Apex Institute of Modern Studies Notes By: Khalid Rahim & Junaid Khan
Apex Institute of Modern Studies Notes By: Khalid Rahim & Junaid Khan
Quantity Lecture 1
CIVIL:
Civil is the branch of engineering science and related with Designing, Construction, and
maintenances of Building, Dams, Highways, Bridges, Tunnels and other structures.
QUANTITY:
Quantity is an art in which we find the quantum or quantity of different building materials.
labors and its Rates.
There are three things required for Quantity with the help of this data we find the quantity
easily.
SCALE:
1) F.P.S System.
2) M.K.S System.
F.P.S SYSTEM:
It means Foot, Pound, Second system. This system is mostly used in Pakistan.
M.K.S SYSTEM:
It means Meter, Kilogram, Second system. This system is used basically in out Countries.
Quantity Lecture 1
AREA OF RECTANGLE:
AREA = π r 2
AREA = 3.1415 x ¿
AREA = 3.1415 x 36
( 12 )2
AREA = 3.1415 x
4
144 ❑
AREA = 3.1415 x
4
AREA = 3.1415 x 36
AREA = 113.09 sft
Quantity Lecture 2
AREA = π r 2 x ½
π r2
AREA =
2
AREA = 3.1415 ¿ ¿
3.1415(25)
AREA =
2
78.58
AREA =
2
2
πd 1
AREA = x
4 2
π d2
AREA =
8
AREA = 3.1415 ¿ ¿
3.1415(100)
AREA =
8
314.15
AREA =
8
Quantity Lecture 2
AREA =
√3 X ¿
4
AREA =
√3 X ¿
4
AREA = 0.433 X 36
a+b+c
S=
2
8+9+12
S=
2
S = 14.5 ft
AREA = √ 1295.93
Say’s = 36 sft.
aXb
AREA =
2
8X9
AREA =
2
72
AREA =
2
AREA = 36 sft.
Apex Institute Of Modern Studies Notes By : Khalid rahim & Junaid Khan
Quantity Lecture 3
a+b+ c+ d
S=
2
13+9+12+8 42
S= =S=
2 2
S = 21 ft
AREA = √ 9 X 13 X 8 X 12
AREA = √ 11232
AREA OF PANTAGON:
NS 2 180
AREA = X cot
4 N
1
Cot =
tan
N = No’s of sides
S = Length of sides
( 6 ) ( 5 )2 180
AREA = X cot
4 6
VOLUME:
Length = 2 ft
Breadth = 2 ft
Height = 2 ft
Volume = 2 X 2 X 2 = 8 cft
Surface Area = 6 (L x B)
Surface Area = 6 (2 X 2)
Quantity Lecture 4
LENGTH OF WALL = 20 ft
HEIGHT OF WALL = 11 ft
QUANTITY OF WALL = L x B x H
QUANTITY OF WALL = 20 x 0.75 x 11
Quantity Lecture 4
INTERNAL DIAMETER = 6 ft
HEIGHT OF WALL = 15 ft
Apex Institute Of Modern Studies Notes By : Khalid rahim & Junaid Khan
Quantity Lecture 5
LENGTH OF WALL = 18 ft
HEIGHT OF WALL = 11 ft
QUANTITY OF WALL = L x B x H
SUM OF RATIO = 1 + 4 = 5
Quantity Lecture 5
30
DRY QUANTITY OF MORTOR = 148.5 x
100
RATIO OF CEMENT
QUANTITY OF CEMENT = DRY QUANTITY OF MORTOR
∑ OF RATIO x
1
QUANTITY OF CEMENT = x 44.55
5
QUANTITY OF CEMENT
NUMBERS OF BAGS OF CEMENT =
1.25
8.91
NUMBERS OF BAGS OF CEMENT =
1.25
SAY’S = 8 BAGS
RATIO OF SAND
QUANTITY OF SAND = DRY QUANTITY OF MORTOR
∑ OF RATIO x
4
QUANTITY OF SAND = x 44.55
5
Quantity Lecture 6
WALL 1:
LENGTH OF WALL = 15 ft
HEIGHT OF WALL = 10 ft
WALL 2:
HEIGHT OF WALL = 10 ft
RATIO = 1:3
QUANTITY OF WALL 1 = L x B x H
QUANTITY OF WALL 2 = L x B x H
