Download as pdf or txt
Download as pdf or txt
You are on page 1of 92

DEPARTMENT OF ELECTRICAL AND COMPUTER ENGINEERING

STUDY OF INSULATION CO-ORDINATION

IN ELECTRIC POWER DISTRIBUTION SYSTEMS

Joshua T. Hurley

12203176

A Thesis Submitted For the Degree of

Bachelor of Engineering in Electrical Engineering


DEPARTMENT OF ELECTRICAL AND COMPUTER ENGINEERING

TITLE:

Study of Insulation Co-ordination in Electric Power Distribution Systems

DEPARTMENT OF ELECTRICAL AND COMPUTER ENGINEERING

AUTHOR

FAMILY NAME: HURLEY

GIVEN NAME: JOSHUA

DATE: 4 November, 2005 SUPERVISOR: Professor Syed M. Islam

DEGREE: Bachelor of Engineering OPTION: Electrical

ABSTRACT

Insulation co-ordination studies should be considered for the design of all medium to extra high voltage electric

power distribution systems. The protection against overvoltage transients is of vital importance for the utility as well

as the customer. This paper focuses on the study of a typical 132/22kV zone substation for a Western Australian

electrical utility.

INDEXING TERMS

Insulation Co-ordination; Lightning Protection: Risk; Substation; Matlab; Simulink;

GOOD AVERAGE POOR

TECHNICAL WORK

REPORT PRESENTATION

EXAMINER CO-EXAMINER
Joshua Hurley
23 Sandover Drive
Karrinyup WA 6018

3 November, 2005

Professor Syed M. Islam


Curtin University of Technology
Department of Electrical and Computer Engineering
Kent Street
Bentley WA 6102

Dear Professor Islam,

I offer this thesis entitled "Study of Insulation Co-ordination in Electric Power

Distribution Systems" as partially satisfying the requirements for completion of the

degree, Bachelor of Electrical Engineering.

Furthermore, I state that this thesis is entirely my own work outside of where

acknowledgement is given and that it has been submitted in accordance with the

requirements of the Department of Electrical and Computer Engineering.

Yours Sincerely,

Joshua Hurley
12203176
SYNOPSIS

This report covers the insulation co-ordination study of a typical 132/22kV zone

substation for a Western Australian electrical utility. The focus is on the various

possible lightning strikes and the associated risk of striking a substation. New

configurations to the system are also investigated such that an economic benefit

and/or increased protection may be realised. This should be read in conjunction with

the thesis by Browne (2005) who co-developed the simulation tool for the study with

the author.

i
ACKNOWLEDGEMENTS

The author wishes to thank the following people –

• David Browne for working diligently with the author for two whole semesters

over all parts of this report. Both he and the author worked together in

creating the model and producing the subsequent results, however have split

up the thesis as required. All work here should also be attributed to him.

• Syed Islam for the constant supervision and advice throughout the semester.

Also, for enhancing the quality of this thesis by criticising the draft.

• Terence Law, Tony Murphy and Tom Pearcy of Western Power for the

supervision and regular meetings that allowed such progress in the report.

• Stuart Romero for critically reading the thesis as well as providing some very

useful advice for the presentation.

• Blake Hurley for critically reading the English within the thesis and

contributing to the quality of the writing.

• John-Ross Torre for critically reading the thesis and providing feedback.

ii
INDEX

1.0 INTRODUCTION 1

1.1 Insulation Co-ordination Study 1

1.2 Simulation Results 3

1.3 Structure of Report 4

2.0 APPROACHES TO INSULATION CO-ORDINATION 5

2.1 Definition 5

2.2 Reasons for Protection 5

2.3 Basic Lightning Impulse Insulation Level 6

2.4 Causes of Overvoltages 6

2.5 Protection of Equipment 7

2.5.1 Measures for Protecting Equipment 7

2.5.2 BIL Level 7

2.5.3 Shielding 8

2.5.4 Protective Devices 8

2.6 The Lightning Surge 9

2.7 Lightning Events 11

2.7.1 Types of Events 11

2.7.2 Shielding Failure 11

2.7.3 Backflash 11

2.7.4 Direct Strike 11

2.8 Brief History 12

2.9 Current Approaches 12

iii
3.0 MODEL-BASED DESIGN 14

3.1 Introduction 14

3.2 Simulation Software 14

3.3 Substation Layout 15

3.4 Element Representation 17

3.4.1 Modelling of Power System Elements 17

3.4.2 Transmission and Distribution Lines 17

3.4.3 Cables 18

3.4.4 Busbars 18

3.4.5 Transformers – Power, Current and Voltage 18

3.4.6 Switchgear 19

3.4.7 Surge Arresters 19

3.5 Basic Development of the Model 19

3.6 Model Layout 20

3.6.1 132kV Side 20

3.6.2 22kV Side 20

3.7 Current Surge 25

3.8 Corona Effects 26

4.0 DATA ACQUISITION 27

4.1 Introduction 27

4.2 Ratings of Substation Elements 27

4.3 All Equipment 27

4.3.1 Transmission Line and Towers 27

4.3.2 Distribution Line and Towers 29

4.3.3 Cables 30

iv
4.3.4 Busbars 31

4.3.5 Transformers – Power, Current and Voltage 31

4.3.6 Switchgear 32

4.3.7 Surge Arresters 32

4.3.8 Distribution Line Load 32

4.3.9 Capacitor Banks 33

5.0 ASSESSING RISK 34

5.1 Probability 34

5.2 Keraunic Level 34

5.3 Lightning Incidence 35

5.4 Line Orientation 36

5.5 Distribution of lightning 37

5.6 Lightning Induced Currents 38

5.7 Risk of Event 39

6.0 INSULATION CO-ORDINATION TESTING 40

6.1 Simulating the Substation 40

6.2 The 132kV Side 41

6.2.1 Possible Events 41

6.2.2 Worst-case Scenario 41

6.2.3 Shielding Failure 43

6.2.4 Backflash 48

6.2.5 Direct Strike 49

6.2.6 Summary of Protection 50

6.3 The 22kV Side 51

6.3.1 Different Events 51

v
6.3.2 Worst-case Scenario 51

6.3.3 Direct Strike 53

6.3.4 Summary of Protection 54

6.4 Current Level of Protection for the Substation 54

7.0 SENSITIVITY ANALYSIS 55

7.1 Introduction 55

7.2 Economic Considerations 55

7.3 Testing Method 56

7.4 BIL Ratings 56

7.5 Surge Arrester 57

7.6 Earth Wire 60

7.7 Surge Arrester Position 61

7.8 Other Possibilities 63

7.8.1 Minor Enhancements 63

7.8.2 Orientation of the line 63

7.8.3 Change of conductor 64

8.0 CONCLUSION 65

9.0 REFERENCES 67

10.0 APPENDIX A – PROJECT SCHEDULE 70

11.0 APPENDIX B – INSULATION CO-ORDINATION TESTING RESULTS 71

B1 Backflash Event to 132kV Side 71

B2 Direct Strike Event to 132kV Side 72

B3 Direct Strike Event to 22kV Side 74

vi
12.0 APPENDIX C – SENSITIVITY ANALYSIS TESTING RESULTS 75

C1 Modification of Surge Arresters 75

C2 Modification of Earth Wire Distance 76

C2.1 Distance of 500 metres 76

C2.2 No Earth Wire 78

vii
LIST OF FIGURES

Figure 2.1: Standard 1.2/50 Lightning Waveshape 10

Figure 3.1: Single line diagram of the 132/22kV zone substation 16

Figure 3.2: Simulink model - Incoming transmission line 21

Figure 3.3: Simulink model - 132kV substation layout 22

Figure 3.4: Simulink model - 22kV side of substation 23

Figure 3.5: Simulink model - 22kV switchboard room 24

Figure 4.1: Orientation of transmission lines 28

Figure 4.2: Typical orientation of distribution lines 29

Figure 5.1: Keraunic levels throughout Australia 35

Figure 5.2: Diagrammatic view of the geometric model 37

Figure 6.1: 132kV configuration for simulation 42

Figure 6.2: Surge arrester 1 performance under shielding failure 44

Figure 6.3: Surge arrester 2 performance under shielding failure 45

Figure 6.4: Transformer performance under shielding failure 46

Figure 6.5: 22kV configuration used for simulation 52

Figure 7.1: Variation of the position of the surge arrester 62

Figure 10.1: Gantt chart of project schedule 70

Figure 11.1: Backflash to 132kV side - Surge Arrester 1 71

Figure 11.2: Backflash to 132kV side - Surge Arrester 2 71

Figure 11.3: Backflash to 132kV side – Power Transformer 72

Figure 11.4: Direct Strike to 132kV side - Surge Arrester 1 72

Figure 11.5: Direct Strike to 132kV side - Surge Arrester 2 73

Figure 11.6: Direct Strike to 132kV side – Power Transformer 73

Figure 11.7: Direct Strike to 22kV side – Power Transformer 74

viii
Figure 12.1: Modified Surge Arrester Test - Surge Arrester 1 75

Figure 12.2: Modified Surge Arrester Test - Surge Arrester 2 75

Figure 12.3: Modified Surge Arrester Test – Power Transformer 76

Figure 12.4: Earth wire of 500m – Surge Arrester 1 76

Figure 12.5: Earth wire of 500m – Surge Arrester 2 77

Figure 12.6: Earth wire of 500m – Power Transformer 77

Figure 12.7: No earth wire – Surge Arrester 1 78

Figure 12.8: No earth wire – Surge Arrester 2 78

Figure 12.9: No earth wire – Power Transformer 79

ix
LIST OF TABLES

Table 4.1: BIL ratings of substation equipment......................................................... 27

