FIRST SUMIDEN CIRCUITS INC.

FSCI -PLANT 3

*New 55KW Air Compressor Utilities

-for PTO (nasa FSCI pa ung Permits)

*Cold Jet Utilities

- PTI (nasatin na ung mga Permits subject for PTO)

- i-uupdate na ung mga asbuilt plans/ nagawa narin ung mga Punchlists

- wala pang balita sa filter cleaner/ dust collector system approval

*Exhaust Platform

- Done 7/7 platform

- Subject for FSCI Facilities & Safety Inspection

*Cooling Tower

- July 5, 2022 Inspection Date of CTSI Contractor

- July 10, 2022 Opening for Shutdown Works (Pipe Leak & Blade Balancing)

*ESI Chiller Exhaust Modification

- Zone 6 and 5 are Done

- Zone 1 (Target July 5, 2022)

- Platform for KRUGER Exhaust to modified this week

- Scheduling of Zone 3 Area will be coordinated to Gab (Target this Week Partial
Mobilization/Execution)

FSCI -PLANT 1
*Front Bldg. Painting Works

- Progress Billing 1 (40%) - Already given to James Construction c/o Dada

- Retention (10%) - will be issued once activity warranty approved by FSCI

- Additional Painting Works - Still Routing on Managers; budget subject on approval as per Norman

*Plating Lab Exhaust

- Wala pang balita sa approval ng schedule ng Installation of Booster Fan & Exhaust

- FRP Ducting (napinturahan na) ; Subject for actual inspection for duct fabrication & lay-out

Percentage of Fabrication c/o Agoy & Rodel

- Preparation of Load Analysis and Structure Design for the Exhaust Platform

*Cold Storage Unit Cooler/ Condensing Unit

- Construction of Concrete Footing & Base Support - Done

- Target Setting of Condensing Unit (July 5, 2022) Atleast 3 Days Curing Time

- Delivery of Unit Cooler c/o Boss Apo

- Installation of Canopy Type Roof & Enclosure - Target this week (pagkakapitan ng Control Panel kasi
ung enclosure)

*AHU 9 at Standard Area

- No updates on Methodology Approval

- subject for scheduling

*LED TV Support

- No updates on Methodology Approval

- TV Bracket Design on Plant 1 - Wall Mounted Support with Swivel/ Tilt Up & Down Motion

Design already given to Kuya Jerry subject for modification & fabrication

(Possible This Week)


Other Items ;

- Quotation for Bosch Audit Renovations - July 4, 2022

- Updates on Fabrication of Pulley of MAU ni Sir Jun Java - to be coordinated