Development of The Logistics Plans in Building Construction: September 2003

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/275345704

Development of the logistics plans in building construction

Conference Paper · September 2003

CITATIONS READS

7 11,222

2 authors:

Sheyla Mara Baptista Serra Otávio José de Oliveira


Universidade Federal de São Carlos São Paulo State University (UNESP)
82 PUBLICATIONS   136 CITATIONS    164 PUBLICATIONS   1,657 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Incorporação de Resíduos de Carvão Vegetal em Argamassas Cimentícias View project

Education, Entrepreneurship and Entrepreneurial Education View project

All content following this page was uploaded by Sheyla Mara Baptista Serra on 23 April 2015.

The user has requested enhancement of the downloaded file.


Development of the Logistics Plans in Building Construction
S. M. B. Serra
Professor Doctoress of Civil Engineering Department of São Carlos Federal University, São Carlos, SP,
Brazil
O. J. Oliveira
Doctor Student of Civil Construction Program of São Paulo University, Professor of São Judas University,
São Paulo, SP, Brazil

ABSTRACT: The main objective is to present a tool for the development and implementation of logistics
plans in building construction. Firstly it shows a review of related concepts. These are followed by a study of
the relationship of the logistic plan with the elements that conditions its success. These are considered as main
requirements for correct plan formulation, such as: simultaneity among external logistics (control of
suppliers) and internal logistics (construction site management). In conclusion, this paper present the
guidelines for formulation and implantation of logistics plans that will aid in the operational planning of the
work, programming of the deliveries of materials and improvement in the conditions of the work. Application
of the logistics guidelines cited is directly dependent on a change in the culture and structure of construction
companies, which must perforce begin to use lean thinking to guide decisions and to execute activities in
every organizational level, with special emphasis on top management.

1 INTRODUCTION the implementation of new technical and managerial


tools.
The new production philosophy (lean production)
According to Vrijhoef; Koskela (1999), the
sees the productive system as a group of
supply chain has been defined as the network of
interconnected and interdependent conversions and
organizations that are involved, through upstream
flow activities that should, ideally, encompass
and downstream linkages, in the different processes
broader concerns than a mere analysis of the
and activities that produce value in the form of
productive process alone. The growing awareness of
products and services in the hands of the ultimate
the importance of improving the flow of materials
customer. The traditional way of managing is
and information has given rise to the emergence of a
essentially based on a conversion view (or
new production paradigm that is generating
transformation view) on production, whereas supply
auspicious results.
chain management (SCM) is based on a flow view
Seen from the standpoint of lean production,
of production. Koskela (1998) mentions that the
innumerable criticisms can be made of the
conversion view suggests that each stage of
traditional production model, which, by focusing
production is controlled independently, whereas the
solely on conversions, neglects the physical flow
flow view focuses the control of the total flow of the
occurring between them, that is, the activities of
production.
transportation, storage and inspection. Because they
Thus, the optimal construction site management
add no value to the final product and are consumed
requires the identification of all the agents present
time and expensive, these activities should be
on the site. Each phase of the construction involves a
eliminated or reduced to a minimum.
variety of suppliers and subcontractors who
Now that the concept of lean production has
contribute to the production with a multiplicity of
matured and it was implemented by the
materials and services. Other agents in the
manufacturing industry, it has finally begun to
productive chain also participate in the construction
arouse the interest of civil construction managers,
process. Edum-Fotwe et al. (2001) presents
originating what can be dubbed lean construction.
examples of different actors that participate in some
Nonetheless, the application of this philosophy in
of the phases of the supply chain. During the
the construction sector still requires experimentation
construction the most important agents are: main
and research aimed at adapting it to the sector’s
contractor, subcontractors, project manager, material
particularities, which are usually factors that hinder
suppliers, equipment suppliers, designers, financial
institution, insurance agency and regulatory bodies.
2 LOGISTICS IN THE BUILDING production. Among the most important activities are
CONSTRUCTION planning and processing of purchased items, supplier
management, transportation of resources to the site,
Construction logistics is a multidisciplinary process
and maintenance of the material resources foreseen
applied to a given construction to ensure the supply,
in the planning.
storage, processing and availability of material
Wegelius-Lehtonen (2001) presents two tools
resources on the construction site, to dimension the
developed to measure the improvement potential of
production teams and to manage the physical flows
deliveries process. The tools measure costs and time
of production. Silva & Cardoso (1998) state that the
of delivery chains. The first step is to identify all the
main support of this process, which occurs through
activities from the supplier’s production line to the
planning, organization, management and control
final assembly of product on construction site. The
activities, is the flow of information prior to and
second step is to calculate costs of each activity and
during the productive process.
finally to present the results in an informative way.
Cardoso (1996) presents a subdivision for
The detailed division of logistics costs both on
logistics applicable to construction companies,
the construction site and at the supplier’s is present
classifying it, in terms of scope, as supply logistics
in Figure 1. The example illustrates how the activity
(external) and on-site logistics (internal). This
and cost analysis results can be used on specific
subdivision allows for a clearer identification of the
material supplier level as a basis for improvement.
main activities associated with construction site
In this case example, construction firm and
logistics.
plasterboard supplier wanted to develop their
material deliveries together.
2.1 Supply Logistics
Supply logistics involves provision of the material
and human resources required for the building

