Professional Documents
Culture Documents
M4 - L4 - Energy Engg - Hydel Power Plant - 4 - GB
M4 - L4 - Energy Engg - Hydel Power Plant - 4 - GB
(18ME81)
[As per Choice Based Credit System (CBCS) Scheme]
Module – 4 Lecture – 4
Faculty In-charge:
Mr. Girish B.
Assistant Professor
Dept. of Mechanical Engg.
Bangalore Institute of Technology
Bangalore
1
Learning Objectives
2
Numerical problem 2
2. The mean monthly discharge for 12 months at a particular site of river is
tabulated below:
i. Draw hydrograph and the flow duration curve on the graph sheet and find the
average monthly flow.
ii. Determine the power available at mean flow of water if available head is 80 m
Solution: at the site and overall efficiency of generation is 80%. Take 30 days in a month.
Data: Available head, H = 80 m; Overall efficiency, o = 80 %
3
Numerical problem 2 (continued)
4
Numerical problem 2 (continued)
Qav = (500+200+1500+2500
+3000+2400+2000+1500+
1500+1000+800+600) / 12
Qav = 562.63 m3 /s
5
Numerical problem 2 (continued)
6
Numerical problem 2 (continued)
7
Numerical problem 2 (continued)
Power developed in MW
P = o g Qav H /106
P = 353.24 MW
8
Numerical problem 3
3. For a particular site of the river, the following run off data was recorded for
ten months. Find the minimum flow available throughout the year, if the
storage capacity at the site is 100 million m3
9
Numerical problem 3 (continued)
Solution: i). To draw Mass curve Mass curve
10
Numerical problem 3 (continued)
Solution: To find minimum available flow rate throughout the period
Draw tangents at points ‘a’ , ‘b’ and ‘c’
such that the distance x = 100 millions
c
of m3.
The flow rates are calculated by
measuring the slopes at points ‘a’ , ‘b’
and ‘c
At point ‘a’,
flow rate = 72.6 millions of m3
At point ‘b’,
flow rate = 166.4 millions of m3
At point ‘c’,
flow rate = 137.6 millions of m3
11
Numerical problem 4
4. The data for twelve months flow at a particular site is given below:
Find
i. The required reservoir capacity for the uniform flow of 50 million
cu-m per month throughout the year.
ii. Spill way capacity.
iii. Average flow capacity if whole water is used and required
capacity of the reservoir for this condition.
12
Numerical problem 4 (continued)
Solution: To draw Mass curve Mass curve
13
Numerical problem 4 (continued)
Solution: To find i). Storage capacity and ii). Spill way capacity
Mass curve From the graph,
i). Storage capacity
For finding the capacity of the reservoir for
uniform flow of 50 million cu-m per month
throughout the year, draw triangle xyz in
which xy represents one month and yz
represents 50 million cu-m
Draw parallel lines to the line xz through the
points ‘e’ and ‘g’ which are the apexes of
g mass curve.
The greatest departure of the mass curve
f from these lines represents the storage
e capacity.
∴ Storage capacity = 82 x 106 m3
14
Numerical problem 4 (continued)
Solution: To find iii). Average flow capacity
Mass curve From the graph,
iii). Average flow capacity
Join the points ‘a’ and ‘b’ then the slope of
the line ab represents the uniform
discharge throughout the year.
= 980 / 12 x 106 = 81.7 x 106 m3 / month
In this case,
storage capacity required = 230 x 106 m3
15
Summary
16
References & Suggested Readings
17