Table 4.2: Transmission line properties ..................................................................... 27

Table 4.3: Sequence impedance parameters for transmission line ............................ 28

Table 4.4: Distribution line properties ....................................................................... 29

Table 4.5: Sequence impedance parameters for distribution line .............................. 30

Table 4.6: 22kV cable data (Cu XLPE 500mm2)....................................................... 30

Table 4.7: Capacitance values for the 132kV side..................................................... 31

Table 4.8: Capacitance values for the 22kV side....................................................... 31

Table 4.9: Surge Arrester characteristics ................................................................... 32

Table 6.1: Summary of simulation for shielding failure to 132kV side..................... 47

Table 6.2: Summary of simulation for backflash event to 132kV side...................... 48

Table 6.3: Summary of simulation for direct strike to 132kV side............................ 49

Table 6.4: Summary of simulations to 132kV side.................................................... 50

Table 6.5: Summary of simulation for direct strike to 22kV side.............................. 53

Table 7.1: Costs of surge arresters ............................................................................. 55

Table 7.2: Comparison of different BIL ratings......................................................... 57

Table 7.3: Minimum MCOV ratings for Distribution Systems ................................. 58

Table 7.4: Comparison of different surge arresters.................................................... 59

Table 7.5: Effects of different earth wire lengths ...................................................... 60

Table 7.6: Safety margins for different positions of the surge arrester...................... 63

x
1.0 INTRODUCTION

1.1 Insulation Co-ordination Study

Insulation co-ordination focuses on the fine line between protection of a power

system against lightning and switching surges, and the cost of providing the

protection. There are many variables that have to be taken into account for a detailed

study including the elements within the substation, the cost of these elements, the

risk the utility is willing to take into account, and so on. As such the study requires a

versatile tool that will allow the elements to be changed and the risk to be quantified

based on the probability of the surge events occurring.

This project was part of a larger joint project between the author and another Curtin

University undergraduate student, David Browne. It was partaken in conjunction

with a Western Australian electrical utility and Curtin University. The entire scope

involves the creation of a tool to conduct a detailed insulation co-ordination study to

a typical 132/22kV substation.

While both students worked on all aspects of the study, Browne (2005) focuses on

the detailed development and validation of the model, whereas this thesis focuses on

the application of the model and the actual insulation co-ordination study. As such, to

appreciate this paper to the full extent, Browne’s thesis should also be read in

conjunction although basic model development is included in this report.

The utility commissioned this study because it uses the recommendations of

manufacturers and has not made as detailed a study as the one encountered in this

1
thesis. Because this study is part of an undergraduate project, the utility saves time

and resources in conducting the research and also greater credibility can be given to

the results because of the backing of a university professor as supervisor. The link

between industry and research institute clearly benefits the utility, Curtin University

and the students involved.

Matlab Simulink with the SimPowerSystems package was used for the development

of the model because the utility has a license for this software. There are many other

examples of software that could be used so this is primarily an economic

consideration. The package allows the layout of the substation to be easily

implemented with the correct power system elements (included in the software).

Modules could also be produced for ease of use, such as automatically working out

the associated risk.

The model that was produced had to correlate with currently available data however

limited it was for strikes against substations. The models that were produced agreed

with that data and this was validated by Browne (2005).

Simulations were based on a standard 132kV/22kV zone substation under both

current and voltage surges where the level of acceptable risk was determined.

Quantifying the risks was possible due to the probabilities associated with the

orientation of the lines and the keraunic level (number of thunderstrike days in a

year).

2
1.2 Simulation Results

After validation by Browne (2005) the models were used to simulate different

lightning events – shielding failure, backflash and direct strikes. These events were

simulated on a transmission line leading into the 132kV side of the substation and

also along the distribution line outgoing from the 22kV switchyard.

Under shielding the worst-case scenarios of lightning strikes hitting the substation

can be found by using a geometric model of the line. In the case of the unshielded

tests the strikes did not have an upper limit so the magnitude was based on a function

of acceptable risk. In all these scenarios flashovers would almost definitely occur as

they exceed the critical flashover levels to a significant extent, however there is still

the possibility of the strike occurring and propagating through the substation.

Worst-case scenarios for the different lightning events allowed the protection of the

substation to be measured. These risks were quantified with the probability of such

events occurring.

The current configuration of the system was deemed to be protected with a good

safety margin of 25% for a worst-case scenario.

Sensitivity analysis was conducted on some of the protective devices to observe the

possible reconfiguration of the system for economic savings and also an increase in

protection. Results show that changes could be made to the basic insulation level, the

surge arrester types or position, and also the length of the earth wire.

3
1.3 Structure of Report

Current and historical approaches to insulation co-ordination are included in Chapter

2 as a formal introduction to the topic. Chapter 3 focuses on the basic development

of the simulation model and the appropriate circuit representations.

Chapters 4 and 5 consider the necessary data that must be inputted into the

simulation tool. Chapter 4 considers the acquisition of data based on the

requirements from Chapter 3. Chapter 5 includes location-based data and an

appreciation of the risk involved in the simulations.

The actual insulation co-ordination study is made in Chapter 6 and details the

important results for the zone substations that the utility uses in the network. The

various strikes are considered to both the 132kV and 22kV sides of the substation.

Chapter 7 investigates possible changes to the current configuration, in particular

different surge arrester ratings, changes to the distance surge arresters are from the

transformer on the 132kV side and the effects of an earth wire. These are dealt with

under the worst cases built up from the previous three chapters.

The conclusion of the report is in Chapter 8 with a summary of all of the

investigations and the usefulness of a detailed study as reported here. Also, further

recommendations are made for future investigations.

4
2.0 APPROACHES TO INSULATION CO-ORDINATION

2.1 Definition

The Australian Standards refers to insulation co-ordination as,

“The selection of the dielectric strength of equipment in relation to the

voltages which can appear on the system for which the equipment is

intended and taking into account the service environment and the

characteristics of the available protective devices.” [AS 1824.1]

The key is to attain a balance between the level of protection and the associated costs

involved.

2.2 Reasons for Protection

Power systems need to be protected for various reasons including,

1. Prevention or minimisation of plant damage;

2. Avoiding loss of revenue for both utility and industry;

3. And maintaining system stability.

Overvoltages can seriously damage various elements within power systems,

especially sensitive equipment such as transformers. If for example a transformer in a

substation is damaged then it is very costly for a utility to replace, and as a result

may cause system down time that will dissatisfy the customer-base due to the loss of

revenue to industry and other business. In an increasingly deregulated industry, both

economics and the customer-base must be considered to keep a competitive edge

within the power industry.

5
2.3 Basic Lightning Impulse Insulation Level

All equipment within a substation is rated with a Basic Lighting Impulse Insulation

Level (BIL). The BIL is defined as the electrical strength of insulation expressed in

terms of the rest value of the standard lightning impulse. In other words the BIL

defines a deterministic maximum voltage level based on a low probability of failure

for a piece of equipment.

Basic impulse levels are measured either statistically or conventionally. Statistical

values define a 10% probability of failure at the rated BIL. Conventional BIL is the

crest value of the lightning that BIL is measured so that the equipment does not

exhibit disruptive discharge.

2.4 Causes of Overvoltages

Insulation co-ordination considers overvoltages caused by lightning and switching

surges. Faults such as phase-phase, phase-earth, etc. as well as other phenomena can

also cause overvoltages but these factors are usually dealt with in power system

protection planning.

Lightning surges, as the name suggests are caused by lightning that hits a

transmission line, distribution line or other element within the power system.

Switching surges are caused by lines switching, for example capacitor banks or loads

turning on or off which generates an impulse current.

6
Switching surges were not to be considered in the study. This was because Australian

Standards 1824.1 specify that switching surges do not need to be examined for

systems less than or equal to 245kV. The reason is that the inductances within the

lines for a system below 245kV generally keeps voltages below any critical values,

and if not, then lower than that experienced by lightning.

The problem of overvoltages is greatly compounded due to the differing impedances

experienced throughout the electrical path of the power system. Steady-state voltages

are disrupted due to the differences in impedance; voltages can be magnified up to

twice the original magnitude over each section of the line.

The overvoltages exhibited on the terminals of any piece of equipment should not be

greater than the BIL otherwise the system is not insulation co-ordinated.

2.5 Protection of Equipment

2.5.1 Measures for Protecting Equipment

Equipment can be protected in numerous fashions. The main options include

changing BIL levels, shielding and surge arresters and are discussed within this

section.

2.5.2 BIL Level

The basic impulse level of equipment can be increased above any possible (or

probable) overvoltage that may be caused by a surge. This option is the most

expensive of all the options and is still at risk of failure if a particularly high

7
magnitude surge hits the network. It is best to take other precautions which are both

more economical and safer. Utilities often adopt a reduced BIL which is a BIL lower

than the maximum recommended by standards.

2.5.3 Shielding

To minimise the possibility of a lightning strike and the generated overvoltages,

shielding is most often employed to protect a system from these problems. For

example, earth wires are strung over substations and transmission lines to absorb a

lightning strike rather than any phase conductors that will transmit the surge to the

elements that require protection.

2.5.4 Protective Devices

Even the best shielding schemes can fail – a lightning strike can still reach a phase

conductor (albeit with a lower probability) and cause serious damage. Protective

devices are used for this purpose. Such devices limit voltages within the system.

