Apex Institute Of Modern Studies Notes By : Khalid Rahim & Junaid khan

Quantity Lecture 1

CIVIL:

Civil is the branch of engineering science and related with Designing, Construction, and
maintenances of Building, Dams, Highways, Bridges, Tunnels and other structures.

QUANTITY:

It is the most important subject of Civil Engineering.

Quantity is an art in which we find the quantum or quantity of different building materials.
labors and its Rates.

DATA FOR ESTIMATE:

There are three things required for Quantity with the help of this data we find the quantity
easily.

1) Drawings. 2) Specification. 3) Rates.

SCALE:

There are two types of scale which we used in Quantity.

1) F.P.S System.
2) M.K.S System.

F.P.S SYSTEM:

It means Foot, Pound, Second system. This system is mostly used in Pakistan.

M.K.S SYSTEM:

It means Meter, Kilogram, Second system. This system is used basically in out Countries.
Quantity Lecture 1

AREA OF RECTANGLE:

AREA = LENGTH x BREADTH

AREA = 15’ x 10’

AREA = 150 sft

AREA OF CIRCULAR SHAPE:

RADIUS OF CIRCLE = 6 ft and DIAMETER OF CIRCLE = 12 ft

 AREA OF CIRCLE IN CASE OF RADIUS:

AREA = π r 2

AREA = 3.1415 x ¿

AREA = 3.1415 x 36

AREA = 113.09 sft

 AREA OF CIRCLE IN CASE OF DIAMETER:


2
πd
AREA =
4

( 12 )2
AREA = 3.1415 x
4

144 ❑
AREA = 3.1415 x
4

AREA = 3.1415 x 36
AREA = 113.09 sft

Apex Institute Of Modern Studies Notes By: Khalid rahim

Quantity Lecture 2

AREA OF SEMI CIRCULAR SHAPE:

RADIUS OF SEMI CIRCLE = 5’ ft and DIAMETER OF SEMI CIRCLE = 10’ ft

 AREA OF SEMI CIRCLE IN CASE OF RADIUS:

AREA = π r 2 x ½

π r2
AREA =
2

AREA = 3.1415 ¿ ¿

3.1415(25)
AREA =
2

78.58
AREA =
2

AREA = 39.26 sft

 AREA OF SEMI CIRCLE IN CASE OF DIAMETER:

2
πd 1
AREA = x
4 2

π d2
AREA =
8

AREA = 3.1415 ¿ ¿

3.1415(100)
AREA =
8
314.15
AREA =
8

AREA = 39.26 sfts

Quantity Lecture 2

AREA OF REGUAR SHAPE TRIANGLE:


 FORMULA FOR TRIANGLE:

AREA =
√3 X ¿
4

AREA =
√3 X ¿
4

AREA = 0.433 X 36

AREA = 15.58 sft

AREA OF IRREGULAR SHAPE TRIANGLE:


 FORMULA FOR TRIANGLE:

AREA =√ s ( s−a )( s−b ) ( s−c )

S = Semi Parameter of Triangle

First we find the semi parameter of triangle

a+b+c
S=
2

8+9+12
S=
2

S = 14.5 ft

Now put the values in above formula

AREA = √ 14.5 (14.5−8 ) ( 14.5−9 ) (14.5−12)


AREA = √ 14.5 X 6.5 X 5.5 X 2.5

AREA = √ 1295.93

AREA = 35.99 sft

Say’s = 36 sft.

AREA OF IRREGULAR SHAPE TRIANGLE BY SECOND METHOD:


 FORMULA FOR TRIANGLE:

aXb
AREA =
2

8X9
AREA =
2

72
AREA =
2

AREA = 36 sft.
Apex Institute Of Modern Studies Notes By : Khalid rahim & Junaid Khan
Quantity Lecture 3

AREA OF IRREGULAR SHAPE:


AREA =√ ( s−a )( s−b ) (s−c ) ( s−d )

S = Semi Parameter of Triangle

First we find the semi parameter of triangle

a+b+ c+ d
S=
2

13+9+12+8 42
S= =S=
2 2

S = 21 ft

Now put the values in above formula

AREA = √ ( 21−12 ) ( 21−8 ) ( 21−13 )( 21−9)

AREA = √ 9 X 13 X 8 X 12

AREA = √ 11232

AREA = 106 sft.

