Daily Liner Installation Report: Project Information Document Information
Daily Liner Installation Report: Project Information Document Information
Daily Liner Installation Report: Project Information Document Information
CI-PR3-LP-F11-Rev00
Daily liner installation report
Local Workers CITILOG National Workers CITLOG Expatriate Workers ESSAKANE EQUIPMENT
ESSAKANE SITE ESSAKANE SITE ESSAKANE SITE ESSAKANE SITE
Number of workers 14 Number of workers 1 Number of workers 3 Manitou 1
Hours worked per day 9 Hours worked per day 9 Hours worked per day 9 Vehicles 1
Total sum of hours worked 126 Total sum of hours worked 9 Total sum of hours worked 27 Generators 4
06:00 We arrive at TSF Essakane, after a safety briefing, our activities will focus on APT, repairs and vacuum testing to complete
the installation process of textured HDPE 1.5 geomembrane in this project.
06:45 The tensiometer samples show a perfect calibration of the PX 06 extruder, so we will continue with the repairs (patches).
7:00 The PX 06 extruder is in optimal conditions to be used, this is deduced by values of samples made in a tensiometer that have
been totally satisfactory.
08:00 We have vacuum tested the repairs to ensure the correct application of the extrusion. The results have been satisfactory in
each of them.
14:00 The PX 06 extruder is in optimal conditions to be used, this is deduced from the values of samples made in a tensiometer
that have been totally satisfactory.
Observations
our technical supervisor Ruben Sanchez, continues with the training that culminates today of the candidates appointed by the
Essakane Mine
Photographic report
Date and place Date and place Date and place Date and place