Quantity Lecture 6
SUM OF RATIO = 1 + 3 = 4
30
DRY QUANTITY OF MORTOR = 202.5 x
100
RATIO OF CEMENT
QUANTITY OF CEMENT = DRY QUANTITY OF MORTOR
∑ OF RATIO x
1
QUANTITY OF CEMENT = x 60.75
4
QUANTITY OF CEMENT = 15.18 cft
QUANTITY OF CEMENT
NUMBERS OF BAGS OF CEMENT =
1.25
15.18
NUMBERS OF BAGS OF CEMENT =
1.25
RATIO OF SAND
QUANTITY OF SAND = DRY QUANTITY OF MORTOR
∑ OF RATIO x
3
QUANTITY OF SAND = x 60.75
4
Apex Institute Of Modern Studies Notes By : Khalid rahim & Junaid Khan
Quantity Lecture 7
RADIUS OF WALL = 2 ft
DIAMETER OF WALL = 4 ft
SUM OF RATIO = 1 + 3 = 4
30
DRY QUANTITY OF MORTOR = 48.51 x
100
RATIO OF CEMENT
QUANTITY OF CEMENT = DRY QUANTITY OF MORTOR
∑ OF RATIO x
1
QUANTITY OF CEMENT = x 14.55
4
QUANTITY OF CEMENT
NUMBERS OF BAGS OF CEMENT =
1.25
3.64
NUMBERS OF BAGS OF CEMENT =
1.25
SAY’S = 3 BAGS
RATIO OF SAND
QUANTITY OF SAND = DRY QUANTITY OF MORTOR
∑ OF RATIO x
3
QUANTITY OF SAND = x 14.55
4
Quantity Lecture 8
QUANTITY OF SLAB:
LENGTH OF SLAB = 30 ft
BREADTH OF SLAB = 20 ft
RATIO = 1:2:4
SUM OF RATIO = 7
RATIO OF CEMENT
QUANTITY OF CEMENT =
∑ OF RATIO x DRY QUANTITY OF SLAB
1
QUANTITY OF CEMENT = X 462
7
66
NUMBERS OF CEMENT BAGS =
1.25
SAY’Ss = 53 BAGS
RATIO OF SAND
QUANTITY OF SAND =
∑ OF RATIO x DRY QUANTITY OF SLAB
2
QUANTITY OF SAND = X 462
7
RATIO OF CRUSH
QUANTITY OF SAND =
∑ OF RATIO x DRY QUANTITY OF SLAB
4
QUANTITY OF CRUSH = X 462
7
Apex Institute Of Modern Studies Notes By: Khalid rahim & Junaid Khan
Quantity Lecture 16
SEPARATE (OR) INDIVIDUAL WALL METHOD :
Sr Description of No' Lengt Breadt Heigh Quantity/
No's Work s h h t cft
1 Excavation
Long Walls 2 15.75 3 3.33 314.69
Short Walls 2 7.75 3 3.33 154.85
TOTAL
= 469.53
2 P.C.C
Long Walls 2 15.75 3 1 94.50
Short Walls 2 7.75 3 1 46.50
TOTAL
= 141.00
Brick work in/
3 foundation
Long Walls
1st step 2 14.75 2 0.67 39.53
2nd step 2 14.41 1.67 0.67 32.25
3rd step 2 14.08 1.33 1 37.45
Short Walls
1st step 2 8.75 2 0.67 23.45
2nd step 2 9.08 1.67 0.67 20.32
3rd step 2 9.42 1.33 1 25.06
TOTAL
= 178.06
4 D.P.C
Long Walls 2 13.5 0.75 1 20.25
Short Walls 2 10 0.75 1 15
TOTAL
= 35.25
Bricks work in
5 super/struc
Long Walls 2 13.5 0.75 12 243
Short Walls 2 10 0.75 12 180
TOTAL
= 423
1 Excavation
2 P.C.C
4 D.P.C
Apex Institute Of Modern Studies Notes By: Khalid rahim & Junaid Khan
Quantity Lecture 17
SEPARATE (OR) TNDIVIDUAL WALL
METHOD :
Sr.No' Description of No' Lengt Breadt Heigh Quantity /
s Work s h h t cft
1 Excavation
Long Walls 2 30.5 3 3.33 609.39
Short Walls 3 9.75 3 3.33 292.21
TOTAL
= 901.60
2 P.C.C
Long Walls 2 30.5 3 1 183.00
Short Walls 3 9.75 3 1 87.75
TOTAL
= 270.75
Brick work in
3 foundation
Long Walls
1st step 2 29.5 2 0.67 79.06
2nd step 2 29.17 1.67 0.67 65.28
3rd step 2 28.83 1.33 1 76.69
Short Walls
