Project Updates
Project Updates
Project Updates
PLANT 3
- i-uupdate na ung mga asbuilt plans/ nagawa narin ung mga Punchlists
*Exhaust Platform
*Cooling Tower
- July 10, 2022 Opening for Shutdown Works (Pipe Leak & Blade Balancing)
- Scheduling of Zone 3 Area will be coordinated to Gab (Target this Week Partial
Mobilization/Execution)
PLANT 1
*Front Bldg. Painting Works
- Additional Painting Works - Still Routing on Managers; budget subject on approval as per Norman
- Wala pang balita sa approval ng schedule ng Installation of Booster Fan & Exhaust
- FRP Ducting (napinturahan na) ; Subject for actual inspection for duct fabrication & lay-out
- Preparation of Load Analysis and Structure Design for the Exhaust Platform
- Target Setting of Condensing Unit (July 5, 2022) Atleast 3 Days Curing Time
- Installation of Canopy Type Roof & Enclosure - Target this week (pagkakapitan ng Control Panel kasi
ung enclosure)
*LED TV Support
- TV Bracket Design on Plant 1 - Wall Mounted Support with Swivel/ Tilt Up & Down Motion
Design already given to Kuya Jerry subject for modification & fabrication