Professional Documents
Culture Documents
1x660 MW Sagardighi TPS, Unit 5 BFP Sizing Calculation (PE DC 445 100 N112)
1x660 MW Sagardighi TPS, Unit 5 BFP Sizing Calculation (PE DC 445 100 N112)
1x660 MW Sagardighi TPS, Unit 5 BFP Sizing Calculation (PE DC 445 100 N112)
MW Sagardighi TPS, Unit‐5
BFP Sizing Calculation (PE‐DC‐445‐100‐N112)
Sl. No. Customer's Comment BHEL Reply WBPDCL/DCPL Reply BHEL Reply (dated 06.10.20) WBPDCL/DCPL Reply (21.10.20) BHEL Reply (dated 02.11.20)
1 Please clarify how "as per case" values are Case values are determined after adding Noted.
determined margins as mentioned in the case description Point Closed
2 Not available in HBD. Extraction line pressure Deaerator pressure is saturaion presuure of the Noted.
only available. feedwater coming out of the deaerator Point Closed
3 Not indicated in HBD Boiler Terminal Point Pressure are taken as per Noted.
BHEL Trichy (SG maufacturer) inputs which are
internal to BHEL.We confirm the inputs are in
order. Point Closed
4 Can only be reviewed upon receipt of all Details provided are in order. After receipt of GADs, if any correction is
relevant GADs needed , BHEL shall incorporate the same. Confirmed
5 Please add the following condition as case‐VI: BMCR flow is considered for underfrequency Noted.
VWO output, 1% make‐up, worst condenser case inline with specification (amendments)
pressure (MDBFP should meet the requirement requirement and the same is in order.
at 47.5 Hz).
Point Closed
6 Please confirm that discharge flow is exclusive Confirmed Noted.
of seal flow, warm‐up flow & balance drum
leakage flow. Point Closed
7 Inter‐stage bleed‐off for RH attemperation shall RH attemperation flows are to be considered as Please consider design value of 130.4 TPH
be minimum 8% of max. reheat steam flow per SG manufacturer's (BHEL Trichy) for inter‐stage RH attemperation as per
rate. recommendation and the same is in order. sl.no. 7 of calculation.
As discussed during virtual meeting
dtd. 21.10.20, please consider max.
Considered inline with our SG quantity of RH attempearation flow
manufacturer's recommendadtion from BFP inter‐stage considering all
and practice followed for all operating condition and different fuel Noted and revised inline with the
sub/super critical projects. firing. discussion.
8 Please confirm that the pressure corresponds In case III. Pressure corresponding to lowest Noted.
to lowest safety valve set pressure of steam safety valve pressure at superheater outlet is
separator considered, inline with the specification
requirement. Point Closed
9 Pressure drop to be calculated based on "as per Pressure drop shall be calculated on actual As per sl. no. 1.0 c)iii) of annexure‐I, sec‐III, BHEL confirmed during virtual
case" flow values values as per HBDs. 10% margin in piping vol. IIC, 10% margin over total pressure meeting dtd. 21.10.20 that density
pressure drop as per spec is already provided. drop (except static height & terminal difference in feed water with increase
pressure requirement) to be considered. Piping pressure drop is already in temp. through HP heaters have
Hence, consider 10% margin on drop considered and the same is in been duly considered in pressure
through heaters and other equipment. order. Margin in equipment drop calculation. BHEL shall furnish a
pressure drop shall not be specimen calculation to show the
considered. same. Noted and attached.
10 Additional 10% margin to be considered on Piping pressure drop margin is already Please exlain why pressure drop figures
frictional drop on both suction and discharge considered during sizing calculation. Same will through heaters and piping reduced from As feed water system engineering still
side. be mentioned suitably. previous submission. Latest inputs received by different not frozen, BHEL shall confirm that
units and departments has been pressure drop figures considered in
updated in the document. calculation shall not exceed later. Confirmed.