AREA OF PANTAGON:
NS 2 180
AREA = X cot
4 N
1
Cot =
tan

N = No’s of sides

S = Length of sides

( 6 ) ( 5 )2 180
AREA = X cot
4 6

AREA = 37.5 x cot30

AREA = 37.5 x 1.732

AREA = 64.95 sft

VOLUME:

Length = 2 ft

Breadth = 2 ft

Height = 2 ft

Volume = Length X Breadth X Height

Volume = 2 X 2 X 2 = 8 cft

Surface Area = 6 (L x B)

Surface Area = 6 (2 X 2)

Surface Area = 24 sft


Apex Institute Of Modern Studies Notes By : Khalid rahim & Junaid Khan

Quantity Lecture 4

NUMBERS OF BRICKS IN WALL:

LENGTH OF WALL = 20 ft

BREADTH OF WALL = 0.75 ft

HEIGHT OF WALL = 11 ft

 FIRST WE FIND THE VOLUME OF WALL (QUANTITY OF WALL).

QUANTITY OF WALL = L x B x H
QUANTITY OF WALL = 20 x 0.75 x 11

QUANTITY OF WALL = 165 cft

 WE KNOW THAT WE USE 13.5 BRICKS IN 1cft.

NUMBERS OF BRICKS = QUANTITY OF WALL x 13.5

NUMBERS OF BRICKS = 165 x 13.5

NUMBERS OF BRICKS = 2227.5 BRICKS

SAY’S = 2228 BRICKS

Quantity Lecture 4

BRICKS WORK IN CIRCULAR WALL:

INTERNAL DIAMETER = 6 ft

EXTERNAL DIAMETER = 7.5 ft

CENTRAL DIAMETER = 6.75 ft

THICKNES OF WALL = 0.75 ft

HEIGHT OF WALL = 15 ft

FORMULA FOR THE LENGTH OF WALL:

LENGTH OF WALL = π x d (d= Diameter)

LENGTH OF WALL = 3.1415 x 6.75

LENGTH OF WALL = 21.20 ft


QUANTITY OF WALL = L x B x H

QUANTITY OF WALL = 21.20 x 0.75 x 15

QUANTITY OF WALL = 238.56 cft

NUMBERS OF BRICKS = QUANTITY OF WALL x 13.5

NUMBERS OF BRICKS = 238.56 x 13.5

NUMBERS OF BRICKS = 3220.6 BRICKS

SAY’S = 3222 BRICKS

Apex Institute Of Modern Studies Notes By : Khalid rahim & Junaid Khan
Quantity Lecture 5

ANALYSIS FOR MASONARY WORK:

LENGTH OF WALL = 18 ft

BREADTH OF WALL = 0.75 ft

HEIGHT OF WALL = 11 ft

RATIO OF MORTOR = 1:4

 FIRST WE FIND THE VOLUME OF WALL (QUANTITY OF WALL).