Devices such as circuit breakers are generally used for clearing faults. They utilise

other current and/or voltage transformers and relays as well as safety margins and

operating times. Surges are very fast compared to the clearance time of circuit

breakers and will cause damage before a circuit breaker could open.

Surges require other methods to keep overvoltages below the basic impulse levels of

equipment. Surge arresters (also known as surge diverters, surge suppressor, and

lightning or line arresters) have the ability to limit voltages within a network.

8
Surge arresters are placed in parallel and within close proximity of equipment to

protect it. Generally surge diverters are made of metal oxide material (such as ZnO)

which have a nonlinear V-I characteristic, which is a property of the boundary layers

between the crystals. They usually have a rated voltage in which the impedance

within them will drop sharply when voltages at the rated voltage are experienced so

that current is diverted through them keeping the voltage around the crest value.

Surge suppressors have an energy rating which should not be exceeded otherwise a

fault could occur, so this value also should be considered when coordinating the

insulation.

2.6 The Lightning Surge

Lightning has been a curiosity to mankind but has only been studied in depth since

the advent of power distribution systems (last 100 years) due to the faults that can be

caused and the advances in technology that can record a lightning surge

(oscilloscopes and such). Many studies have been undertaken on lightning and a

general standard wave shape is accepted as the best representation for a surge which

is listed in numerous standards in the international arena including AS 1824.1 and

IEEE Standard 1313.1. This representation generally involves the shape of a double

exponential however a more accurate mathematic model of the lightning stroke has

been used in this study by Cvetić, Heidler and Stanić (1999).

9
The main properties of a lighting surge include:

1. Maximum current – the peak crest current cause by the voltage impulse.

2. Front time (tf) – the time difference when the current is rising between 30%

and 90% of the crest value.

3. Tail time (tT) – the time the impulse falls to 50% of the crest value.

Generally surges are denoted as a tf/tT impulse such as the standard 1.2µs/50µs or

8µs/20µs used in different tests.

In Australia, insulation co-ordination is based on AS 1824.1 which is in turn based

on the international electrical standard, IEC 71-1. These standards specify the tests

that should be made on equipment including the properties of the surges that could

be exposed to the system. As specified earlier, switching surges are not considered

within this report. Lightning surges are to be tested with 1.2µs/50µs waveshape. This

standard lightning waveshape appears in Figure 2.1.

Figure 2.1: Standard 1.2/50 Lightning Waveshape

10
2.7 Lightning Events

2.7.1 Types of Events

Lightning surges can cause a number of different events to take place including

shielding failures, backflashovers and direct strikes. Each of these possibilities

should be simulated as each could produce a worst-case scenario.

Of course, multiple events of the following can occur as well as flashovers to other

surfaces or lines and also multiple strikes to the lines.

2.7.2 Shielding Failure

Shielding failures occur when a lightning flash misses an earth wire (the shield) and

hits the phase conductor instead. There is a theoretical maximum current that will be

caused by this particular event.

2.7.3 Backflash

Backflashovers occur when lightning hits a shield wire and has a high enough

magnitude that it breaks down over the insulation to a phase conductor. This

particular event also has a theoretical maximum.

2.7.4 Direct Strike

Without shielding, phase conductors are not protected and lightning will terminate

directly to cause this event. There is no maximum threshold except flashovers will

almost definitely occur at high currents.

11
2.8 Brief History

Theory of elements within the substation has been built from the ground up from

reflections in transmission lines, to the representation of a transformer by a shunt

capacitor. These representations are modelled by equations and were originally very

tedious to work with because results were produced by hand.

The complexities of the networks that need to be examined require a powerful tool to

be studied. Software packages such as Matlab Simulink allow a symbolic view of the

network to be studied and with ease that would have been unimaginable to the early

pioneers of the work.

Computer simulations of electrical networks allow the equipment to be setup and

tested with a theoretical surge. Of course an equation is never truly representative of

either the surge or the apparatus within a substation. However, the representations

used are fairly accurate and are necessary to conduct the study.

The simulations also allow for the changing of the substation configuration with ease

by changing the parameters of particular equipment or even changing the layout

through the pictorial view.

2.9 Current Approaches

The utility does not currently undertake insulation co-ordination studies to its

substations. Some minor studies have been made but none as detailed as the model

that was developed for this project.

12
The utility uses both manufacturer’s recommendations and Australian Standards to

build the network. While these options generally produce a very acceptable level of

protection, the networks can be overprotected. The insulation co-ordination study in

this report allows the utility to have economic gains while keeping protection to a

suitable level.

Many other utilities such as ARTC (2005) or Merlin Gerin (Metz-Noblat 1994)

throughout the world use simulations as in this report. Metz-Noblat (1994) includes a

study of the associated risk similar to in this paper. Of course, some utilities without

the expertise sometimes only rely on previous experience and the recommendations

of manufacturers.

All of the options are acceptable but a simulation of a network can give the most

detailed answer for a utility and a greater appreciation of the risk involved, as well as

the sacrifices that can be made.

13
3.0 MODEL-BASED DESIGN

3.1 Introduction

A basic explanation of the SimPowerSystems model produced by Browne (2005) and

the author is detailed within this chapter. All of the major components are detailed

from choice of software, to the actual layout of the substation, to the simulated

version of the substation. A copy of the model is available in Browne (2005).

The thesis by Browne (2005) should be read if the explanations within this chapter

are not sufficient for the reader. The thesis gives all of the components in greater

detail, as well as expanded concepts and programming that were introduced into the

model for ease of use while simulating.

3.2 Simulation Software

There are many different forms of software that are used for power system

simulation such as the SimPowerSystems pack for use with Matlab Simulink,

PSCAD, HYPERSIM, and EMTP. All of these programs allow for the study of

transients using a graphical representation of the power system.

Matlab Simulink with SimPowerSystems was chosen for this project because the

utility already had the software and the software is understood by the employees. The

choice of software also allows a proper design-based project due to the programming

and flexibility involved.

14
This package has the functionality to allow an accurate representation of all the

models used within the substation and thus a new product was not considered. The

added functionality of this software is based on Matlab’s mathematical capability for

differential equations, feedback loops and other tools required for the study of

transients in electrical systems.

3.3 Substation Layout

This substation considered in the modelling will be based on the standard design for

new substations of this size and is therefore the model that is used within this design.

Whereas it is not representative of all 132/22kV substations built in the past, it is a

very useful approximation. The model can be easily modified if a more accurate

simulation of a past design is required.

The actual layout is defined by a single line diagram and appears in Figure 3.1. The

diagram clearly shows the location of surge arresters, current and voltage

transformers, busbars, bus-ties, capacitor banks, transmission and distribution line

connections and of course the power transformers which are the focus of the study.

The design is clearly a two transformer system, with the high voltage side involving

two incoming transmission lines. The low voltage side involves two 22kV indoor

switchboard arrangements with eight outgoing distribution lines and four capacitor

banks each extending from the switchgears.

15
Figure 3.1: Single line diagram of the 132/22kV zone substation

16
3.4 Element Representation

3.4.1 Modelling of Power System Elements

All of the elements that are shown in Section 3.3 are accurately modelled for the

simulation. Due to the high frequency surge, elements are represented differently to

the usual low frequency model. Discussions of the different models are included

within this section.

3.4.2 Transmission and Distribution Lines

Both transmission lines and distribution lines are generally modelled using a Pi-

network or other approximation under normal power system studies. These models

however are not accurate enough to represent the voltages on a line when subjected

to a high frequency impulse current such as a lightning surge. This is because this

type of model only uses two-sections.

A distributed parameter model accurately models the surge impedance and

propagation velocity of the surge. This model allows for reflections to be considered

in the model and thus an accurate account of the voltage magnifications occurring

along the lines.

There is a component within SimPowerSystems that models distributed parameters

using lumped losses based on Bergeron’s model (Mathworks 2004) which is also

available in a similar transient program specifically used for insulation co-ordination

and other related studies, EMTP.

17
3.4.3 Cables

The cables are modelled the same as the transmission and distribution lines, that is

with a distributed parameter. Cables are basically the same as for the lines but have a

lower inductance and higher capacitance as they are closer together. The electric

field is also confined due to shielding.

Clearly, the biggest difference from overhead lines is that cables are not exposed to

air as they are laid underground meaning that lightning will not hit them.

3.4.4 Busbars

The HV and LV busbars were modelled using surge impedance due to the limited

data available from the utility. Basically, the impedance was split up equally through

the busbar portions using resistors. This form of representation is adequate because it

represents the most recent data available from the utility.

3.4.5 Transformers – Power, Current and Voltage

Transformers can be approximated using a shunt capacitance due to the high

frequencies exhibited by the surge. At high frequencies, the stray capacitances

exhibited by the transformer drop to very low impedance to ground and the

capacitance is therefore the dominant feature. Also, all currents are directional

because currents cannot penetrate due to the inductance in the windings at the high

frequencies. Ideally, the capacitance is measured at high frequencies as the

capacitance properties of materials do not follow the same relationship as at lower

frequencies.

18
3.4.6 Switchgear

Switchgear data was very limited with a single capacitance for phase to ground given.

Using this data assumptions were made so that the measured capacitance could be

distributed among the eight current transformers and two voltage transformers.

The distribution of the capacitances was done such that the voltage transformer

capacitance was six times greater than the capacitance of the current transformer.

This is valid when comparing the data in Section 4.3.5.

3.4.7 Surge Arresters

SimPowerSystems includes a default surge arrester model. This model utilises the

rated currents and voltages from surge arrester data. The high frequency of the surge

does not affect the operation of the arresters significantly as they are designed for

limiting voltages caused by such events.

