Professional Documents
Culture Documents
Irjmetstemplate Finial With Abstract
Irjmetstemplate Finial With Abstract
Irjmetstemplate Finial With Abstract
5208
International Research Journal of Modernization in Engineering Technology and
Science
( Peer-Reviewed, Open Access, Fully Refereed International Journal )
Volume:04/Issue:05/May-2022 Impact Factor- 6.752 www.irjmets.com
Substructure :-
Bridge substructure is the part of the bridge that supports the entire structure on a given surrounding soil.
Substructure: The substructure is the part of the bridge that supports the entire structure on a given surrounding
soil.
1.Abutment :- It is a structure that is mainly used for bridges and dams as a span of the bridge or at the end of
thebridge as a substructure and the structure above it is resting. The single span bridge has two abutments
supporting it vertically and sideways. It also plays the role of retaining the walls to resist the movement of the
side of the earth fill in the approach of the bridge. Abutment can also be defined by the supporting structure on
one side of the arch or the stone construction used to resist lateral forces.
2.Piers –Provides central support in spans. Bridge piers mainly support the bridge superstructure element and
transfer the load to the foundation. The pier must be strong to handle horizontally as well as laterally. used is
presented in this section. Table and model should be in prescribed format.
3.Wing walls - It is one of the structures that holds the earth in place. They are located next to the abutments and
act as retaining walls. The wing wall reserves for soil, road, and ramparts, which may be at right angles to the
abutment or at different angles.
2. Superstructure :-
The components of the bridge over the bearing are known as the superstructure. The main part of the bridge is
its upper structure. The superstructure bears heavy loads while crossing the bridge. This includes deck slabs,
girders, trusses, etc. Specific elements vary depending on the type of bridge and the material, such as concrete
or steel.
1.Beam and grider :-Both have the same function of supporting the roadway and preventing bends. The girder is
also a type of beam support. Girders are used where the load is high beam support instead. The beams have a
rectangular cross-section, while the girders are I-shaped web for cross-section and stabilization with two load-
bearing flanges.
2.Bearing:-A bearing is provided between the bridge girder and the pier cap. The main function of the bearing is
to reduce the free movement or vibration of the upper superstructure and the impact stress to reach the bridge
foundation.
3.Arch and Cables- Specify both arc and cable used. Arches are used for construction of arch bridges and cables
are used for suspension, cable-stayed bridges etc. An arch bridge is a bridge with a curved arch at each end. Arch
bridges operate by transferring the weight of the bridge and its load in part to the horizontal thrust restrained
by abutments on both sides. Ways (long bridges) can be made from a series of arches, although other more
economical structures are commonly used today.
4.Parapet wall -A parapet is a safety element of any bridge that prevents a vehicle from falling where there is a
drop. It is also useful for blocking views, preventing debris from going down and acting as a sound barrier. The
roof surface may be just part of an exterior wall running along the edge line, or may be a continuation of a vertical
feature under the roof, such as a firewall or party wall, parapets originally used to protect buildings from military
attack. , But today they are mainly used as guard rails, to hide roofing equipment, to reduce the wind load on the
roof, and to prevent the spread
4.Cofferdam :-
cofferdam, a watertight enclosure from which water is pumped to open the bed of water body to allow the
construction of piers or other hydraulic works. Cofferdams are made by driving sheetpiling, usually steel in
modern works, in beds to create a watertight fence. Vertical piles are held in place by horizontal framing
members built of heavy wood, steel or a mixture of the two.
The sides of the cofferdam should be strong and well-built to
withstand the impact of a heavy dredging bucket; When water
is pumped in from the cofferdam, it must be able to withstand
the horizontal forces in the body surrounding the water.
Cofferdam at least goes back to Roman engineers, who built
many of these attachments to find their stone-arch bridges and
naval pillars.
There are several types of cofferdam. Cofferdam is defined as
a temporary obstruction in or around a body of water that allows the process of removing, diverting, or retaining
water in a confined area. The main purpose of any cofferdam type is to hold excessive or inconvenient water and
create a dry work environment. This allows the project to proceed with less resistance and as much safety as
possible.