QUANTITY OF WALL = L x B x H

QUANTITY OF WALL = 18 x 0.75 x 11


QUANTITY OF WALL = 148.5 cft

 WE KNOW THAT WE USE 13.5 BRICKS IN 1cft

NUMBERS OF BRICKS = QUANTITY OF WALL x 13.5

NUMBERS OF BRICKS = 148.5 x 13.5

NUMBERS OF BRICKS = 2004.75 BRICKS

SAY’S = 2005 BRICK

WE KNOW THAT WE USE THE RATIO =1:4

SUM OF RATIO = 1 + 4 = 5

Quantity Lecture 5

WET QUANTITY OF MORTOR = 148.5 cft

30
DRY QUANTITY OF MORTOR = 148.5 x
100

DRY QUANTITY OF MORTOR = 44.55 cft

RATIO OF CEMENT
QUANTITY OF CEMENT = DRY QUANTITY OF MORTOR
∑ OF RATIO x
1
QUANTITY OF CEMENT = x 44.55
5

QUANTITY OF CEMENT = 8.91 cft

QUANTITY OF CEMENT
NUMBERS OF BAGS OF CEMENT =
1.25

8.91
NUMBERS OF BAGS OF CEMENT =
1.25

NUMBERS OF BAGS OF CEMENT = 7.128 BAGS

SAY’S = 8 BAGS

RATIO OF SAND
QUANTITY OF SAND = DRY QUANTITY OF MORTOR
∑ OF RATIO x
4
QUANTITY OF SAND = x 44.55
5

QUANTITY OF SAND = 35.64 cft

 (1.25 cft IS THE SIZE OF ONE CEMENT BAG)

Quantity Lecture 6

ANALYSIS FOR MASONARY WORK:

WALL 1:

LENGTH OF WALL = 15 ft

BREADTH OF WALL = 0.75 ft

HEIGHT OF WALL = 10 ft

WALL 2:

LENGTH OF WALL = (12.75 – 0.75) = 12 ft

BREADTH OF WALL = 0.75 ft

HEIGHT OF WALL = 10 ft

RATIO = 1:3
QUANTITY OF WALL 1 = L x B x H

QUANTITY OF WALL 1 = 15 x 0.75 x 10

QUANTITY OF WALL 1 = 112.5 cft

QUANTITY OF WALL 2 = L x B x H

QUANTITY OF WALL 2 = 12 x 0.75 x 10

QUANTITY OF WALL 2 = 90 cft

TOTAL QUANTITY OF ‘’L’’ SHAP WALL = QUANTITY OF WALL 1 + QUANTITY OF WALL 2

TOTAL QUANTITY OF ‘’L’’ SHAP WALL = 112.5 + 90

TOTAL QUANTITY OF ‘’L’’ SHAP WALL = 202.5 cft

NUMBERS OF BRICK IN ‘’L’’ WALL = TOTAL QUANTITY OF ‘’L’’ WALL x 13.5

Quantity Lecture 6

NUMBERS OF BRICK IN ‘’L’’ WALL = 202.5 x 13.5

NUMBERS OF BRICK IN ‘’L’’ WALL = 2733.75 BRICKS

SAY’S = 2735 BRICKS

RATIO OF MORTOR = 1:3

SUM OF RATIO = 1 + 3 = 4

WET QUANTITY OF MORTOR = 202.5 cft

30
DRY QUANTITY OF MORTOR = 202.5 x
100

DRY QUANTITY OF MORTOR = 60.75 cft

RATIO OF CEMENT
QUANTITY OF CEMENT = DRY QUANTITY OF MORTOR
∑ OF RATIO x
1
QUANTITY OF CEMENT = x 60.75
4
QUANTITY OF CEMENT = 15.18 cft

QUANTITY OF CEMENT
NUMBERS OF BAGS OF CEMENT =
1.25

15.18
NUMBERS OF BAGS OF CEMENT =
1.25

NUMBERS OF BAGS OF CEMENT =12.15 BAGS

SAY’S =13 BAGS

RATIO OF SAND
QUANTITY OF SAND = DRY QUANTITY OF MORTOR
∑ OF RATIO x
3
QUANTITY OF SAND = x 60.75
4

QUANTITY OF SAND = 45.56 cft

 (1.25 cft IS THE SIZE OF ONE CEMENT BAG)

Apex Institute Of Modern Studies Notes By : Khalid rahim & Junaid Khan

Quantity Lecture 7

BRICKS WORK IN ARCH WALL:

LENGTH OF WALL = 10.25 ft

BREADTH OF WALL = 0.75 ft


HEIGHT OF WALL = 13 ft

RADIUS OF WALL = 2 ft

DIAMETER OF WALL = 4 ft

RATIO OF MORTOR = 1:3

 QUANTITY OF PILLARS = 3(L x B x H)

QUANTITY OF PILLARS = 3(0.75 x 0.75 x 7)

QUANTITY OF PILLARS = 3(3.94)