11 Inter‐stage bleed‐off for RH attemperation shall refer reply to point no7 Please consider design value 130.4 TPH for refer reply to point no7
be minimum 8% of max. reheat steam flow inter‐stage RH attemperation as per sl.no.
rate. 7 of calculation. Refer reply above. Refer reply above at point no 7
12 Not considered in calculation. This is for interstage design, actual requirement As actual requirement is 24.8 TPH only, It is to meet specification
shall be considered for RH attemperation flow please explain why design value is requirements.
inline with standard practice followed for our consiered as 130.4 TPH.
all projects. Refer reply above. Refer reply above at point no 7
13 Please include HP‐LP bypass condition with
one TDBFP running as case VI. As per cl. No. 1.01.03 of sec‐III, vol‐
IIC, BFP shall be adequately designed
for by‐pass condition, hence this case
is to be included and shown that
selected pump will be capacble of
stable operation at this point. As per
HBD no. S‐0226, two BFPs are
Pumps selection is in order and as working at HP‐LP bypass condition,
per specification requirement. please include this case accordingly. Noted and incorporated
14 Why 2076.70 m3/hr is not considered for Steam flow is mentioned only. For
BMCR 1% MU, as per HBD S0230 ? Pump Calculation feed flow of
2076.7 T/hr is considered only ,
refer case IV. Noted. Point Closed
16 Shall be calculated at 2054.48 TPH flow
Pressure drops are calculated at
2029.68 only and then
recalculated for different flow as
per HBDs. Calculation is in order. Noted. Point Closed
18 These figures do not match. Please explain Unit is different
Please refer reply above for sl. No. 9. Refer reply above at point no 9
Kindly clarify how the MDBFP rating is met Underfrequency case considered Noted.
following clause No. 1.0 (d) of Annexure‐I in case IV of sizing calculation.
of V‐IIC/S‐III MDBFP parameters selected are
inline with spec requirements of
mentioned clause.
Point Closed
As per cl.no. 4.01.06 of sec‐III, vol‐IIC,
vendor to ensure that NPSH (A) at
design point with lowest deaerator
level and maximum pressure drop
across the strainer shall be at least
2.5 times the NPSH (R) at 3% head BHEL checked and confirms to meet
drop for booster pump as well as the mentioned specification
main pump. requirement of NPSH(A)
BOILER FEED PUMP SIZING CALCULATION DOC NO.: PE-DC-445-100-N112
BHEL
PEM
PROJECT TITLE : WBPDCL - SAGARDIGHI TPP, PHASE III, 1X660 MW SHEET NO.: 2 OF 5
DISCH. DISCH.
SUCTION SUCTION DEAERATOR BOILER TP
FLOW (T/Hr) FLOW SUCTION
DESCRIPTION FLOW (T/Hr) FLOW (T/Hr) PRESSURE PRESS
(AS PER (T/Hr) (AS TEMPERATURE ( oC)
(AS PER HBD) (AS PER CASE) (kg/cm2a) (kg/cm2a)
HBD) PER CASE)
03
CASE-II : BEST EFFICIENCY POINT
CORRESPONDING TO TMCR, 0% MU UNDER 1872.47 1872.47 1872.47 1872.47 11.95 316.2 186.9
RATED CONDITIONS. Ref HBD No. S0201 03
02
03
BOILER INPUTS
In the last submission of Heat Balance Diagram, BHEL has not indicated the HP heater drip
to Deaerator (K). In their reply BHEL PEM has stated that ' it shall be added in the next
revision'. Therefore unless the HBD is approved this document will be under CAT (2)
approval catagory.