supplier construction site


75% 43%
21% 21%
9% 16% 10%
5%

Transportation Storage Loading Unloading Storage Transportati Transportati Transportation


by forklift by crane on by crane on by hand by wheelbarrow

Figure 1 – Division of the logistics costs in the plasterboard deliveries (Wegelius-Lehtonen, 2001)

According to Wegelius-Lehtonen (2001), the are: management of the physical flows involved in
standard materials, like timber, mortar and the execution (detailed planning of the service flow
plasterboard, have the biggest logistics costs of and its control mechanisms), interface management
material flows as percentage of the purchasing price, between agents interacting in the construction
because the logistics chain of standard materials process (information and interposition among the
consist of many movements and warehousing. The services), and physical management of the
accuracy and delivery time analysis is most useful in construction site (establishment of the site, internal
the development of customized material deliveries, movements, storage and prefabrication areas, and
like windows, concrete elements and kitchen work safety requirements).
cabinets. With the accuracy and delivery time
analysis, the improvement potential in information
flows and co-ordination can be identified. 3 THE LOGISTICS APPROACH DURING THE
DESIGN PHASE
2.2 On-Site Logistics Novaes (1998) highlights two design concepts:
static – which refers to the design as a product
On-site logistics involves the management of the constituted of graphic and descriptive elements,
physical flows and information flows associated ordered and elaborated according to an appropriate
with on-site activities, the most important activities language and with main objective to reach the
requirements of the production phase, and dynamic The “on-site design is an integral part of the
– which gives the design a sense of process through construction process, responsible for defining the
which solutions are identified and adapted, assuming size, shape and location of both permanent and
a technological and managerial character temporary work areas and the circulation routes
(production design). This latter concept (dynamic needed to develop the operations of support and
design) is the focus of our attention here, owing to execution during each phase of construction work,
its direct relation with the logistics activity in the in an integrated and evolutive manner and in line
construction site. From the beginning the concept of with the enterprise’s production design, offering
the design should include the building production specific conditions for the workers’ safety, health
with the integrated operation of all its constituents. and motivation, and for the rational execution of the
services” (Ferreira, 1998).
The Systematic Layout Planning method (SLP)
3.1 Production Design is a systematization tool for physical arrangement
During the phase of construction work, the design’s designs. According to Muther & Wheeler (2000),
performance is largely dependent of the production layout planning involves three essential conditions:
team’s interpretation and of the communication level the relations between the different functions or
used. A design that foresees good constructive activities in the environment, the amount and type of
techniques is useless if those techniques are not space for each activity, and the adjustment of these
conveniently intelligibly by the work team two factors within the layout itself. The logistics
(Nascimento & Formoso, 1998). approach and the development of management tools
are important strategies for the success of the
The detailed operational planning should be carried
construction site design.
out simultaneously with the product conception. In
this stage it is very important the agents'
participation that more influence, direct or 3.3 Influence of Production Design and Site Design
indirectly, the production phase: designers and on Construction Logistics
building companies. Oliveira (2001) states that production design and site
In the words of Melhado (1994), production design are the instruments that enable the
design is “a set of design elements drawn up constructor to plan and develop on-site logistics
concurrently with the detailing of the execution efficiently. The information they contain support the
design, for use within the scope of on-site production planning, operation and monitoring of the logistic
activities, containing the definitions of disposition activities of construction work (supply, storage,
and sequence of on-site activities and work teams, processing and availability of material resources),
the use of equipments, and the arrangement and indicating when, where and how the production
evolution of on-site work, among other resources activities are to be performed and the amount of
connected with the construction company’s materials to be used in each phase, allowing for
characteristics and resources”. labor planning and aiding in the performance of the
According to Ferreira (1998) the production information system. These characteristics facilitate
design should proceed the four great stages of the the development of supply logistics activities,
production planning : strategic production planning allowing for the early identification of material and
of the enterprise, production tactical planning, labor requirements, facilitating the planning and
production operational planning and production processing of purchased materials and optimizing
operational planning detail. the management of transportation to the site.
With regard to on-site logistics, multiple benefits
3.2 Construction Site Design accrue from the use of these designs, including
visibly improved mapping and, hence, improved
The design of the construction site is possibly the management of the physical flows relating to the
design whose concept most strongly influences execution of the work, smoothing out of the
logistics. Several elements and areas must be problems that usually appear at the interfaces
considered, such as areas for the storage of between the different agents during the productive
materials, living areas for the workers, process, and a substantial reduction of wastage
administrative areas and production areas. resulting from a well organized and signalized
To meet legal regulations and to reach the construction site. Finally, a schedule of the activities
requirements of a highly demanding and competitive and another of materials movements are of
market, the companies have to design construction inestimable value for the control of on-site logistic.
sites according to the current legislation and still A well-implemented and managed logistic
allow improvements in the safety conditions on the system, based on reliable information supplied by
on-site work, rendering the edifice’s production production and site designs, is expected to result in
system more efficient. reduced rehandling, material shifting and losses,
transforming the site into a creditable calling card,  site work conditions.
reducing the risk of accidents, creating greater According Agapiou et al. (1998), the basic
worker motivation and providing a substantial components of the logistics model consisted of a
increase in competitiveness. number of management’s tools, as it can be seen in
the Table 1.
Because of the repetitiveness of this process and
4 CONSTITUENTS OF THE LOGISTICS PLAN in order to reduce the managerial efforts of those
IN BUILDING CONSTRUCTION responsible for it, it is important to develop tools to
aid in the administration and control of information
transference. The examples proposed are: a schedule
4.1 Logistics Model of Civil Construction of the materials and components requirements, and a
schedule of materials deliveries to the site. The latter
In a study on logistics in construction, Agapiou et al.
is based on the logistics concept, knowledge of the
(1998) propose a logistics model developed to
conditions at the site, such as storage space,
improve the aspects of the design and construction
production pace and reduction of transportation
process. The project team identified several criteria
flows. In addition to the need of distribution of
for consideration, including:
efforts among the professionals or workers on the
 planning of site activities;
site, it is advisable that the delivery processes be
 deliveries of material to site;
well distributed. Figure 2 illustrates a schedule of
 number of changes to the detailed design;
materials deliveries to the site.
 re-work during the construction stages; and