QUANTITY OF PILLARS = 11.81 cft

 QUANTITY OF RECTANGULAR PORTION = L x B x H

QUANTITY OF RECTANGULAR PORTION = 10.25 x 0.75 x 6

QUANTITY OF RECTANGULAR PORTION = 46.125 cft


2
πd
 QUANTITY OF SEMI-CIRCULAR PORTION = x BREADTH OF WALL
8

QUANTITY OF SEMI-CIRCULAR PORTION = 2(3.1415 ¿ ¿ x 0.75)

QUANTITY OF SEMI-CIRCULAR PORTION = 2(6.28 x 0.75)

QUANTITY OF SEMI-CIRCULAR PORTION = 2 x 4.71

QUANTITY OF SEMI-CIRCULAR PORTION = 9.42 cft

 DEDUCTION IN QUANTITY OF RECTANGULAR PORTION = 46.125 – 9.42

DEDUCTION IN QUANTITY OF RECTANGULAR PORTION = 36.70 cft

 TOTAL QUANTITY OF ARCH WALL = 36.70 + 11.81

TOTAL QUANTITY OF ARCH WALL = 48.51 cft

 NUMBERS OF BRICK IN ARCH WALL = QUANTITY OF ARCH WALL x 13.5

NUMBERS OF BRICK IN ARCH WALL = 48.51 x 13.5

NUMBERS OF BRICK IN ARCH WALL = 654.95 BRICKS


SAY’S = 655 BRICKS

RATIO OF MORTOR = 1:3

SUM OF RATIO = 1 + 3 = 4

WET QUANTITY OF MORTOR = 48.51 cft

30
DRY QUANTITY OF MORTOR = 48.51 x
100

DRY QUANTITY OF MORTOR = 14.55 cft

RATIO OF CEMENT
QUANTITY OF CEMENT = DRY QUANTITY OF MORTOR
∑ OF RATIO x
1
QUANTITY OF CEMENT = x 14.55
4

QUANTITY OF CEMENT = 3.64 cft

QUANTITY OF CEMENT
NUMBERS OF BAGS OF CEMENT =
1.25

3.64
NUMBERS OF BAGS OF CEMENT =
1.25

NUMBERS OF BAGS OF CEMENT = 2.91 BAGS

SAY’S = 3 BAGS

RATIO OF SAND
QUANTITY OF SAND = DRY QUANTITY OF MORTOR
∑ OF RATIO x
3
QUANTITY OF SAND = x 14.55
4

QUANTITY OF SAND =10.91 cft

 (1.25 cft IS THE SIZE OF ONE CEMENT BAG)


Apex Institute Of Modern Studies Notes By : Khalid rahim & Junaid Khan

Quantity Lecture 8

QUANTITY OF SLAB:
LENGTH OF SLAB = 30 ft

BREADTH OF SLAB = 20 ft

HEIGHT OF SLAB = 0.5 ft

LENGTH OF SLAB x BREADTH OF SLAB x HEIGHT OF SLAB = 30 x 20 x 0.5

WET QUANTITY OF SLAB = 300

DRY QUANTITY OF SLAB = 300 x 1.54

DRY QUANTITY OF SLAB =462 cft

RATIO = 1:2:4

SUM OF RATIO = 1+2+4

SUM OF RATIO = 7

RATIO OF CEMENT
 QUANTITY OF CEMENT =
∑ OF RATIO x DRY QUANTITY OF SLAB
1
QUANTITY OF CEMENT = X 462
7

QUANTITY OF CEMENT = 66 cft

66
NUMBERS OF CEMENT BAGS =
1.25

NUMBERS OF CEMENT BAGS = 52.80 BAGS

SAY’Ss = 53 BAGS
RATIO OF SAND
 QUANTITY OF SAND =
∑ OF RATIO x DRY QUANTITY OF SLAB
2
QUANTITY OF SAND = X 462
7

QUANTITY OF SAND = 132 cft

RATIO OF CRUSH
 QUANTITY OF SAND =
∑ OF RATIO x DRY QUANTITY OF SLAB
4
QUANTITY OF CRUSH = X 462
7

QUANTITY OF CRUSH = 264 cft

Quantity Lecture 9 ( P.W.D Method Straight Wall )