BOILER FEED PUMP SIZING CALCULATION DOC NO.: PE-DC-445-100-N112
BHEL
PEM
PROJECT TITLE : WBPDCL - SAGARDIGHI TPP, PHASE III, 1X660 MW SHEET NO.: 3 OF 5
RESULT SHEET
FLOW CALCULATION
FLOW THRO' EACH PUMP AT DISCH. FLANGE T/hr 1116.32 936.24 1014.84
HEAD CALCULATION
PARAMETERS CALCULATED :
3
FLOW PER PUMP (m /hr) 1299.9 1064.6 1171.0
HEAD (MLC) 3637.8 3542.2 3897.6
FLOW CALCULATION
CASE-IV(A) CASE-IV(B)
PARAMETERS CASE-V CASE-VI
(TDBFP) (MDBFP)
SUCTION FLOW (AS PER HBD) T/hr 2076.70 2076.70 1166.67 1430.09
SUCTION FLOW (AS PER CASE) T/hr 2076.70 2186.00 1166.67 1430.09
DISCHARGE FLOW (AS PER HBD) T/hr 2076.70 2076.70 1166.67 1430.09
DISCHARGE FLOW (AS PER CASE) T/hr 2076.70 2186.00 1166.67 1430.09
SUCTION FLOW THROUGH EACH PUMP T/hr 1038.35 1093.00 1166.67 715.05
DISCH. FLOW THROUGH EACH PUMP T/hr 1038.35 1093.00 1166.67 715.05
FLOW THRO' EACH PUMP AT DISCH. FLANGE T/hr 1038.35 1093.00 1166.67 715.05
HEAD CALCULATION
2
DISCHARGE PRESSURE (kg/cm )
BOILER TP PR. 325.0 325.0 201.4 293.3
PRESSURE DROP IN DISCH. PIPING, FLOW ELEMENT ET 4.71 4.71 1.49 2.23
PARAMETERS CALCULATED :
3
FLOW PER PUMP (m /hr) 1182.1 1244.4 1302.0 770.7
HEAD (MLC) 3659.8 4055.2 2178.3 3162.4
5.0 Pressure drop across suction strainer 03 0.15 kg/cm2 maximum with choked condition
7.0 Rated discharge flow through interstage bleed off from feed pump for reheater attemperation shall not be less than
130.4 T/Hr (combined flow from two pumps). Min. RH Spray line pressure at Block valve shall not be less than 115
Kg/cm2(g) at BMCR flow. At best efficiency point, interstage bleed discharge to be considered as closed.
%)33UHVVXUH'URS&DOFXODWLRQV 6$*$',*+,;0: $QQH[XUH
Operating Flow Outer Thickness Specific Velocity Length Elbows Reducer Gate Valve NRV
SL. No. Line Description Pressure Temp ( T/Hr ) dia. (mm) (mm) volume (m3/kg) ( m/s ) (m) Pres. Drop 90o 45o Pres. Drop No. of Large Small Length Pres. Drop No. of Pres. Drop No. of Pres. Total Pres. Drop
(Kg/cm2) (oC) (kg/cm2) (kg/cm2) Dia. Dia. (mm) (kg/cm2) (kg/cm2) Drop (kg/cm2)
(mm) (mm) (kg/c
m2)
TD BFP INDIVIDUAL DISCRAGE 332.76 195.1 1014.84 457 82 0.001121428 4.69 28 0.1309 6 1 0.1276 1 450 350 450 0.0095 1 0.0108 1 0.07 0.3465
HEADER TO HPH -7A 331.6 195.1 1014.84 368 50 0.001122 5.60 15 0.1081 4 1 0.1305 2 450 350 450 0.0272 1 0.0157 0.2816
HPH 7A TO 8A 331.31 226.9 1014.84 368 50 0.001167 5.83 59 0.4494 9 1 0.2792 2 450 350 450 0.0283 0.7570
HPH 8A TO 9A 330.56 280.5 1014.84 406.4 60 0.001273 5.57 13 0.0758 4 1 0.1121 1 450 350 450 0.0118 0.2150
HPH 9A TO 7A DESUPERHEATER FULL FLOW 330.34 306.6 1014.84 406.4 60 0.001346 5.89 11 0.0686 6 0.1501 1 450 350 450 0.0125 0.2670
HPH 9A TO 7A DESUPERHEATER 40% FLOW 330.07 307.6 405.936 273 40 0.001349 5.20 7 0.0511 2 0.0422 1 450 350 450 0.0097 0.1633
7A DESUPERHEATER TO HEADER 40 % FLOW 330.34 310 405.936 273 40 0.001357 5.23 11 0.0822 4 0.0849 1 450 350 450 0.0098 0.1768
7A DESUPERHEATER TO HEADER 330.07 310 1014.84 406.4 60 0.001357 5.94 21 0.1314 6 0.1513 2 450 350 450 0.0253 1 0.0144 0.3584
HEADER TO ECONOMISER INLET 329.91 310 2029.68 559 77 0.001357 5.94 48 0.1973 4 2 0.1290 0.4945
(Terminal point with boiler manufacturer)
3.8784
%)3'LVFKDUJH/LQH
3.88
7RWDOSUHVVXUHGURSLQGLVFKDUJHOLQH
0.20
3UHVVXUHGURSLQIORZHOHPHQW
4.08
7RWDO%)3GLVFKDUJHGURS
4.50
6HOHFWHGSUHVVXUHGURS NJFP