5.Bridge foundation :- The bridge foundation is the foundation of the bridge that transmits loads from
piers, abutments and wings to the support level. It should be deep enough so as not to affect the acidity of the
river.
Types of foundation:-
1.Spread Foundation – Spread foundation is also called open foundation. The foundation of a normal height
bridge based on strong and dry ground is reasonable to help with the construction. This type of foundation is
suitable where there is minimal rubbing and the rough ground starts from 1.5m - 3m below the water level.
2.Raft Foundation - These types of bridge foundation are generally utilized where there passable bearing limit
of thesoil is less and the watercourse bed contains delicate clay and silt. It favors foundations where hard soil
isn’t found inside sensible profundity of 1.5m – 2.5m, beneath the watercourse.
3.Pile Foundation Bridge – Pile foundations are a type of bridge foundation that is used in situations where
the soil is extremely fragile and the hard layer is not accessible with the proper intensity. It is also used to remove
river erosion and to lift a huge concentrated load by the foundation.
4.Well Foundation Bridge –Bridge well foundation is a type of bridge foundation that is used when there is
sandy soil on the bed, hard soil 3-4 meters below the water flow level. Cotton with fragile soils is most suitable
for soils, depending on sandy soils and heavy erosion due to the rapid flow of the river.
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[3]
e-ISSN: 2582-
5208
International Research Journal of Modernization in Engineering Technology and
Science
( Peer-Reviewed, Open Access, Fully Refereed International Journal )
Volume:04/Issue:05/May-2022 Impact Factor- 6.752 www.irjmets.com
5.Caisson Bridge Foundation –The Caisson Foundation is a type of bridge foundation that is used in areas with
a hard layer near the river bed and there is a huge amount of water that is not economically strong.Remove strong
sinking wells for well feet.
6.Grillage Foundation –A foundation consisting of teams of one, two or more layers (usually steel) One layer of
concrete has a grillage foundation to spread the load over a wide area. It is used at the bottom of columns. This
type of foundation is commonly used for columns of heavy structures and for scatolda. This type of bridge
foundation is suitable for heavy and split feet of ghats where D (CI) ions should be avoided. Grillage foundation
is most suitable if the soil condition is bad.
7.Inverted Arc Foundation -This type of bridge foundation is suitable when the intensity of finding the
foundation is low. Inverted foundations are most suitable where soil holding limits are low. Especially when the
subsoil has some fragile pockets and the possibility of inconsistent settlement.
• Accurate layout of the center line of the bridge with the help of total station and marking the
location of the ghat.
• Reference survey points will be established away from the area of blowup or away from potential
colonial area as a result of well sinking.
• Such reference points will be permanently connected with the bank's baseline
• the distance should be checked by accurate tape and accurate distomat
• First of all, internal formwork shall be erected and joined to form the proper shape as perdrawing.
• Providing and fixing of horizontal and diagonal supports.
• Shuttering should be cleaned, and standard form releasing agent(shuttering oil) applied.
• Seal the shutter joints using foam sheets to make leakproof.
Reinforcement Fixing:
• The entire floor area should be properly cleaned before fixing outer formwork.
• Formwork shall be fixed as per approved drawing.
• Shuttering shall be cleaned, and standard form releasing agent applied.
• Seal the shutter joints using foam sheets to make leakproof.
• Fix coil anchors at appropriate locations for the erection of shutter for next lift.
• Outer formwork is supported by encompassing the circumference by wire rope tightenedwith the
turnbuckle.
• The inner and outer shutter should be connected by lateral bracing
• Grounding of well curb is the process for transferring the load from Wooden sleeper to the ground
truly concentrically and vertically without tilt or shift. Successfully groundingis crucial for further
activities of construction of well foundation.
• After grounding of well curb and its initial sinking, the well is built up by constructingsteining in
stages/lifts and subsequent sinking of the same.
• The height of steining is 2.0m for 1st lift and thereafter 2.0 to 2.5m, and number of liftsshould be
minimum to avoid construction joint.