Quantity Lecture 10 ( P.W.D Method “T “Shape Wall )

Quantity Lecture 11 ( P.W.D Method “L “ Shape Wall )

Quantity Lecture 12 ( P.W.D Method “ F & E” Shape Wall )

Quantity Lecture 13 ( P.W.D Method “H “Shape Wall )

Quantity Lecture 14 ( P.W.D Method “U” Shape Wall )

Quantity Lecture 15 ( P.W.D Method “ D” Shape Wall )

Apex Institute Of Modern Studies Notes By: Khalid rahim & Junaid Khan

Quantity Lecture 16
SEPARATE (OR) INDIVIDUAL WALL METHOD :
Sr Description of No' Lengt Breadt Heigh Quantity/
No's Work s h h t cft
             
1 Excavation          
  Long Walls 2 15.75 3 3.33 314.69
  Short Walls 2 7.75 3 3.33 154.85
TOTAL
          = 469.53
2 P.C.C          
  Long Walls 2 15.75 3 1 94.50
  Short Walls 2 7.75 3 1 46.50
TOTAL
          = 141.00
Brick work in/
3 foundation          
  Long Walls          
  1st step 2 14.75 2 0.67 39.53
  2nd step 2 14.41 1.67 0.67 32.25
  3rd step 2 14.08 1.33 1 37.45
  Short Walls          
  1st step 2 8.75 2 0.67 23.45
  2nd step 2 9.08 1.67 0.67 20.32
  3rd step 2 9.42 1.33 1 25.06
TOTAL
          = 178.06
4 D.P.C          
  Long Walls 2 13.5 0.75 1 20.25
  Short Walls 2 10 0.75 1 15
TOTAL
          = 35.25
Bricks work in
5 super/struc          
  Long Walls 2 13.5 0.75 12 243
  Short Walls 2 10 0.75 12 180
TOTAL
          = 423

CENTRE LINE METHOD :


Sr.No' Description of No' Lengt Breadt Heigh Quantity /
s Work s h h t cft
             

1 Excavation          

  For all Walls 1 47 3 3.33 469.53

2 P.C.C          

  In all foundation 1 47 3 1 141


Brick work in
3 foundation          

  1st step 1 47 2 0.67 62.98

  2nd step 1 47 1.67 0.67 52.5883

  3rd step 1 47 1.33 1 62.51


TOTAL
          = 178.0783

4 D.P.C          

  For all Walls 1 47 0.75   35.25


Brick work in super
5 struc          

  All walls 1 47 0.75 12 423

Apex Institute Of Modern Studies Notes By: Khalid rahim & Junaid Khan

Quantity Lecture 17
SEPARATE (OR) TNDIVIDUAL WALL
METHOD :
Sr.No' Description of No' Lengt Breadt Heigh Quantity /
s Work s h h t cft
             
1 Excavation          
  Long Walls 2 30.5 3 3.33 609.39
  Short Walls 3 9.75 3 3.33 292.21
TOTAL
          = 901.60
2 P.C.C          
  Long Walls 2 30.5 3 1 183.00
  Short Walls 3 9.75 3 1 87.75
TOTAL
          = 270.75
Brick work in
3 foundation          
  Long Walls          
  1st step 2 29.5 2 0.67 79.06
  2nd step 2 29.17 1.67 0.67 65.28
  3rd step 2 28.83 1.33 1 76.69
  Short Walls          
  1st step 3 10.75 2 0.67 43.22
  2nd step 3 11.08 1.67 0.67 37.19
  3rd step 3 11.42 1.33 1 45.57
TOTAL
          = 347.00
4 D.P.C          
  Long Walls 2 28.25 0.75   42.38
  Short Walls 3 12 0.75   27.00
TOTAL
          = 69.38
Brick work in super
5 struc          
  Long Walls 2 28.25 0.75 12 508.50
  Short Walls 3 12 0.75 12 324.00
TOTAL
          = 832.50

