Alexandria Shipyard Company: Quality Control Manual
Alexandria Shipyard Company: Quality Control Manual
ASY-ASME-1
UT is not carried out by ASY for fulfilling Code requirements. If required in the
future, UT will be performed by personnel whose qualifications comply with
the requirements of SNT-TC-1A Current Code accepted Edition and
Construction Code. Written UT procedures qualified by demonstration,
approved by NDE Level III, authorized by QSD and accepted by the AI will be
used.
The ASY NDT department shall provide the following documents for review
and verification by QSD.
All above documents shall be verified and approved by QSD. A copy of all the
above documents that shall be kept for records and for review by AI.
a) All code required NDE shall be performed at appropriate stages as per drawing
and ITP requirement based on NDE requisition issued by QC Inspector to NDT
Department.
b) In case of spot radiography, the spots shall be clearly marked on the job with
identification of the spot. AI shall be given the opportunity to mark the spots
for radiography.
d) All NDE results are evaluated by NDE Level II or Level III personnel. The
names of personnel who carried out and evaluated the results shall be clearly
indicated on reports. NDE reports shall be submitted to AI for his review and
acceptance.