Professional Documents
Culture Documents
Checklist Readiness BOP Construction - by Engineering
Checklist Readiness BOP Construction - by Engineering
Checklist Readiness BOP Construction - by Engineering
Document
- Engineering 3
- Manufacturing
- Supply DDP 4
- Installation work
- Test & inspection
- Pre-commissioning 5
6
5
6
Scope : 2
- Engineering 3
- Manufacturing
- Material Supply 4
- Test & inspection
- Technical Advisor During Erection, Pre- 5
commissioning and Commissioning
6
6
13 TBA
Sump Pit Electrical Gauge & Elin Cable
2
- Engineering
- Manufacturing 3
- Supply DDP
- Installation work
- Test & inspection
- Pre-commissioning
- Engineering
- Manufacturing
- Supply DDP
- Installation work 4
- Test & inspection
- Pre-commissioning 5
Tank --> Boiler, Aux Boiler & etc (ELIN Cable &
19 Instrument ) TBA
5
6
Drawing GA v 1
Installation Manual v 2
Commissioning Procedure v 3
Training Manual v 4
Operation Manual v
Recommendation Spare Part list v
Drawing GA v 1
Installation Manual v 2
Commissioning Procedure v 3
Not applicable. There is no specific
Training Manual training for tank 4
Not Applicable. There is no specific
Operation Manual operation manual for tank.
Not Applicable. There is no spare part
Recommendation Spare Part list for tank.
Drawing GA 1
Installation Manual 2
Commissioning Procedure 3
Training Manual 4
Operation Manual
Recommendation Spare Part list
Drawing GA v 1
Installation Manual v 2
Commissioning Procedure v 3
Training Manual v 4
Operation Manual v
Recommendation Spare Part list v
Drawing GA v 1
Installation Manual v 2
Commissioning Procedure v 3
Training Manual v 4
Operation Manual v
Recommendation Spare Part list v
Drawing P&ID v 1
Installation Manual v 2
Commissioning Procedure Not Applicable 3
Training Manual Not Applicable 4
Operation Manual Not Applicable
Recommendation Spare Part list Not Applicable
Drawing P&ID v 1
Installation Manual Not Applicable 2
Commissioning Procedure Not Applicable 3
Training Manual Not Applicable 4
Operation Manual Not Applicable
Recommendation Spare Part list Not Applicable
Drawing P&ID v 1
Installation Manual v 2
Commissioning Procedure Not Applicable 3
Training Manual Not Applicable 4
Operation Manual Not Applicable
Recommendation Spare Part list Not Applicable
SLD Drawing v 1
Installation Manual v 2
Commissioning Procedure v 3
Training Manual v 4
Operation Manual v
Recommendation Spare Part list v
Drawing GA v 1
Installation Manual v 2
Commissioning Procedure v 3
Training Manual v 4
Operation Manual v
Installation Manual v 2
Training Manual v 4
Drawing GA v 1
Installation Manual v 2
Commissioning Procedure v 3
Training Manual v 4
Operation Manual v
Drawing P&ID v 1
Installation Manual v 2
Drawing GA v 1
Installation Manual v 2
Commissioning Procedure v 3
Not applicable. There is no specific
Training Manual training for tank 4
Not Applicable. There is no specific
Operation Manual operation manual for tank.
Not Applicable. There is no spare part
Recommendation Spare Part list for tank.
Drawing GA v 1
Installation Manual v 2
Commissioning Procedure v 3
Training Manual v 4
Operation Manual v
Drawing GA v 1
Installation Manual v 2
Commissioning Procedure v 3
Training Manual v 4
Operation Manual v
Recommendation Spare Part list v
P CONSTRUCTION
Quality Procurement
Status Status
Document Document
N/Y Finish Remarks N/Y
SAT Procedure
1 Klarifikasi Teknis
2 Klarifikasi Harga
3 SPMK / PO Rilis
4 Kick Off Meeting
1 Klarifikasi Teknis
2 Klarifikasi Harga
3 SPMK / PO Rilis
4 Kick Off Meeting
SAT Procedure
SAT Procedure
1 Klarifikasi Teknis
2 Klarifikasi Harga
3 SPMK / PO Rilis
SAT Procedure
SAT Procedure
SAT Procedure
SAT Procedure
1 Klarifikasi Teknis
2 Klarifikasi Harga
3 SPMK / PO Rilis
SAT Procedure
SAT Procedure
1 Klarifikasi Teknis
2 Klarifikasi Harga
3 SPMK / PO Rilis