CENTRE LINE METHOD :


Total Length = 27.5'+27.5'+12.75'+12.75'+12.75' = 93.25 ft
Perfect Length =Length-junction x breadth/2 = ( 93.25'-2 x 0.75/2 = 92.5 ft )

Formula for Excavation = L+(B-T) & Formula for brick worck in foundation = L-(B-T)

Sr.No' Description of No' Lengt Breadt Heigh Quantity


s Work s h h t /cft

             

1 Excavation          

  For all walls 1 90.25 3 3.33 901.60

2 P.C.C          

  For all walls 1 90.25 3 1 270.75

3 Brick work in foundation          

  1st step 1 91.25 2 0.67 122.28

  2nd step 1 91.58 1.67 0.67 102.47

  3rd step 1 91.92 1.33 1 122.25


TOTAL
          = 347.00

4 D.P.C          

  For all walls 1 92.5 0.75   69.38

5 Brick work in super struc          

  All walls 1 92.5 0.75 12 832.50

Apex Institute Of Modern Studies Notes By: Khalid rahim & Junaid Khan

Quantity Lecture 18
APEX INSTITUTE OF MODERN STUDIES NOTE BY: JUNAID KHAN
Given Data Find = ?
Thicknes of all Walls = 9 inche Excavation for all walls & columns

Thicknes of slab = 6 inche Brick work in foundation


  Brick work in super structure

Length of windiws = 6 ft Analysis of mortor


Breadth of windows = 9 inche Quantity of Cement , Sand , Crush in Slab & Columns

Height of windows = 5 ft Quantity of steel in slab


 

Length of bed rooms Door = 4 ft


Breadth of bed rooms Door = 9 inche

Height of bed rooms Door = 8 ft


 

Length of kitchen Door =3 ft


Breadth of kitchen Door = 9 inche

Height of kitchen Door = 8 ft


 

Length of bath & store Door =2.5 ft


Breadth of bath & store Door = 9 inche

Height of bath & store Door =6 ft


 

Ratio for mortor = 1:2


Ratio fot concrete = 1:2:4

 
Diameter of steel = 0.5 inche (0.04167 ft)

Spacing ofMain & Disttribution bar= 0.5'  

Long Wall and Short Wall Method :


No' No' length/ Breadth/ Height/ Quantity/
s Description of work s ft ft ft cft
             
1 Excavation for walls          
  Long wall 2 34.75 2.5 2.25 390.94
  Short wall 4 12.25 2.5 2.25 275.63
Central wall of Bath &
  store 1 4.25 2.5 2.25 23.91
  Long wall of kitchen 1 14 2.5 2.25 78.75
  Short wall of kitchen 2 8.25 2.5 2.25 92.81
  Excavation for column         0.00
  Column 2 2.5 2.5 2.25 28.13
        Total Excavation = 890.16
2 Concrete in wall footing          
  Long wall 2 34.75 2.5 0.5 86.88
  Short wall 4 12.25 2.5 0.5 61.25
Central wall of Bath &
  store 1 4.25 2.5 0.5 5.31
  Long wall of kitchen 1 14 2.5 0.5 17.50
  Short wall of kitchen 2 8.25 2.5 0.5 20.63
Concrete in column
  footing          
  Column 2 2.5 2.5 0.5 6.25
        Total P.C.C = 197.81
Brick work in wall
3 foundation          
  Long wall          
  1st step of (1.5') 2 33.75 1.5 0.5 50.63
  2nd step of (1.125') 2 33.375 1.125 0.75 56.32
  3rd step of (0.75') 2 33 0.75 0.75 37.13
  Short wall          
  1st step of (1.5') 4 13.25 1.5 0.5 39.75
  2nd step of (1.125') 4 13.625 1.125 0.75 45.98
  3rd step of (0.75') 4 14 0.75 0.75 31.50
Central wall of Bath &
  Store          
  1st step of (1.5') 1 5.25 1.5 0.5 3.94
  2nd step of (1.125') 1 5.625 1.125 0.75 4.75
  3rd step of (0.75') 1 6 0.75 0.75 3.38

