Professional Documents
Culture Documents
TEKTON TCX Test Forms
TEKTON TCX Test Forms
CORP.
TE CONNECTIVITY
MANUFACTURING PHILIPPINES
INC.
Tab Supervisor:
Approved By:
Date
PRELIMINARY CHECKS
System Cleanliness
Check
Check List Mark Remarks
5 Cooler batteries
7 Dampers
8 Ducting
10 Machine room
Check
Check List Remarks
Mark
On activating the motor starter check
Check
Check List Remarks
Mark
Check that the following are fitted and
1 not damaged:
Tuning vanes
Straigntening vanes
Themal insulation
Sensing elements
check that cooler batteries are installed
2 correctly in relation to air flow
check that filters are correctly installed
3 in relation to air flow
4 check that test holes for measurement
of air flow are provided
5 check that test holes are provided with
plugs
Mechanical Checks
1 External cleanliness
2 All components, bolts, fixings are
secured
LOCATION: POWER:
DATE:
LOCATION: POWER:
DATE:
DATE:
Centrifugal fan
Drain pan
State of System
PRELIMINARY CHECKS
FOR CHILLED WATER SYSTEM
Check that:
1 Probes, pockets, pressure gauges, orifice plates
and air vents are installed
2 Drains and overflows are connected and free
from blockage
3 Connections to cooler batteries are correct in
relation to the design water flow directions
4 Control and non return valves are installed the
right way round
5 Relief valve outlets are piped away to suitable
drain points
6 Strainer mesh is of the correct grade and
material
7 Tanks are cleaned
8 Drain valves are closed and other valves left
open or closed according to the plant for filling
9 Pipe work and fittings are adequately supported
Mark
1 That the direction and speed of
rotation of the motor shaft are
correct
2 That the motor, pump and drive are
free from vibration and undue noise
3 The motor starting correct for
sequence timing adjustment
4 The motor running current on all
phases to ensure that they are
balanced between phases
5 That there is no sparking at the
commutator or slip ring
6 That there is no overheating of the
motor
7 That there is no seepage of lubricant
from the housing
8 That there is no over heating of the
bearings
9 That the water flow to water cooled
bearings is sufficient
PRELIMINARY CHECKS
System Cleanliness
4 Sensing elements
5 Compressor
Mechanical Checks
Test Report
REF. NO.:
Voltage
KW input
REF. NO.:
LOCATION: CAPACITY:
REF. NO.:
LOCATION:
DESIGN OUTPUT
CAPACITY:
Test Report
REF. NO.:
LOCATION: RATING:
Primary Water:
Entering water pressure
Leaving water pressure
DELTA P
Entering water temp.
Leaving water temp.
DELTA T
Flow rate
Secondary Water:
Entering water pressure
Leaving water pressure
DELTA P
Entering water temp.
Leaving water temp.
DELTA T
Flow rate
Test Report
REF. NO.:
LOCATION:
Evaporator:
Measure motor current (each phase)
Measure motor voltage
Measure duct inlet / outlet S.P
Measure fan RPM
Measure F.A flow rate
Measure R.A flow rate
Measure total air flow rate
Measure outlet air velocity
No. of fins & spacing
Coil face area
Measure coil face velocity
Measure DELTA T across the coil
Drain fan
REF. NO.:
LOCATION:
Gauge glass
Combination of pressure
regulator & relief valve
Pressure gauge
Check valve
REF. NO.:
LOCATION:
LOCATION:
LOCATION:
Location of Metering Type Metering Size of Metering Design Design Test Result
Station Station Station Flow ∆P
Initial Final
Valve
∆P Flow % Design ∆P Flow % Design
Position
(CONSTANT VOLUME)
SYSTEM NO.:
AREA SERVED:
NO. SIZE FACTOR DESIGN DESIGN TEST TEST TEST ACTUAL ACTUAL REMARKS
C.F.M VEL. OR NO. 1 NO. 2 NO. 3 FINAL FINAL &
S.P. VEL. VEL. VEL. VEL. OR C.F.M % OF
OR S.P. OR S.P. OR S.P. S.P. DESIGN
TOTAL:
DATE:
Test Report
TYPE/REF.:
TYPE/REF.:
MOTOR SPEED
HP/KW:
MOTOR: (OVERLOAD
SETTING)
TOTAL VOL.
STATIC PRESSURE:
BEFORE FAN:
FAN MEASURED DUTY
AFTER FAN: