Human Resource Management

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

MAY 10, 2022

BARANGAY SAINT PETER PEDESTRIAN


ENVIRONMENT IMPROVEMENT PROJECT

HUMAN
RESOURCE
MANAGEMENT
PLAN

1. INTRODUCTION
1.1 PURPOSE OF THE QUALITY MANAGEMENT PLAN
The Barangay Saint Peter Pedestrian Environment Improvement Project Quality
Management Plan (QMP) contains the necessary information required to e ectively
manage project quality from project planning to completion. It de ines a project’s quality
policies, procedures, criteria, and output. The Quality Management Plan is created during
the Planning Phase of the project. Its intended audience of the QMP is the project
manager, project members and engineers, and project stakeholders (see stakeholder
management plan) whose support is needed to carry out and complete the project. Using
the inputs of the stated audiences, proper steps can be done in planning, implementing,
checking, and acting to improve project quality standards and the project outputs.

f
ff

2. AUDIENCE AND ROLES

PERSONNEL TASK/ROLE

Construction Engineer Assess the usability and construction quality of the newly repaired or
constructed pedestrian structures. These include but are not limited to
the structural capabilities/durability and the inishing works applied.

Project Heads Review and make decisions in response to the assessments provided by
the engineers and the stakeholders.

Stakeholders Assess the usability and visual appeal of the newly completed, repaired
and improved pedestrian structures. Their feedback on the output may
also determine the viability of this project and the possibility of
application in other areas
f

3. QUALITY ASSESSMENT PLAN


This section is where the quality standards and expectations are identi ied and the
stakeholder and project goals are de ined. These shall be done by providing success
factors and metrics for which to measure the level of success or acceptance the project
has achieved.

3.1 Engineer Assessment


They shall be done by means of a report detailing the output of the project on each
road upon each of their completions. This is done in order to make changes in early on if
there is an issue present in any of the pedestrian structures completed. This will be using
the criteria stated below which will aid in identifying the level of quality the completed
and improved structures have.


f
f

Aspect Assessed Criteria Acceptance CLARIFICATIONS

Sidewalk Grading: 0-10 Minimum: 8 All structural issues


Structural 0 - Bad quality with poor The project aims to reach at least a and construction
Quality structure output with a satisfactory quality level for the problems shall be
good amount of issues sidewalks provided upon the
3 - Below average (may assessment of the
describe no clear engineer
improvement to damaged
structures)
5 - Satisfactory output
capable of lasting
8 - Good quality with clear
improvement
10 - Great Quality with no
issues

Sidewalk Grading: 0-10 Minimum: 7 Paint quality would


Painting Works 0 - Poor painting done with The project aims to reach a highly not be part
Quality a good amount of issues satisfactory quality level for the assessed but the
5 - Satisfactory output assistive structures like curb ramps application quality
10 - Great Quality output along with the usability of the and method shall
currently improved structures

Pedestrian Grading: 0-10 Minimum: 9 Paint quality would


Crossing Quality 0 - Poor painting done with The project aims to provide a good not be part
a good amount of issues quality crossing which aims to assessed but the
5 - Satisfactory output lessen accident by making them application quality
10 - Great Quality output highly visible and make these and method shall
structures safer for use.

3.2 Stakeholder Criteria


They shall be done by means of a interview or survey detailing the opinions of the
stakeholders on the outputs of project and shall be done with the help of the selected
stakeholders (some residents and pedestrians and the barangay tanod). This is done in
order to assess the quality and make changes if there are unfavourable aspects that are
possible to improve. This will be using the criteria stated below which will aid in
identifying the level of quality the completed and improved structures have.

Aspect Criteria Acceptance CLARIFICATIONS


Assessed

Sidewalk Quality Grading: 0-10 Minimum: 7 This shall be a visual


0 - Bad quality with poor structure The project aims to appeal and assessment.
and painting work reach at least a The stakeholders are
3 - Below average (may describe no satisfactory quality urges to write down or
clear improvement to damaged level for the state any issue they ind
structures) sidewalks
5 - Satisfactory output
8 - Good quality with clear
improvement
10 - Great Quality with no issues

Accessibility and Grading: 0-10 Minimum: 8 This shall be an


Usability 0 - Bad quality with poor assistive The project aims to assessment on how
structures and painting works and reach a highly easy and accessible the
di icult to use satisfactory quality pedestrian environment
3 - Below average (may describe no level for the assistive is as a whole is upon the
clear improvement). Somewhat structures like curb projects completion.
di icult to use for PWDs but doable. ramps along with The stakeholders are
5 - Satisfactory output the usability of the urges to write down or
8 - Good quality with easy currently improved state any issue they ind
accessibility and usage structures
10 - Great Quality with no issues

Pedestrian Grading: 0-10 Minimum: 8 This shall be a visual


Crossing Quality 0 - Bad quality with poor and very The project aims to appeal and assessment.
faded painting work (no provide a good The stakeholders are
improvement) quality crossing urges to write down or
3 - Below average, somewhat usable which aims to lessen state any issue they ind
5 - Satisfactory output accident by making
8 - Good quality with clear them highly visible
improvement and make these
10 - Great Quality with clear and very structures safer for
visible painting works use.

Pedestrian
Environment
Safety

3.3 QUALITY ASSURANCE AND CONTROL


ff
ff

f
f
f

In order to assess if that the resulting structure meets the quality required in the
previously stated criteria, the stakeholders shall be asked to ill out a form that would
allow the assessment of the newly build portions of the road. Upon the completion of
each road sidewalk, this form shall be given to the residents residing on said area
connected to the said road. Additionally, the tanod shall be given these forms so that he/
she may assess the work done as well. These shall be complied into a reportand analyzed
for any signi icant problems found.

The engineers shall assure the quality of the structures by performing routine site
visits and check ups each week. These shall be for the purpose of assessing the progress,
with each new completed section check for structural errors or other problems. Their
inding will be compiled in a report that will be used to assess any possible problem and
provide any needed actions if required.
Another purpose for the site visits by the engineers are to direct the construction
workers to any possible changes decided by the project head to improve the quality of
the resulting structure. Because of their weekly site visits, this would enable the changes
to be applied very quickly. Additionally as seen in the cost management plan, a maximum
budget was allotted for the project to cover various possible problems and one would be
a lack in quality. The allowance in the budget would allow improvements to be made in
the project is any were to be suggested and subsequently approved by the project head.

3.3.1. MATERIAL QUALITY ASSURANCE

Quality of the materials such as the concrete and aggregates will be checked by
the engineer and project head by means of requesting the speci ications and assessing if
it is appropriate for use. Aggregates may be sent to labs for speci ic testing. The cement
and subsequent concrete mixes may also be tested using the concrete cylinder test. To
ensure the quality of the materials to be used, these will not be delivered in one but in
batches which is found in the procurement management plan.

f



f

f
f
f

The tools bought shall be be check and assured of quality based on testing (done
by the engineer and/or project head) right after they are obtained and by checking the
speci ications. Aside from these, speci ic lab based testing will not be done.

f
f