Energization Plan MV - Employer Office
Energization Plan MV - Employer Office
‐ Expansion Project
Employer Office Energization Plan MV NETWORK
10:00:00 AM
11:00:00 AM
10:00:00 AM
11:00:00 AM
12:00:00 PM
12:00:00 PM
5:00:00 AM
6:00:00 AM
7:00:00 AM
8:00:00 AM
9:00:00 AM
8:00:00 AM
9:00:00 AM
8:00:00 AM
1:00:00 PM
2:00:00 PM
3:00:00 PM
4:00:00 PM
5:00:00 PM
6:00:00 PM
1:00:00 PM
2:00:00 PM
3:00:00 PM
4:00:00 PM
5:00:00 PM
24 Hours
Sl. No. Activity description Remarks
Shutdown for MV Cable Cable Between C5700
1 By LINK
and E1200
2 Switching off M2 in MSG‐C5700‐001 By LINK
3 Switching off M1 in LVS‐E1200‐001 By LINK
4 MV Cable Identification UBT/JV ‐ QPC
5 Cable spiking UBT/JV ‐ QPC
6 Cable cutting and Jointing UBT/JV ‐ QPC
7 Cable testing UBT/JV ‐ QPC
8 End to End Test UBT/JV ‐ DE
9 Soak and Phasing Verfication Test By LINK
10 C2410 ‐ Energization (MV Busbar) By LINK
1/1