  Long wall of kitchen          


  1st step of (1.5') 1 13 1.5 0.5 9.75
  2nd step of (1.125') 1 12.625 1.125 0.75 10.65
  3rd step of (0.75') 1 12.25 0.75 0.75 6.89
  Short wall of kitchen          
  1st step of (1.5') 2 9.25 1.5 0.5 13.88
  2nd step of (1.125') 2 9.625 1.125 0.75 16.24
  3rd step of (0.75') 2 10 0.75 0.75 11.25
      Total brick work in foundation = 342.02
Concrete in column
  foundation          
  1st step of (1.5') 2 1.5 1.5 0.5 2.25
  2nd step of (1.125') 2 1.125 1.125 0.75 1.90
  3rd step of (0.75') 2 0.75 0.75 0.75 0.84
Total concrete in column
      foundation= 4.99
4 Brick work in super structure          
  Long wall 2 33 0.75 11 544.50
  Short wall 4 14 0.75 11 462.00
  Central wall of Bath & store 1 6 0.75 11 49.50
  Long wall of kitchen 1 12.25 0.75 11 101.06
  Short wall of kitchen 2 10 0.75 11 165.00
Total brick work in super
      structure= 1322.06
Deduction of doors &
  windows          
  Bed room doors 2 4 0.75 8 48.00
  Kitchen door 1 3 0.75 8 18.00
  Bath room & store doors 2 2.5 0.75 6 22.50
  Windows 2 6 0.75 5 45.00
      Total deduction = 133.50
      Tatal brick work in super structure= 1188.56
  Concrete in super structure          
  Column 2 0.75 0.75 11 12.38
  Slab 1 33 26.25 0.5 433.13
      Total concrete work = 445.50
5 Steel in slab          

5 Steel in slab          
3.1415(0.0416 x
  Main bars     0.0416)/4  
    67 26.25 0.001363   2.40
3.1415(0.0416 x
  Disttribution bars     0.0416)/4  
    53 33 0.001363   2.38
        Total Steel = 4.78
             

Now We the Second Method of Quantity “ CENTER LINE METHOD “ is given below.
Center Line Method:
No' No' length/ Breadth/ Height/ Quantity/
s Description of work s ft ft ft cft
             
1 Excavation for walls          
  For walls 1 153.25 2.5 2.25 862.03
  For Collumn 2 2.5 2.5 2.25 28.13
      Total Excavation = 890.16
2 Concrete in footing          
  Concret in wall footing 1 153.25 2.5 0.5 191.56
  Concrete in column footing 2 2.5 2.5 0.5 6.25
      Total concrete in footing = 197.81
Brick work in wall
3 foundation          
  For walls          
  1st step of (1.5') 1 157.25 1.5 0.5 117.94
  2nd step of (1.125') 1 158.75 1.125 0.75 133.95
  3rd step of (0.75') 1 160.25 0.75 0.75 90.14
      Total brick work in foundation = 342.02
Concret in column
  foundation          
  1st step of (1.5') 2 1.5 1.5 0.5 2.25
  2nd step of (1.125') 2 1.125 1.125 0.75 1.90
  3rd step of (0.75') 2 0.75 0.75 0.75 0.84
      Total concrete in column foundation= 4.99
Brick work in super
4 structure          
  For walls 1 160.25 0.75 11 1322.06
Deduction of doors &
  windows          
  Bed room doors 2 4 0.75 8 48.00
  Kitchen door 1 3 0.75 8 18.00
  Bath room & store doors 2 2.5 0.75 6 22.50
  Windows 2 6 0.75 5 45.00
      Total deduction = 133.50
      Tatal brick work in super structure= 1188.56
  Concrete in super structure          