3.5 Basic Development of the Model

The single line diagram is easily translated into a three-phase circuit including all of

the elements described earlier in the previous section. Three phases were included

where all of the single lines exist and equipment was similarly replaced with the

model representations.

The model must be split into two because no data exists on capacitance between the

HV and LV sides of the 132/22kV transformer. If the data for the inter-capacitances

19
existed, the model could be built so that the propagation of the surge would be

modelled through the whole substation as per Greenwood (1991).

Generally, in industry only one side of a substation is modelled at a time. In fact, no

examples were found that had a fully propagating network from HV to LV sides and

vice versa which validates the choice made here. This representation is possible due

to the propagating surge only significantly affecting the first side that is hit by the

surge, the other side is exposed but most of the current is lost through the low

impedance of the stray capacitance.

3.6 Model Layout

3.6.1 132kV Side

The 132kV side with incoming lines and the substation component appear in Figure

3.2 and Figure 3.3 respectively. The components are clearly marked in each case.

3.6.2 22kV Side

One half of the 22kV side appears in Figure 3.4, the actual model does not fit well on

an A4 page but the other half is basically connected at the bus-tie and is the same as

the first half except no lightning surge. Figure 3.5 includes the model of the

switchboard room.

20
Figure 3.2: Simulink model - Incoming transmission line

21
Figure 3.3: Simulink model - 132kV substation layout

22
Figure 3.4: Simulink model - 22kV side of substation

23
Figure 3.5: Simulink model - 22kV switchboard room

24
3.7 Current Surge

The current surge has been produced so that it can simulate any specified tf/tT

waveform. Equation (3.1) was used to produce this flexibility and was derived by

Cvetić et al (1999). A double exponential has often been used in the past but the

characteristics don’t quite match the standard waveshape definition and the high

derivative at the origin can cause singularities in the result as was discovered in the

development stage.

n −t
⎛t ⎞ ( )
Io ⎜ ⎟ e τ 2
i (t ) = ⎝ τ1 ⎠ (3.1)
⎛ ⎞
⎜ ⎟
⎜ ⎟
⎜ −τ1 ⎟
⎜ ⎛ 1 ⎞ ⎟
⎜ ⎛ nτ 2 ⎞⎜⎝ n+1 ⎟⎠ ⎟
⎛ ⎛ t ⎞⎞ ⎜⎜ τ 2 ⎜
⎝ ⎝ τ1 ⎠
⎟ ⎟⎟
⎜1 + ⎜ ⎟ ⎟ e

⎝ ⎝ τ1 ⎠ ⎠

The parameters are given such that,

Io : Maximum current

n: Steepness factor of approximately 7 for Perth

τ1 : Front time (equal to 1.2us for the standard lightning waveshape)

τ 2 : Tail time (equal to 50us for the standard lightning waveshape)

25
3.8 Corona Effects

The corona effect affects surges to a large degree by decreasing the steepness of the

wavefront. An accurate account of the effects of corona has been inbuilt into the

model.

Corona will lessen the impact of a lightning surge the further a surge travels along a

line. It is caused when a threshold voltage on the line is reached such that the

effective radius of the conductor is increased due to streamers emanating from the

conductor. This effective increase results in an increase of capacitance to ground and

also results in a decrease of velocity of propagation and surge impedance which

pushes back the wave front of the surge.

There are other phenomena, such as earth resistivity that also causes attenuation and

distortion of travelling waves but corona is the dominant effect.

26
4.0 DATA ACQUISITION

4.1 Introduction

All of the data that was acquired for the model of the substation has been supplied by

WP (2005a) unless otherwise specified. Data sheets or typical values have been used

where information was not given specifically to the author.

4.2 Ratings of Substation Elements

The BIL ratings and approximate CFO for all equipment are listed in Table 4.1.

Rated Voltage (kV) BIL (kV) CFO (kV)


132 650 980
22 150 220
Table 4.1: BIL ratings of substation equipment

4.3 All Equipment

4.3.1 Transmission Line and Towers

The possible incoming lines for the 132kV side of the substation included Triton

wires where the details are as follows,

Geometric Mean Conductor Outside A.C Resistance @


Conductor
Radius (mm) Diameter (mm) 75° (Ω/km)
Triton 9.82 26.3 0.087
Table 4.2: Transmission line properties

The arrangement of the wires is important and the most common arrangements were

the following two types,

27
Arrangement 1 Arrangement 2
E

B
18.5m

C
16.7m

15.9m
15m

Figure 4.1: Orientation of transmission lines

Using the conductor parameters and the orientation of the line allows the sequence

impedances to be calculated. An intrinsic program within SimPowerSystems known

as RLC Calculator allows this information to be easily obtained.

Arrangement One Arrangement Two


Positive Sequence
6.32 10.54
Resistance (Ω/km)
Zero Sequence Resistance
270.49 201.97
(Ω/km)
Positive Sequence
1.1 1.27
Inductance (Ω/km)
Zero Sequence
2.24 1.84
Inductance (mH/km)
Positive Sequence
1.08 9.2
Capacitance (nF/km)
Zero Sequence
5.27 6.42
Capacitance (F/km)
Table 4.3: Sequence impedance parameters for transmission line

28
Arrangement one is the most common and is therefore used for the insulation co-

ordination studies. It is also shown in Browne (2005) that the possible exposure to

current from a shielding failure is greatest for this arrangement type and thus further

warrants the study.

The transmission line tower impedance is given as 400Ω.

4.3.2 Distribution Line and Towers

The outgoing 22kV lines are modelled as follows,

Geometric Mean Conductor Outside A.C Resistance @


Radius (mm) Diameter (mm) 75° (Ω/km)
5.86 16.3 0.226
Table 4.4: Distribution line properties

The arrangement of the wires is important and the most common arrangement was

the following type,

Figure 4.2: Typical orientation of distribution lines

29
Using the conductor parameters and the orientation of the line allows the sequence

impedances to be calculated. An intrinsic program within SimPowerSystems known

as RLC Calculator allows this information to be easily obtained.

Parameters
Positive Sequence Resistance (Ω/km) 119
Zero Sequence Resistance (Ω/km) 743
Positive Sequence Inductance (Ω/km) 1.11
Zero Sequence Inductance (mH/km) 3.09
Positive Sequence Capacitance (nF/km) 10.9
Zero Sequence Capacitance (F/km) 3.89
Table 4.5: Sequence impedance parameters for distribution line

The transmission line tower impedance is given as 320Ω.

4.3.3 Cables

The cables that are used for the 22kV side of the substation are of type 500mm2 1/C

Cu XLPE Heavy Duty Cu wire SCR, PVC Sheath. Datasheets give the relevant data

and are displayed in Table 4.6.

Zero Seq. Impedance (Rated Temp) 0.45 + j0.055 ohms/km


Pos Seq. Impedance (Rated Temp) 0.098 + j0.114 ohms/km
Shunt Capacitance 0.302uF/km
Table 4.6: 22kV cable data (Cu XLPE 500mm2)

Cables are assumed to run for 100m before joining to distribution lines as per WP

(2005a).

30
4.3.4 Busbars

The 132kV busbar is built from an 80 OD x 6 WT Aluminium Tube. The surge

impedance is given as 380Ω from WP (2005b).

The 22kV busbar is assumed to be 310Ω which is a measure based on typical

conductors within the station, also from WP (2005b).

4.3.5 Transformers – Power, Current and Voltage

The power transformers, current transformers, and voltage transformer values for the

132kV side were measured from terminal to ground and are summarised in Table 4.7.

132kV Equipment Capacitance (nF)


132/22kV Transformer, T1 on 132kV side 8.094
132/22kV Transformer, T3 on 132kV side 8.092
132kV VT 6.25
132kV CT 1
Table 4.7: Capacitance values for the 132kV side

Likewise, the values were also measured for the 22kV side of the substation and are

displayed in Table 4.8.

22kV Equipment Capacitance (nF)


132/22kV Transformer, T1 on 22kV side 11.7
132/22kV Transformer, T3 on 22kV side 11.34
Table 4.8: Capacitance values for the 22kV side

The capacitances given were not measured at high frequency to simulate lightning.

However, the representation is the best that the utility had to offer and is therefore

acceptable within the study.

31
4.3.6 Switchgear

A single capacitor value for each of the 22kV switch rooms was given as 400pF.

This was measured from phase to ground with the other phases connected to ground.

Older stations are within the range of 400pf to 9000pf.

4.3.7 Surge Arresters

The surge arrester data is based on equipment specifications provided by the utility

and important characteristics are summarised in Table 4.9.

132kV Arrester 22kV Arrester


Arrester Type XA3095 ABB POLIM-D18-L
High energy dissipation, Standard 22kV Line
brown, with insulated Arrester
base, zinc-oxide
MCOV (kVRMS) 96 15.3
Lightning Impulse Residual Voltages (8/20μs, kVP)
5kA 265 52.1
10kA 285 56
20kA 315 63.6
Energy Handling Capability 6.5kJ/kV 3.6kJ/kV
based on MCOV 624kJ 55kJ
Table 4.9: Surge Arrester characteristics

4.3.8 Distribution Line Load

Total load outgoing from the substation was given as 24MW and 9MVAR. These

loads are averaged out into the eight distribution lines and therefore the outgoing

power is estimated as 3MW with 1.125MVAR per feeder.

32
4.3.9 Capacitor Banks

Capacitor bank loading was given as 5MVAR, 22kV nominal with 4.53% series

reactors.

