Professional Documents
Culture Documents
Activity1 Final Term CE Laws
Activity1 Final Term CE Laws
CE LAWS
Probable total cost is a major concern of the client throughout the planning design, and construction
phases of a subject. The following compose this budget:
Study and Report. Analysis of client needs, evaluation of alternatives and recommendations of a
preferred option, conceptual design, opinions of probable project cost.
Preliminary Design. Preparation of final design criteria, preliminary drawings, outline
specification, and estimate of construction cost.
Final Design. Preparation of construction drawings, specification, estimates of probable
construction cost and other contract documents.
Bidding or Negotiation. Assistance to the client with the bidding or negotiating process for the
project if construction.
Construction and Operation. Representation of client during and inspection and construction of
project to the startup operation of the project including inspection.
Construction Cost. It is a part of the overall costs incurred during the development of a built
asset such as a building. However, the construction contract may include costs such as fees,
profits, overheads, etc. Contract sum can be adjusted. Cost plan is used to analyze the estimated
cost during the pre and post construction phases of the project. This would include initial cost
appraisals, elemental cost plans and approximate quantities cost plans, pre-tender estimates,
contract sum, final accounting
3. Contingency. To provide for intangible costs, contingencies should routinely be added to the
basic cost estimate. It is common practice to add 20%or more to the estimated probable total
project cost at the completion of the study end report phase, reducing this to perhaps 10% at
the completion of final design and perhaps to 5% when the construction bids become known.
Larger or more complex projects may require higher contingencies.