Professional Documents
Culture Documents
Primavera Exercise Book Sample
Primavera Exercise Book Sample
Create a new calendar with six workdays and give Monday holiday in the your calendar. Find whether the
changes are affected in the new calendar. Also change the shift time to 7 AM to 5PM. If changes are affected in
the new calendar, save the calendar.
Create a new calendar with five workdays and apply it to a task and find how the task in scheduled, while the
project calendar being 7 days workweek.
Create a new calendar with planning units in hours. Give 10hr/day as working time and 1 hr break in between. The
working time start from 8 AM ands at 7 PM.
Create a night calendar, in which the planning units are in weeks. The shift starting from 10 PM to7 AM having 1hr
break at 2AM to 3AM. Find whether it is possible to give the holidays in days.
Create a night calendar in which shift starting from 11 PM to8 AM having 1hr break at 2AM to 3 AM. Make 2nd
Saturday as holiday and 15th August and 30th August as holiday. The project starts from 14th July2007.
Create a new hourly based calendar with timings from 6AM to 5PM with 1 hr break in between and six workdays
per week. Give holidays for the following days 26th January, 1st May, 15th August, 2nd October, 14th November
and 25th December.
Create a calendar with two shifts. The major shift is from 7AM to 3PM break in between is 1hr from 11AM. Give the
start date of the project as 01 April,.2006. Add five activities and assign the different two calendars to any two
activities and find how the tasks work after assigning.
Create a calendar, having 24 hrs working with 5 activities. 2 activities are for working starting from 12AM to12AM.
Find whether it is possible to give the holidays.
. . .
TRAINIING PLACEMENT SOFTWARE CONSULTANCY
PRACTICE 4- CRITICAL PATH ANALYSIS
Find the critical path for the problem by giving the relationship as shown below. The duration is given in days. 26th,
May 1st, Aug 15th and Oct 2nd are holidays. Find the details in the form of PERT chart select A007 and check the
relationship.
. . .
TRAINIING PLACEMENT SOFTWARE CONSULTANCY
Resource Assignment
The following list shows the application of resources for each activity
DE FE SE EE PR SU SX DF OA SK FW F
TD/1 1 - - - - - - 2 - - - -
TD/2 1 - - - - - - 2 - - - -
TD/3 - - - - - - - 1 - - -
TD/4 1 - - - - - - 1 - - - -
PP/1 - - - - - - - 1 - - - -
PD/1 - - - - - - - 1 - - - -
PD/2 - - - - - - - 1 - - - -
FN/1 - - - - - - - 1 - - - -
FN/2 - - - - - - - 1 - - - -
FN/3 - - - - - - - 1 - - - -
FN/4 - 1 - - - - - - - 3 -
FN/5 - 1 - - - - - - - - 3 -
ST/1 1 - - - - - - - 1 - - -
ST/2 - - - - - - - 2 - - - -
ST/3 - - - - 1 - 1 - - 1 - -
ST/4 - 1 - - - - - - - - - -
ST/5 - - - - 1 1 - - - - -
ST/6 - - - 1 - 2 - - - - - 3
CR/1 1 - - - - - - - 1 - - -
CR/2 - - - - - - - 1 - - - -
CR/3 - - - - - - 1 - - - - -
CR/4 - - - - 1 - 1 - 1 - - -
CR/5 - - - - 1 - - - - 1 - -
CR/6 - 1 - - - - - - - - - 2
CR/7 - - - - - - 1 - 1 - - -
CR/8 - - - 1 - 1 - - - - - -
CR/9 - - - - - - - 1 - - - -
CR/10 - - - - 1 - 1 - - - - -
CR/11 - 1 - - - - - - - - - -
CR/12 - - - - - - 1 - 1 - - -
CR/13 - - - 1 - 1 - - - - - -
CR/14 - - - - - - - 2 - - - -
CR/15 - - - - - - 1 - - - - -
CR/16 - - - - 1 - 1 - 1 - - -
CR/17 - 1 - - - - - - - - - -
CR/18 - 1 - - - - - - - - - 2
CR/19 1 1 - - - 1 - - - - - 3
CR/20 - - - - 1 - - - 1 1 - -
CR/21 - - - 1 - - - - - - - 3
The activities for the fabrication and erection of a telephonic tower (comprises of Mechanical, Civil and Electrical
works) are given below with the WBS. The duration for each activity is given below. Draw the network diagram and
find the project completion date. The start date of the project is 01/10/2003. The activity details are listed below.
The duration is in hours and the calendar that is followed is six-day calendar.
Soll investigation
1 Site survey 12 a
2 Identify vendor for soil investigation 10 1 SS
3 Begin soil investigation 10 1 SS
4 locate bore holes 10 1 SS
5 Drill bore 1 5 2, 4
6 Drill bore 2 5 5
7 Fax result HQ 1 6
8 Prepare soil investigation reports 10 7
9 Determine SBC 10 8
10 Soil investigation complete` 0 9 FF
Design
11 Design Foundation 20 9
12 Begin Design 0 11 SS
13 Design tower 20 11 SS+10H
14 Design fasteners 10 13 SS
15 Prepare substructure drawings 40 11
16 Prepare supersturcture drawings 40 13
17 Prepare method statements 50 15 FS-8H, 16 FS-8H
18 Design complete 0 17 FF
Fabrication
19 Begin fabrication 0 16 SS
20 Procure Gl fasteners 20 14
21 Procure Structural steel 30 15, 16
22 Bottom segments 10 17 FS-10H, 21
23 Drill holes in elements 20 17 FS-10H
24 Drill holes in connecting plates gussets 20 17 FS-10H
25 Other segments 50 22
26 Connecting Plate segments 20` 17 FS-10H
27 Foundation template 10 26 SS
. . .
TRAINIING PLACEMENT SOFTWARE CONSULTANCY