  Column 2 0.75 0.75 11 12.38

  Slab 1 33 26.25 0.5 433.13

      Total concrete work = 445.50

5 Steel in slab          
3.1415(0.0416 x
  Main bars     0.0416)/4  

    67 26.25 0.001363   2.40


3.1415(0.0416 x
  Disttribution bars     0.0416)/4  

    53 33 0.001363   2.38

        Total Steel = 4.78


Apex Institute Of Modern Studies Notes By: Khalid rahim & Junaid Khan

Quantity Lecture 19

MULTIPLE FACTOR FOR CEMENT CONCRETE (in cft)


RATIO CEMENT BAGS SAND/cft CRUSH/cft
       
1:1.5:3 0.225 0.42 0.84
1:2:4 0.18 0.44 0.88
1:3:6 0.123 0.462 0.924
1:4:8 0.095 0.474 0.948
1:6:12 0.065 0.486 0.973
       
MULTIPLE FACTOR FOR BRICKS WORK:
RATIO NO's OF BRICKS CEMENT BAGS SAND/cft
       
1:3 13.5 0.06 0.225
1:4 13.5 0.048 0.24
1:5 13.5 0.04 0.25
1:6 13.5 0.0342 0.2571
       
MULTIPLE FACTOR FOR PLASTER:
RATIO CEMENT BAGS SAND/cft  
       
1:1 0.508 0.635  
1:2 0.339 0.847  
1:3 0.254 0.953  
1:4 0.203 1.016  
1:5 0.17 1.058  
1:6 0.145 1.088  
       
Apex Institute Of Modern Studies Notes By: Khalid rahim & Junaid Khan

Quantity Lecture 20

Long Bars are called “ DISTTRIBUTION BARS “ ……………

Short Bars are called “ MAIN BARS “…………….

Length of Slab = 20 ft

Width of Slab = 15 ft

Spacing between the MAIN BARS & DISTRIBUTION BARS = 7 inches

Spacing between the MAIN BARS & DISTRIBUTION BARS = 7/12 =0.58 ft
Calculation and Quantity of Steel are given Below …………
 NUMBER OF MAIN BARS :

Number of main bars = Length of slab / Spacing +1

Number of main bars = 20/0.58+1

Number of main bars = 36 No’s

 NUMBER OF DISTRIBUTION BARS :

Number of distribution bars = Width of slab / Spacing +1

Number of distribution bars = 15/0.58+1

Number of distribution bars = 27 No’s

 LENGTH OF MAIN BARS :

Length of main bars = No’s of main bar X Length of each main bar

Length of main bars = 36 X 15

Length of main bars = 540 ft

 LENGTH OF DISTRIBUTION BARS:

Length of distribution bar = No’s of distribution bar X Length of each Distribution bar

Length of distribution bar = 27 X 20

Length of distribution bar = 540 ft

 TOTAL LENGTH = Main bars + Distribution bars

Total length = 540 + 540

Total length = 1080 ft

 NOW WE USE THE FORMULA

πd 2
Volume of Steel = X total length of bars
4

3.1415(0.041) 2
Volume of Steel = X 1080
4

0.00545
Volume of Steel = X 1080
4

Volume of Steel = 0.00136 X 1080

Volume of Steel = 1.473

Total Weight of Steel = Volume of steel X Unit Weight

Total Weight of Steel = 1.473 X 490

Total Weight of Steel = 721.584 lbs

Total Weight of Steel in Kg = 721.584/2.204

Total Weight of Steel in Kg = 327.397 Kg


Apex Institute Of Modern Studies Notes By: Khalid rahim & Junaid Khan

Quantity Lecture 21

RENT FIXATION OF LAND + BUILDING

Land = 5%

Structure = 6%

Plot Rate = 30,00000 Rs

Construction Rate of sft = 25 X 50 = 1250 sft Rate of per sft is equal to 1200 Rs

Construction Rate = 1200 /sft

Cost of Building = 1250 X 1200 = 1500000 Rs

Rent Fixation of Land = 5/100 X 30,00000

Rent Fixation of Land = 150000 Rs

Rent Fixation of building = 6/100 X 1500000

Rent Fixation of building = 90,000 Rs

Total Rent = Land + Building = 150000 + 90,000

Annual Rent = 240000 Rs

Per Month = 20,000 Rs.