• The chances of tilting increase if the well is made top-heavy by raising the steining toohigh in the
first stance.
• The steining shall be built in one straight line from bottom to top such that if the well istitled, the
next lift of steining will be aligned in the direction of the tilt.
• Straightness check shall be with the aid of an approved length of straight edges
• Plumb bob or spirit level shall never be used for alignment
Before the erection of shutter for next lift damaged portions if any, of steining top of theprevious lift shall be
properly repaired.
9. Well Sinking
• The sinking of well is done by two methods open sinking of wells (Most commonly usedmethod in
India) and Pneumatic sinking (Used rarely when open sinking does not help due to hard strata)
• The sinking operation involves lowering of well by dredging in the dredge hole.
• Plate grab is used in soft strata like sandy silt, soft clay, sandy clay, dense sand etc.
• In hard/stiff clay strata heavy-duty chisel used, followed by dredging by tyne grab.
• Levels and alignment (tilt and shift) of well shall be checked regularly at every 0.5m of sinking.
• Sinking operation shall preferably be non-stop under skilled supervision.
• Dredged materials shall not be heaved on one side of well to avoid tilt and shift. tion of Well
Foundation - Well SinkingThe above cycle of well steining and sinking shall be repeated up to the last
lift of the well until well reaches to the founding level.
10. Seating of Foundation Well:-
• The well shall be uniformly seated on the founding strata.
• It shall be ensured that the soil strata encountered at the founding level and up to a depthof one and
a half times the foundation well diameter, is uniform and identical to that adopted in the design.
• In case the well is in hard steeply slopes rocky strata, pneumatic methods of sinking maybe adopted
to seat the well evenly.
• Suitable sump (preferably D/6) shall be provided.
• In sandy strata, light blasting may be done for consolidating the soil, and loose materialsshall be
dredged out thereafter.
• The final level of Cutting edge and sump shall be jointly recorded.
11. Bottom Plug:-
• Bottom plug concreting will be done by “Tremie Method” or Skip box method.
• The top-level of bottom plug shall be kept minimum 300 mm above the top of the wellcurb.
• Concrete shall be poured without interruption up to the required level as per drawing.
• The concrete mix used in the bottom plug shall have a minimum cement content of 330 kg per cum
with a slump of about 150 mm or specified in the design.
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[6]
e-ISSN: 2582-
5208
International Research Journal of Modernization in Engineering Technology and
Science
( Peer-Reviewed, Open Access, Fully Refereed International Journal )
Volume:04/Issue:05/May-2022 Impact Factor- 6.752 www.irjmets.com
• The soundness of the bottom plug should be checked by dewatering the well after sevendays to a
level 5.0m below the surrounding water level and checking the rise of water, which should not be
greater than 10 cm per hr.
12. Sand filling:
3D Drawing of model :-
Preparing Model :- ``
VII. CONCLUSION
After study of the underwater bridge construction, we get to know that there are many type of structure we
needed before the bridge construction such as cofferdam, cassion and well foundation. Cofferdam are
temporary structure and uses in case where the plane area of foundationin very large, depth of water is less
and the soil is soft. We also study the various component partsof bridge and detail study of the temporary
structures. Further we will prepare a miniature modelof underwater construction of bridge.
VIII. REFERENCES
1. IJTE special issue for ICRISET 2017
2. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684, p-ISSN: 2320-334
3. .International Journal of Scientific Research and Review Volume 7, Issue 5, 2018 ISSN NO:2279-543X
4. International Conference on: “Engineering: Issues, opportunities and Challenges forDevelopment”
ISBN: 978-81-929339-1-7
5. Hindawi Publishing Corporation Journal of Construction Engineering Volume 2013, ArticleID 874180
6. Proceedings of the 1st International Conference on Concrete Technology, Tabriz, Iran,
7 November 2009
7. .© 2021, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal
8. ARADHANA (1BI16CV020)
9. Wiwatanapataphee et al. Advances in Difference Equations (2019) 2019:225
10. 16th feb 2018,www.conferenceworld.in ISBN:978- 93-87793-00-2