33
5.0 ASSESSING RISK

5.1 Probability

The probability of an event occurring allows the utility to assess risk in a quantifiable

manner. If a standard level of acceptable risk is decided upon then a company has a

benchmark level of safety and can set a standard cost structure to pay for the required

level of protection. Numerous studies have been made in the past of lightning strike

intensities and the probability of events occurring. Most of these have been

summarised in Hileman (1999) with comparisons and acknowledgements to many

other sources. Also, the probability of the events is inbuilt into the model and

described in Browne (2005).

This chapter focuses on the probability of the events occurring and some of the

theory that is necessary to build these models, specifically focusing on line

orientation and keraunic levels.

5.2 Keraunic Level

The keraunic level is defined as the average number of thunderstorm days in a year.

The Bureau of Meteorology conducts numerous studies into lightning intensity and

creates maps based on these values as shown in Figure 5.1.

It is clearly seen in the diagram that Perth experiences approximately 10 to 15

thunderstorm days per year.

34
Figure 5.1: Keraunic levels throughout Australia

It is very important to note that if the utility built a system in the north of the state,

then the system would be looking upwards of 80 thunderstorm days per year. Given

that the system is in Perth, there are tradeoffs that are applicable that may not be in

other places. These possibilities may need to be considered in another insulation co-

ordination study.

5.3 Lightning Incidence

To quantify the rate and likelihood of lightning surges hitting a transmission line and

thus leading into a substation, the incidence of lightning flashes is needed. The

number of lightning flashes occurring is found in numerous sources – notably the

IEEE Standard 1312.1.

35
The lightning flash density, Ng is an approximation of past data and is a regression

line (5.1) that is based on the keraunic level which is represented as thunderstorm

days per year, Td.

N g = 0.04Td1.25 [flashes/km 2 ⋅ years] (5.1)

The number of lightning flashes is also taken from the aforementioned IEEE

standard and is estimated by,

28h 0.6
N (G ) = N g [flashes/100km ⋅ years] (5.2)
10

5.4 Line Orientation

The orientation of the lines exposed to lightning surges is of vital importance.

Flashovers are most highly influenced by the orientation of the lines. However, this

chapter deals with what is known as the geometric model and basically defines an

upper limit for surges against a shielded line.

The geometric model presented here is referenced from Hileman (1999) who in turn

references numerous sources to its validity. This model is the accepted method and is

commonly used in practice in insulation co-ordination studies as Hileman (1999)

suggests and Metz-Noblat (1994) implements.

The model itself is based on a regression line that looks at the striking distance and

the current magnitude. The intensity of current that could strike a line is near

proportional to the distance from the conductors and earthing wire. By drawing arcs

from the lines, it can be seen where a current can protect a line and where it cannot.

36
(a) Unprotected zone (b) Protected zone

Figure 5.2: Diagrammatic view of the geometric model

Figure 5.2 demonstrates that at a certain current the phase conductors are exposed to

the lightning surge but when the magnitude of the surge increases, the phase

conductors are protected by the shielding wire which suggests an upper maximum to

the possible current that can strike the line.

Equation (5.3) gives the maximum theoretical current, i, that can be exposed to the

phase conductors. DC must be greater than or equal to zero for the current to have a

possibility of hitting the line.

⎛ ⎛ ⎛ a2 ⎞⎞⎞
⎜ ⎜ ⎜ (h − y ) 1 + ⎟⎟⎟
⎜ (r − y ) 2
⎜ ⎛ a ⎞ 1 −1 ⎜ (h − y )2 ⎟⎟⎟ (5.3)
Dc = rc ⎜ 1 − g 2 − cos ⎜ tan −1 ⎜ ⎟ + sin
rc ⎝h− y⎠ 2 ⎜ 2rc ⎟⎟⎟
⎜ ⎜ ⎜ ⎟⎟⎟
⎜ ⎜ ⎜ ⎟⎟
⎝ ⎝ ⎝ ⎠ ⎠ ⎠⎟

5.5 Distribution of lightning

There have been many studies, with Berger one of the major contributors and

summarised in Hileman (1999) that have investigated the distribution of lightning.

The most accepted distribution is the log normal distribution (5.4). Consensus on the

parameters is not entirely established however due to the different data sets that have

37
been used to create them. This simulation uses M equal to 34 and β equal to 0.74

which are the accepted values from CIGRE (1991).


2
1 ⎡ ln( I / M ) ⎤
1 − ⎢
β ⎥
f (I ) = e 2⎣ ⎦
(5.4)
2π β I

5.6 Lightning Induced Currents

With the aforementioned knowledge, it is possible to determine the occurrence of the

different types of lightning events.

The rate of shielding failures to the line is a product of the geometric model, the

length of exposed line and also the probability density function of lightning

mentioned in section 5.5. Thus the rate of shielding failures is found from (5.5).
I max

SFR = 2 N g L ∫
0
Dc f ( I )dI (5.5)

Backflash rates are also a function of the probability density function of lightning,

with the lightning exceeding the critical current as defined by the CFO (critical

flashover) of the line simulation. Equation (5.6) gives the backflash rate.

BFR = N (G ) P( I c ) (5.6)

Direct strikes are simply based on the distribution of lightning from section 5.5.

38
5.7 Risk of Event

The measure of risk for the event happening in the substation’s lifetime can be found

using the exponential distribution. The statistical time between two occurrences is

equal to,

1
Td = (5.7)
λ

Where λ is the rate of flashes per year.

The risk of the event exceeding the magnitude of the lightning current being

investigated is equivalent to,

Risk = 1 − e( − ts / Td ) (5.8)

Where ts is the substation life in years.

39
6.0 INSULATION CO-ORDINATION TESTING

6.1 Simulating the Substation

The substation was simulated using the Simulink tool that is defined in prior chapters

of this report. All of the system data that was available and appearing in chapter 4.0

was inputted into the model as well as the keraunic level appearing in Figure 5.1.

As such, with all of the data, the substation is able to be accurately simulated. All of

the possible lightning events need to be considered and tested on the model. Possible

events are chosen by simply selecting the type of strike required.

The typical 132/22kV zone substation design must be modelled on both the 132kV

and 22kV sides to prove the validity of the design. It is noted however that in general

practice only the high voltage side is modelled because flashovers almost always

occur on the 22kV side due to the size of the conductors, the spacing and proximity

to ground (Metz-Noblat 1994).

The most important statistics including the maximum voltage experienced by the

transformers and also the energy absorbed by the surge arresters is summarised in the

results output and is displayed in tabular format within this chapter for each event.

The graphical outputs are displayed only for the shielding failure and thereafter

appear in Appendix B.

40
Based on the output of the model, the substation can be shown to be insulation co-

ordinated or in need of a better design. The main figure that governs this is the safety

margin – a safety coefficient of 20%-30% is the norm for a substation (ARTC 2005).

The safety coefficient can be found using the following equation,

BIL − Vmax
S= *100 (6.1)
BIL

6.2 The 132kV Side

6.2.1 Possible Events

The 132kV side of the substation includes two incoming transmission lines with

shielding wires of approximately 1.5km in length. As such, the possible events are a

shielding failure, a backflash or a direct strike.

The shielding failure and the backflash can occur in the section of line where the

earth wire exists. Direct strikes occur beyond this point as there is no shielding.

6.2.2 Worst-case Scenario

The worst-case scenarios that the substation could be exposed to should be

considered. The highest transfer of surge occurs to a single transformer when the

high voltage bus-tie is not connected and the surge occurs within the span of

transmission line closest to the substation. Figure 6.1 shows the connections for the

substation.

41
Figure 6.1: 132kV configuration for simulation

42
Even though this situation is regarded as having a low probability of occurring as

opposed to the high probability of the substation operating at full capacity, the safe

level of operation at this level shows that the substation is even higher protected at

normal operation. The following page shows the setup of the model for this scenario.

6.2.3 Shielding Failure

The shielding failure has been tested within the final span of the model (80m of

transmission line) and the results are shown in this chapter. As this is the first

simulation, all figures are shown and explained as a representation of the results.

Chapters thereafter will only summarise the results and figures can be referred to in

Appendix B.

The simulation automatically tests the model for the highest current theoretically

possible due to the geometrical model of the line as discussed in Section 5.4.

Running the simulation gives Figures 6.2, 6.3 and 6.4 that give the two surge

arresters performance as well as transformer performance respectively.

43
Surge Arrester 1 of Tx 1 Voltage
2000

Voltage (kV) 0

-2000
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Current
50
Current (kA)

-50
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Absorbed Energy
400
Energy (kJ)

200

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 6.2: Surge arrester 1 performance under shielding failure

Figure 6.2 shows that for the first surge arrester, the voltage has indeed been limited

to the rated voltage level. The current resembles the lightning surge current which

shows that the lightning current has entered the substation and when it drops to zero

the voltage has dropped to a low enough level such that the surge arrester no longer

diverts energy (also evident from the energy diagram). This figure shows the user

that the surge arrester operates as expected.

44
Surge Arrester 2 of Tx 1 Voltage
500

Voltage (kV)
0

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Current
20
Current (kA)

-20
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Absorbed Energy
400
Energy (kJ)

200

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 6.3: Surge arrester 2 performance under shielding failure

Surge arrester two also performs like surge arrester one and is clearly very

comparable in attributes except the current and energy is lower. This is expected as

the second surge arrester is exposed to the surge after the first surge arrester has

diverts much of the surge previously.

45
Transformer 1 Voltage (kV)
500

Voltage (kV)
0

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Transformer 1 Current (kA)
4

2
Current (kA)

-2

-4
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 6.4: Transformer performance under shielding failure

The power transformer experiences a maximum voltage at the beginning of the surge

and then drops slowly for 140µs, followed by significant decreases further after this

point as the surge has started to dissipate.