1st step 3 10.75 2 0.67 43.22
2nd step 3 11.08 1.67 0.67 37.19
3rd step 3 11.42 1.33 1 45.57
TOTAL
= 347.00
4 D.P.C
Long Walls 2 28.25 0.75 42.38
Short Walls 3 12 0.75 27.00
TOTAL
= 69.38
Brick work in super
5 struc
Long Walls 2 28.25 0.75 12 508.50
Short Walls 3 12 0.75 12 324.00
TOTAL
= 832.50
Formula for Excavation = L+(B-T) & Formula for brick worck in foundation = L-(B-T)
1 Excavation
2 P.C.C
4 D.P.C
Apex Institute Of Modern Studies Notes By: Khalid rahim & Junaid Khan
Quantity Lecture 18
APEX INSTITUTE OF MODERN STUDIES NOTE BY: JUNAID KHAN
Given Data Find = ?
Thicknes of all Walls = 9 inche Excavation for all walls & columns
Diameter of steel = 0.5 inche (0.04167 ft)
5 Steel in slab
3.1415(0.0416 x
Main bars 0.0416)/4
67 26.25 0.001363 2.40
3.1415(0.0416 x
Disttribution bars 0.0416)/4
53 33 0.001363 2.38
Total Steel = 4.78
Now We the Second Method of Quantity “ CENTER LINE METHOD “ is given below.
Center Line Method:
No' No' length/ Breadth/ Height/ Quantity/
s Description of work s ft ft ft cft
1 Excavation for walls
For walls 1 153.25 2.5 2.25 862.03
For Collumn 2 2.5 2.5 2.25 28.13
Total Excavation = 890.16
2 Concrete in footing
Concret in wall footing 1 153.25 2.5 0.5 191.56
Concrete in column footing 2 2.5 2.5 0.5 6.25
Total concrete in footing = 197.81
Brick work in wall
3 foundation
For walls
1st step of (1.5') 1 157.25 1.5 0.5 117.94
2nd step of (1.125') 1 158.75 1.125 0.75 133.95
3rd step of (0.75') 1 160.25 0.75 0.75 90.14
Total brick work in foundation = 342.02
Concret in column
foundation
1st step of (1.5') 2 1.5 1.5 0.5 2.25
2nd step of (1.125') 2 1.125 1.125 0.75 1.90
3rd step of (0.75') 2 0.75 0.75 0.75 0.84
Total concrete in column foundation= 4.99
Brick work in super
4 structure
For walls 1 160.25 0.75 11 1322.06
Deduction of doors &
windows
Bed room doors 2 4 0.75 8 48.00
Kitchen door 1 3 0.75 8 18.00
Bath room & store doors 2 2.5 0.75 6 22.50
Windows 2 6 0.75 5 45.00
Total deduction = 133.50
Tatal brick work in super structure= 1188.56
Concrete in super structure
5 Steel in slab
3.1415(0.0416 x
Main bars 0.0416)/4
53 33 0.001363 2.38
Quantity Lecture 19
Quantity Lecture 20
Length of Slab = 20 ft
Width of Slab = 15 ft
Spacing between the MAIN BARS & DISTRIBUTION BARS = 7/12 =0.58 ft
Calculation and Quantity of Steel are given Below …………
NUMBER OF MAIN BARS :
Length of main bars = No’s of main bar X Length of each main bar
Length of distribution bar = No’s of distribution bar X Length of each Distribution bar
πd 2
Volume of Steel = X total length of bars
4
3.1415(0.041) 2
Volume of Steel = X 1080
4
❑
0.00545
Volume of Steel = X 1080
4
Quantity Lecture 21
Land = 5%
Structure = 6%
Construction Rate of sft = 25 X 50 = 1250 sft Rate of per sft is equal to 1200 Rs