3 , BOTH FACES
ARE PLASTERED – 1.72 + 0.24(2) = 2.2 KPA
➔ INTERIOR WALL
◆ CONCRETE MASONRY THICKNESS (150MM), 19.6 KN/M3 , BOTH FACES
ARE PLASTERED – 1.34+ 0.24(2) = 1.82 KPA
● BEAM A-B
2.85 2
5.546 (2) 5.546 (2.85) 3− ( )
W = 2
+ 3
[ 2
5.2
] + 2.95
= 15.608 kN/m
● BEAM B-D
5.546 (2) 5.546 (4.5)
W = 2
+ 3
+ 2.95 + 7.189
= 24.004 kN/m
● BEAM D-E
5.546 (2) 5.546 (3)
W = 2
+ 3
+ 1.888 + 8.69 + 2.95
= 24.62 kN/m
● BEAM E-F
2 2
5.546 (2) 3− ( 2.2 )
W = 3
[ 2
] + 2.95 + 8.69
= 15.658 kN/m
DEAD LOADS ON FRAME ALONG GRID E (2ND FLOOR)
● BEAM 1-2
5.546 (2)
W = 3
+ 2.95
= 6.647 kN/m
● BEAM 2-3
3 2
5.546 (2.2) 5.546 (3) 3− ( 4.5 )
W = 2
+ 3
[ 2
] + 2.95 + 8.69
= 24.827 kN/m
● BEAM 3-5
2.2 2
5.546 (2.2) 5.546 (2.2) 3− ( )
W = 2
+ 3
[ 2
5
] + 2.95 + 8.69
= 24.095 kN/m
● BEAM 5-7
2.2 2
5.546 (2.2) 3− ( 2.26 )
W = 3
[ 2
] + 2.95
= 7.124 kN/m
DEAD LOAD (ROOF DECK)
a. SDL = 1.896kPa
b. SLAB = 23.6kN/m3 x 0.125m = 2.95kPa
TOTAL = 4.846kPa
c. SELF-WEIGHT OF BEAM = 23.6kN/m3 x (0.25m x 0.5m) = 2.95kN/m
d. JOIST = 23.6kN/m3 x (0.2m x 0.4m) = 1.888kN/m
● BEAM A-B
2.85 2
4.846 (2) 4.846 (2.85) 3− ( )
W = 2
+ 3
[ 2
5.2
] + 2.95
= 14.01 kN/m
● BEAM B-D
4.846 (2) 4.846 (4.5)
W = 2
+ 3
+ 2.95
= 15.065 kN/m
● BEAM D-E
4.846 (2) 4.846 (3)
W = 2
+ 3
+ 1.888 + 2.95
= 14.53 kN/m
● BEAM E-F
2 2
4.846 (2) 3− ( 2.2 )
W = 3
[ 2
] + 2.95
= 6.461 kN/m
DEAD LOADS ON FRAME ALONG GRID E (ROOF DECK)
● BEAM 1-2
4.846 (2)
W = 3
+ 2.95
= 6.181 kN/m
● BEAM 2-3
3 2
4.846 (2.2) 4.846 (3) 3− ( 4.5 )
W = 2
+ 3
[ 2
] + 2.95 + 8.69
= 14.473 kN/m
● BEAM 3-5
2.2 2
4.846 (2.2) 4.846 (2.2) 3− ( )
W = 2
+ 3
[ 2
5
] + 2.95 + 8.69
= 13.833 kN/m
● BEAM 5-7
2.2 2
4.846 (2.2) 3− ( 2.26 )
W = 3
[ 2
] + 2.95
= 6.597 kN/m
LIVE LOAD (2ND FLOOR & ROOF DECK)
LIVE LOADS ON FRAME ALONG GRID 2 (2ND FLOOR AND ROOF DECK)
● BEAM A-B
2.85 2
1.9(2) 1.9(2.85) 3−( )
W = 2
+ 3
[ 2
5.2
]
= 4.336 kN/m
● BEAM B-D
2.9(2) 1.9(4.5)
W = 2
+ 3
= 5.75 kN/m
● BEAM D-E
2.9(2) 1.9(3)
W = 2
+ 3
= 4.8 kN/m
● BEAM E-F
2 2
2.9(2) 3−( 2.2 )
W = 3
[ 2
]
= 2.101 kN/m
LIVE LOADS ON FRAME ALONG GRID E (2ND FLOOR AND ROOF DECK)
● BEAM 1-2
2.9(2)
W = 3
= 1.933 kN/m
● BEAM 2-3
3 2
2.9(2.2) 1.9(3) 3−( 4.5 )
W = 2
+ 3
[ 2
]
= 5.618 kN/m
● BEAM 3-5
2.5 2
2.9(2.2) 1.9(2.5) 3−( )
W = 2
+ 3
[ 2
5
]
= 5.367 kN/m
● BEAM 5-7
2.2 2
2.9(2.2) 3−( 2.26 )
W = 3
[ 2
]
= 2.182 kN/m