The graphical outputs are necessary to show that in the testing range of 200µs, the

transformer has been exposed to the maximum voltage and also the surge arresters

have absorbed all the energy that is possible from the surge. The above figures

validate these showing that the testing time of 200µs is a valid operational time for

the simulation to run and as such results can be used with high reliability.

46
Results can be summarised (Table 6.1) to look at the current that was supplied, the

safety coefficient and the energy to the surge arresters as well as the risk that is

entailed under this scenario.

Maximum Lightning Current (kA) 15.9


Peak Transformer Voltage (kV) 485
Transformer BIL (kV) 650
Max Voltage as % of BIL 75
Safety Coefficient (%) 25
Surge Arrester Fault Level (kJ) 624
Surge Arrester 1 (kJ) 341
Surge Arrester 1 (% of fault) 55
Surge Arrester 2 (kJ) 211
Surge Arrester 2 (% of fault) 34
Lifetime of Substation (years) 30
Risk of event (%) 0
Table 6.1: Summary of simulation for shielding failure to 132kV side

Clearly, the surge leaves the power transformer intact with a large safety margin. The

surge arresters also do not exceed the maximum energy for a fault and have a large

safety factor built into them.

An anomalous result occurs in this case as the risk of this event is zero due to the

geometric model limiting the current to a maximum and simulation runs at that

maximum value. The risk for shielding failure is considering the conditional

probability of the current exceeding that level.

As a conclusion, the worst-case possible scenario caused by a shielding failure (of

which is probably never going to occur in the lifetime of the substation), an

overvoltage caused by lightning will reach 485kV corresponding to 75% of the

defined BIL, i.e. a calculated safety coefficient of 25%.

47
6.2.4 Backflash

The backflash event has been tested within the final span of the model (80m of

transmission line) and the results are summarised in Table 6.2 with the graphical

outputs in Appendix B.

The simulation automatically tests the model for the highest current theoretically

possible for a backflash due to the geometric model and insulation of the line.

Maximum Lightning Current (kA) 7.26


Peak Transformer Voltage (kV) 462
Transformer BIL (kV) 650
Max Voltage as % of BIL 71
Safety Coefficient (%) 29
Surge Arrester Fault Level (kJ) 624
Surge Arrester 1 (kJ) 120
Surge Arrester 1 (% of fault) 19
Surge Arrester 2 (kJ) 85
Surge Arrester 2 (% of fault) 14
Lifetime of Substation (years) 30
Risk of event (%) 11
Table 6.2: Summary of simulation for backflash event to 132kV side

Clearly, the surge leaves the power transformer intact with a large safety margin. The

surge arresters also do not exceed the maximum energy for a fault and have a large

safety factor built into them. Graphs in the appendix show the runtime is sufficient.

As a conclusion, there is an 11% chance that, during the service life of the substation,

an overvoltage caused by a lightning resulting in a backflash event will reach or

exceed 462kV, corresponding to 71% of the defined BIL, i.e. a calculated safety

coefficient of 29%.

48
6.2.5 Direct Strike

Direct strike events can only occur for the 132kV line at 1.5km and beyond because

of the earth wire. This event is thus tested at the 1.5km limit and the results are

summarised in with the graphical outputs in Appendix B.

At a 1.5km distance, attenuation of the surge due to corona and earthing resistivity

lowers the possibility of a destructive surge. And in fact, due to the very high

possibility of flashovers for any surges over the CFO of the line only a low

magnitude current can possibly hit the substation.

The design current used is such that 2 times the CFO voltage is experienced so that a

relative large safety margin of 100 percent above the CFO is considered. The current

can be determined by,

2* CFO
I direct = (6.2)
Z tower

This corresponds to the following simulation output,

Maximum Lightning Current (kA) 4.9


Peak Transformer Voltage (kV) 424
Transformer BIL (kV) 650
Max Voltage as % of BIL 65
Safety Coefficient (%) 35
Surge Arrester Fault Level (kJ) 624
Surge Arrester 1 (kJ) 83
Surge Arrester 1 (% of fault) 13
Surge Arrester 2 (kJ) 59
Surge Arrester 2 (% of fault) 9
Lifetime of Substation (years) 30
Risk of event (%) 99
Table 6.3: Summary of simulation for direct strike to 132kV side

49
Clearly, the surge leaves the power transformer intact with a large safety margin. The

surge arresters also do not exceed the maximum energy for a fault and have a large

safety factor built into them. Graphs in the appendix show the runtime is sufficient.

As a conclusion, there is a very high risk of this event occurring (in terms of the

magnitude of the current however this is unlikely due to the extremely high

possibility of flashovers) during the service life of the substation. An overvoltage

caused by lightning resulting in a direct event will reach or exceed 424kV,

corresponding to 65% of the defined BIL, i.e. a calculated safety coefficient of 35%.

6.2.6 Summary of Protection

Shielding
Failure Backflash Direct Strike
Maximum Lightning Current (kA) 15.9 7.26 4.9
Peak Transformer Voltage (kV) 485 462 424
Transformer BIL (kV) 650 650 650
Max Voltage as % of BIL 75 71 65
Safety Coefficient (%) 25 29 35
Surge Arrester Fault Level (kJ) 624 624 624
Surge Arrester 1 (kJ) 341 120 83
Surge Arrester 1 (% of fault) 55 19 13
Surge Arrester 2 (kJ) 211 85 59
Surge Arrester 2 (% of fault) 34 14 9
Lifetime of Substation (years) 30 30 30
Risk of event (%) 0 11 99
Table 6.4: Summary of simulations to 132kV side

The conclusion that can be arrived from the tests to the 132kV side of the substation

is that it is highly protected against strikes. With worst-case events the safety

coefficient is at a very acceptable level of 25%. This shows that changes can be made

to the 132kV side such that the cost may be decreased if the current safety level is

relaxed.

50
6.3 The 22kV Side

6.3.1 Different Events

The 22kV side of the substation includes eight outgoing distribution lines with no

shielding wires. As such, the only possible event is a direct strike.

6.3.2 Worst-case Scenario

The worst-case scenarios that the substation could be exposed to should be

considered. The highest transfer of surge occurs to a single transformer when the low

voltage bus-tie is not connected, only one distribution line is connected and no

capacitor banks, and the surge occurs within the span of distribution line closest to

the substation. Figure 6.5 shows the connections for the simulation.

Even though this situation is regarded as a low probability of occurring as opposed to

the high probability of the substation operating at full capacity, the safe level of

operation at this level shows that the substation is even higher protected at normal

operation. The following page shows the setup of the model for this scenario.

51
Figure 6.5: 22kV configuration used for simulation

52
6.3.3 Direct Strike

The 22kV line is high at risk of flashovers; in fact using equation (6.2) only registers

a current crest of 1.375kA. Generally, surges are run from a minimum of 3kA and

this event is therefore considered in the context of the 22kV line.

This corresponds to the following simulation output,

Maximum Lightning Current (kA) 3


Peak Transformer Voltage (kV) 113
Transformer BIL (kV) 150
Max Voltage as % of BIL 75
Safety Coefficient (%) 25
Line Arrester Fault Level (kJ) 55
Line Arrester (kJ) 11
Line Arrester (% of fault) 20
Lifetime of Substation (years) 30
Risk of event (%) 97
Table 6.5: Summary of simulation for direct strike to 22kV side

Clearly, the surge leaves the power transformer intact with a large safety margin. The

surge arresters also do not exceed the maximum energy for a fault and have a large

safety factor built into them. Graphs in Appendix B show the runtime is sufficient.

As a conclusion, there is a very high risk of this event occurring (in terms of the

magnitude of the current however these are unlikely due to the extremely high

possibility of flashovers) during the service life of the substation. An overvoltage

caused by lightning resulting in the direct event will reach or exceed 113kV,

corresponding to 75% of the defined BIL, i.e. a calculated safety coefficient of 25%.

53
6.3.4 Summary of Protection

The conclusion that can be arrived from the tests to the 22kV side of the substation is

that it is highly protected against strikes. With worst-case events the safety

coefficient is at a very acceptable level of 25%.

6.4 Current Level of Protection for the Substation

The simulations on both the 132kV and 22kV sides successfully show that the power

transformer is highly protected against lightning surges. A lower bound safety

margin of 25% is recorded for both sides of the station with surge arresters not

hitting fault levels for the worst-case scenarios that were tested.

This insulation co-ordination study has shown that the typical 132/22kV zone

substation for the utility is protected. It is protected enough to warrant further

investigation into possible changes to the configuration that may incur a loss of some

protection but with an economic windfall. The next chapter deals with this topic of

interest.

54
7.0 SENSITIVITY ANALYSIS

7.1 Introduction

Sensitivity analysis was conducted to consider alternative configurations for the

substation focusing mainly on the elements but also on the layout. The purpose of

this section is to consider alternative setups that while still providing protection, also

show an economic benefit in changing the configuration. Possible improvements in

protection are also considered through simulation.

7.2 Economic Considerations

Economically, there are only a limited number of changes that can be made to a

substation while keeping it at a protected level. The considerations made in this

chapter are the power transformer and the surge arresters. There are other options

such as changes to the cables but these are only discussed later and not researched.

The bulk cost of a substation is attributed to the power transformer(s). In the case of

a 132/22kV transformer with a 650kV BIL rating, the cost is approximately

$700,000 but this depends greatly on the demand for new transformers and the price

of copper.

Current surge arrester prices are summarised below,

132kV overhead line connected $2,200


132kV cable connected $2,700
22kV aerial feeder (LD class 1) $130
22kV transformer connected (LD class 3) $850
Table 7.1: Costs of surge arresters

55
The surge arresters considered in this report are the 132kV overhead line connected

and the 22kV aerial feeder. Clearly, the cost of a surge arrester is insignificant when

compared to the cost of the reduced BIL of the power transformers.

7.3 Testing Method

The sensitivity analysis utilised, where necessary, the same methods as the original

insulation co-ordination study. The worst case scenario was taken for the

comparisons. This allowed a regimented set of controls so that an accurate study

could be taken of the alternative arrangements.

Some of the study did not need new simulations, rather an in-depth discussion of the

ramifications of changing the setup based on the results from the initial study.

The relative cheapness and the high protection already existing on the 22kV side

warrant no further investigation. Also, the power transformer cost is mainly based on

the HV BIL further reducing the warrant to study the 22kV side in further depth.

7.4 BIL Ratings

In terms of cost of the substation, the BIL rating has the most significant impact

when looking at protection. Australian Standards 1824.1 specifies two different BIL

ratings for 132kV power transformers – 550kV and 650kV plus some provisions for

a 450kV rating. The current configuration is 650kV and therefore the other two

options are considered.

56
Transformer BIL (kV) 650 550 450
Maximum Lightning Current (kA) 15.9 15.9 15.9
Peak Transformer Voltage (kV) 485 485 485
Max Voltage as % of BIL 75 88 108
Safety Coefficient (%) 25 12 -8
Table 7.2: Comparison of different BIL ratings

A comparison of the different BIL ratings that are possible shows that the 450kV

BIL does not protect the substation. However, the 550kV BIL has a high enough

safety coefficient to run in the station although this somewhat out of the safety

margin of 20-30% considered earlier.

A typical 132kV transformer for the utility costs approximately $700,000 and even

though the quoting for a 550kV BIL is still under consideration, it is believed a

significant portion of the cost could be reduced. Therefore, the 550kV BIL power

transformer should be considered when building any new substation.

7.5 Surge Arrester

If the surge arrester limiting voltage is modified, then the exposed transient voltages

throughout the substation and in particular the power transformer will change

applicably also.

It is not possible to reduce the surge arrester voltage ratings indefinitely because

surge arresters have a rating known as the MCOV – the maximum continuous

overvoltage. In other words the limiting voltage is a function of the surge arrester

type but the type is limited by the MCOV. The MCOV must be greater than the line-

57
neutral voltage of the line with an added safety margin to take into account the

voltage regulation.

The IEEE Std C62.11-1993 lists numerous MCOV voltages. Of concern in this

report is the MCOV ratings of 96kV and a lower value of 84kV with the former

value being the current surge arrester type. Lower ratings are not investigated

because the minimum MCOV will be breached as in Table 7.3. Of course, there are

intermediate ratings (88kV) that could be tested also but the best results are assumed

from the chosen option. The relevant system is italicised.

Steady state operation:


system voltage and arrester ratings
Max system Max system Min MCOV
voltage L-L voltage L-G rating
kVrms kVrms kVrms
4.37 2.52 2.55
8.73 5.04 5.1
13.1 7.56 7.65
13.9 8.00 8.4
14.5 8.37 8.4
26.2 15.1 15.3
36.2 20.9 22
48.3 27.8 29
72.5 41.8 42
121 69.8 70
145 83.7 84
169 97.5 98
242 139 140
362 209 209
550 317 318
800 461 462
Table 7.3: Minimum MCOV ratings for Distribution Systems
[IEEE Std C62.22-1997]

58
The simulation was run using the trial arrester with MCOV of 84kV. Results (Table

7.4) show that the trial arrester offers far superior performance with an enhanced

safety margin. The one drawback of this different arrester could be the extra risk in

receiving a continuous overvoltage however there is still a large safety margin

(greater than 10% above the rms voltage) so any problems should be avoided.

Appendix B shows the graphical results for the test which show the runtime is

sufficient.

Current Arrester Trial Arrester


Peak Transformer Voltage (kV) 485 429
Transformer BIL (kV) 650 650
Max Voltage as % of BIL 75 66
Safety Coefficient (%) 25 34
Surge Arrester Fault Level (kJ) 624 546
Surge Arrester 1 (kJ) 341 284
Surge Arrester 1 (% of fault) 55 52
Surge Arrester 2 (kJ) 211 171
Surge Arrester 2 (% of fault) 34 31
Table 7.4: Comparison of different surge arresters

The cost difference between the two surge arresters is minimal with a slight saving of

$100-$200 produced from the change. The protective nature of the new device would

be the reason for the change however and not the cost saving.

Another enhancement that could be made is lowering the energy level that the surge

arrester could handle, the large gap between absorbed energy and energy to fault at

present leaves this as an option. Generally, however the ratings are fairly standard by

manufacturers and no different alternatives could be found. If it were possible, the

cost saving would most likely be minimum (if anything at all) and the increased risk

in fault does not justify the means.

59
7.6 Earth Wire

The shielding wire extending from a substation can substantially increase the cost of

the design due to the extra loading on the towers and the tower designs necessary to

include space for the shielding wire as well as the cost of the conductor. While these

differences may not come close to the cost of a power transformer, they are

significant in terms of time, especially if design modifications are necessary or

upgrades are made to existing substations.

The current length of earth wire (approximately 1.5km) is based on surge arrester

manufacturer recommendations. As Perth, has a lower level of lightning than most

other places in the world, modifications should be possible to the system.

The simulations were made by testing a direct strike outside of the earth wire range.

Two scenarios – an earth wire length of 500m and no earth wire at all were compared

with the results of the 1.5km length and results are below in Table 7.5.

1.5km 0.5km No earth – 10m


Peak Transformer Voltage (kV) 424 424 434
Transformer BIL (kV) 650 650 650
Max Voltage as % of BIL 65 65 67
Safety Coefficient (%) 35 35 33
Surge Arrester Fault Level (kJ) 624 624 624
Surge Arrester 1 (kJ) 83 88 94
Surge Arrester 1 (% of fault) 13 14 15
Surge Arrester 2 (kJ) 59 62 64
Surge Arrester 2 (% of fault) 9 10 10
Table 7.5: Effects of different earth wire lengths

60
Quite clearly, the results show that no earth wire at all would be sufficient for

protection of the substation. However, this is not recommended because the tests are

based on the risk of a flashover across the line insulation. On the low probability that

a flashover might occur, such an event could be very destructive without the shield to

provide protection against a maximum crest current based on the geometric model.

Based on the results as well as reasoning of the possible event where a flashover does

not occur, it appears that the current length of earth wires can be shortened to

perhaps two or three spans running to approximately 500m to 800m of length. This

would be a very useful design modification for the utility.

7.7 Surge Arrester Position

The position of the surge arresters can have a large affect on the voltage that would

be experienced on certain parts of the line. Position is important because it lowers the

length of the line for reflections to build up if the conductor is shorter. In particular,

the surge arrester closest to the power transformer is investigated because if it is

possible to make it closer, then lower transient voltages would be experienced at the

terminals of the transformer.

The testing of the position of the surge arrester was made such that the distance

between the second current transformer and the power transformer were fixed but the

surge arrester was not, which makes 6.6m leeway withstanding physical constraints.

Physical constraints do not allow the surge arrester to be within 1.4m of the

transformer.

61
The model was simulated numerous times for different distances with similar

graphical results in all cases. The shielding failure results in Section 6.2 are

representative of all the cases with only slight variations.

A clear downward trend from the results in Figure 7.1 is seen as the distance is

shortened. Clearly, the closer the transformer is to the transformer the better. This

backs up the hypothesis expressed earlier.

Maximum Voltage vs Distance from Transformer

500
495
490
485
Voltage (kV)

480
475
470
465
460
455
450
0 0.5 1 1.5 2 2.5 3 3.5 4
Distance (m)

Figure 7.1: Variation of the position of the surge arrester

Based on the data, it is best to have the surge arrester as close to the transformer as

possible. A safety margin increase of approximately 4% (Table 7.6) is achievable at

the closest position possible to the transformer.

62
Distance Maximum Safety Margin
(m) Voltage (kV) (%)
1.4 462 29
1.6 464 29
1.7 465 28
1.75 466 28
2 468 28
2.25 471 28
2.5 473 27
2.75 475 27
3 477 27
3.1 483 26
3.2 485 25
3.5 490 25
Table 7.6: Safety margins for different positions of the surge arrester

7.8 Other Possibilities

7.8.1 Minor Enhancements

There are numerous other changes that could be made to the substation design. While

these are not considered in the analysis due to the small difference made and/or

complexity of the change, they are left here as a discussion.

7.8.2 Orientation of the line

Orientation of the line can enhance the substation in two ways – further shielding and

also to change the RLC parameters of the line.

Further shielding by modifying the angles of the lines in comparison to the shielding

wire can result in exposure to a theoretical lower maximum current which would

reduce the need for a higher BIL rating. This is based on the geometric model

explained in Section 5.4.


63
RLC parameters can be modified by changing distances between the phase

conductors. If these parameters are changed then the inductance and capacitance of

the line changes which may retard the strength of the surge.

The problem with the change in orientation is the cost of the modifications to be

made and to the standard towers that are used not just at the entrance to substations

but to entire lengths of line. A new standard could be created for outgoing of

substations but this will require further investigation.

7.8.3 Change of conductor

Changes to the conductors that are used for transmission lines, distribution lines and

within the substation are possible but because most suitable conductors used for this

job have similar parameters. As before the RLC parameters would be changed with

different conductors. Thus, because of only a theorised slight improvement it is not

deemed significant compared to the other modifications that were considered within

this study.

64
8.0 CONCLUSION

This project was undertaken by David Browne and the author whom together co-

developed a Matlab Simulink model to run insulation co-ordination studies. The full

development of the model can be found in the thesis by Browne (2005).

Utilising the tool in Simulink, the current configuration of the utility’s standard

132/22kV zone substation has been simulated under a full insulation co-ordination

study. The study shows that under a worst-case scenario the substation is protected

with a safety margin of 25% from the basic insulation level.

Possible changes to the current configuration were also investigated that could bring

an economic windfall and/or enhanced protection if the substation design was

modified. Recommendations for the following have been made:

1. Reduce the BIL of the 132kV side of the substation to 550kV.

2. Change the surge arresters on the 132kV side to a MCOV level of 84kV.

3. Move the surge arrester closest to the power transformer on the high voltage

side to a position as close as possible to the transformer.

4. Reduce the length of the earth wire to two to three spans instead of the

current 1.5km.

As the realm of insulation co-ordination is very large and with the flexibility of the

model that was produced for this project, much of this topic can be explored in

greater depth. There are many additional topics of interest that can be included in

future studies as an extension.

65
Substations of all voltage ratings whether low, high or extra high can be simulated

using the methods described within this report. The model is simply adjusted by

modifying the constraints with the new ratings.

Substations of higher voltage (greater than 245kV) can be simulated for both

lightning surges as well as potentially damaging switching surges as described in

Section 2.

An insulation co-ordination tool of greater detail could be built using even higher

order models as long as the equivalent data was obtainable from the utility or

manufacturer. Also, more accurate measurements could be made, for example using

high frequency tests to calculate capacitances for the transformers rather than 50Hz.

Multiple strikes leading into the substation could be investigated. Generally multiple

strikes do not damage the transformer equipment because the average time between

surges is 35ms to 45ms (Hileman 1999) and surge propagation from the former strike

has already diminished by then. However, if a circuit breaker opens then damage can

occur to that CB with subsequent lightning strikes. A detailed analysis of these

effects could be worked into the current tool.

The scope can also be extended beyond protection towards many other interests such

as harmonics. Using simulations there is no real limit to what can be achieved except

for the data that is available and the processing power of the computer.

66
9.0 REFERENCES

AS 1824.1-1995, Insulation Co-ordination - Definition, principles and rules

AS 1824.2–1985, Insulation Co-ordination Part 2: Application Guide

Australian Rail Track Corporation (2005). Insulation Co-ordination & Surge

Arrester Selection, Internal Report, ARTC, NSW. Downloaded from

www.artc.com.au/docs/nsw/engineering-standards/pdf/pds17_insulation_

coordination.pdf in May 2005.

Browne, D. (2005). Development of a Transient Over Voltage Assessment Tool for

Medium Voltage Distribution Systems, Undergraduate Thesis, Curtin University of

Technology, Perth.

CIGRE Working Group 33.01 (1991). Guide to Procedures for Estimating the

Lightning Performance of Transmission Lines, Technical Brochure, no. 63. Cited by

Hileman (1999).

Cvetić J., Heidler, F. and Stanić, B. (1999). Calculation of Lightning Current

Parameters. IEEE Transactions on Power Delivery, vol. 14, no. 2, pp. 399-404.

Greenwood, A. (1991). Electrical Transients in Power Systems, 2nd edition, John

Wiley & Sons, New York.

67
Hileman, A. (1999). Insulation Coordination for Power Systems, Marcel Dekker,

New York.

IEEE Std 1313.1-1996, IEEE standard for insulation coordination - definition,

principles, and rules

IEEE Std 1313.2-1999, IEEE guide for the application of insulation coordination

IEEE Std C66.22-1997, IEEE Guide for the Application of Metal-Oxide Surge

Arresters for Alternating-Current Systems

The Mathworks, Inc. (2004). Distributed Parameter Line (SimPowerSystems),

SimPowerSystems 4.0 Help, The Mathworks, Inc.

Metz-Noblat, B. (1994). Lightning and HV Electrical Installations, Internal Report,

Merlin Gerin, Germany. Downloaded from

www.merlingerin.com.tr/ftp/literature/publications/ECT168.PDF in May 2005.

Western Power Corporation (2004a). SS1/32/5/1/1 Standard Drawing Single Line

Schematic Diagram Zone S/S Typical Ultimate Development, Internal Document,

Western Power Corporation, Perth.

Western Power Corporation (2004b). SS193/3/2/2 Landsdale Substation 132/22kV

Electrical Equipment Elevation, Internal Document, Western Power Corporation,

Perth.

68
Western Power Corporation (2005a) Personal communication

Western Power Corporation (2005b). Power System Study Report - Insulation

Coordination, Internal Report, Western Power Corporation, Perth.

69
10.0 APPENDIX A – PROJECT SCHEDULE

The project schedule is shown in Figure 10.1. The schedule was followed from start

to end with only minor modifications of up to a week which were deemed

insignificant to update or change the schedule.

Figure 10.1: Gantt chart of project schedule

70
11.0 APPENDIX B – INSULATION CO-ORDINATION TESTING RESULTS

B1 Backflash Event to 132kV Side

Surge Arrester 1 of Tx 1 Voltage


500
Voltage (kV)

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Current
20
Current (kA)

-20
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Absorbed Energy
200
Energy (kJ)

100

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 11.1: Backflash to 132kV side - Surge Arrester 1

Surge Arrester 2 of Tx 1 Voltage


500
Voltage (kV)

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Current
10
Current (kA)

-10
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Absorbed Energy
100
Energy (kJ)

50

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 11.2: Backflash to 132kV side - Surge Arrester 2

71
Transformer 1 Voltage (kV)
500

Voltage (kV)
0

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Transformer 1 Current (kA)
4
Current (kA)

-2
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 11.3: Backflash to 132kV side – Power Transformer

B2 Direct Strike Event to 132kV Side

Surge Arrester 1 of Tx 1 Voltage


500
Voltage (kV)

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Current
10
Current (kA)

-10
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Absorbed Energy
100
Energy (kJ)

50

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 11.4: Direct Strike to 132kV side - Surge Arrester 1

72
Surge Arrester 2 of Tx 1 Voltage
500

Voltage (kV)
0

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Current
5
Current (kA)

-5
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Absorbed Energy
100
Energy (kJ)

50

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 11.5: Direct Strike to 132kV side - Surge Arrester 2

Transformer 1 Voltage (kV)


500
Voltage (kV)

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Transformer 1 Current (kA)
2
Current (kA)

-1
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 11.6: Direct Strike to 132kV side – Power Transformer

73
B3 Direct Strike Event to 22kV Side

Transformer 1 Voltage (kV)


200

Voltage (kV) 100

-100
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Transformer 1 Current (kA)
0.5
Current (kA)

-0.5

-1
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 11.7: Direct Strike to 22kV side – Power Transformer

74
12.0 APPENDIX C – SENSITIVITY ANALYSIS TESTING RESULTS

C1 Modification of Surge Arresters

Surge Arrester 1 of Tx 1 Voltage


500
Voltage (kV)

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Current
50
Current (kA)

-50
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Absorbed Energy
400
Energy (kJ)

200

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 12.1: Modified Surge Arrester Test - Surge Arrester 1

Surge Arrester 2 of Tx 1 Voltage


500
Voltage (kV)

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Current
20
Current (kA)

-20
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Absorbed Energy
200
Energy (kJ)

100

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 12.2: Modified Surge Arrester Test - Surge Arrester 2

75
Transformer 1 Voltage (kV)
500

Voltage (kV)
0

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Transformer 1 Current (kA)
5
Current (kA)

-5
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 12.3: Modified Surge Arrester Test – Power Transformer

C2 Modification of Earth Wire Distance

C2.1 Distance of 500 metres

Surge Arrester 1 of Tx 1 Voltage


500
Voltage (kV)

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Current
10
Current (kA)

-10
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Absorbed Energy
100
Energy (kJ)

50

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 12.4: Earth wire of 500m – Surge Arrester 1

76
Surge Arrester 2 of Tx 1 Voltage
500

Voltage (kV)
0

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Current
5
Current (kA)

-5
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Absorbed Energy
100
Energy (kJ)

50

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 12.5: Earth wire of 500m – Surge Arrester 2

Transformer 1 Voltage (kV)


500
Voltage (kV)

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Transformer 1 Current (kA)
2
Current (kA)

-1
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 12.6: Earth wire of 500m – Power Transformer

77
C2.2 No Earth Wire

Surge Arrester 1 of Tx 1 Voltage


500

Voltage (kV)
0

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Current
10
Current (kA)

-10
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 1 of Tx 1 Absorbed Energy
100
Energy (kJ)

50

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 12.7: No earth wire – Surge Arrester 1

Surge Arrester 2 of Tx 1 Voltage


500
Voltage (kV)

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Current
5
Current (kA)

-5
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Surge Arrester 2 of Tx 1 Absorbed Energy
100
Energy (kJ)

50

0
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 12.8: No earth wire – Surge Arrester 2

78
Transformer 1 Voltage (kV)
500

Voltage (kV)
0

-500
0 20 40 60 80 100 120 140 160 180 200
Time (us)
Transformer 1 Current (kA)
2
Current (kA)

-1
0 20 40 60 80 100 120 140 160 180 200
Time (us)

Figure 12.9: No earth wire – Power Transformer

79

You might also like