Table 1 – Components of logistics management model (Agapiou et al., 1998)

Logistics management Description


tools
Materials coordinator Responsible for managing the logistics model during the construction
process
Supply plan Supply plan indicates the proposed delivery dates of units for the whole
project. This plan is specified by the materials coordination in cooperation with
each supplier / subcontractor
Request schedule A detailed version of the supply plan covering a three week period. The
schedule is draw up by the coordinator in cooperation with each subcontractor.
Unloading plans These plans indicated where daily supplies (units) would be delivered on
site
Unit specification A unit is a package of materials required for one working operations within
one craft at one location on the construction site. The whole project is divided
into units. The content of each unit was specified by individual subcontractors.
A unit plan is specified by the materials supplier in conjunction with the
materials coordinator.

ACTIVITIES Delivery Week


material Strategy 16 17 18 19 20 21 22 23
STRUCTURE
steel (ton) month 5000
concrete (m3) week 25 25 25 25
MASONRY
block (unit) two week 10000 10000 10000
cement (bag 50Kg) month 146 525
whitewash (bag 20Kg) month 548 1971
sand (m3) week 30 30 30

Figure 2 - Gantt chart of deliveries of materials to the site


of the enterprise, this is, from its conception to its
In addition, charts can also be developed to execution. All the agents participating in the
facilitate comparisons between proposed quotations, enterprise should be integrated so that the logistics
drafts in consonance with the negotiation phase, and (supply and site) tools and instruments can be
to draw up guidelines for on-site materials storage. utilized systematically, aiming for synergic gains.
The following guidelines seek to take into Table 2 presents guidelines and tools for the
account the importance of the topics discussed here. preparation and application of logistics plans in
building construction.
4.2 Logistics Plan Guidelines
The logistics approach should be considered
throughout the development of the production cycle

Table 2 – Logistics Production Plan Guidelines

Production cycle Guidelines and tools


Design  Logistics guidelines for the conception
 Analysis of technological alternatives
 Definition of the plan of attack for on-site work
 Production design
 Site design
 As-built design
Planning  Gantt physical chart
 Gantt materials consumption chart
 Gantt equipment chart
 Histogram of own labor
 Gantt subcontractor chart
 Gantt chart of implementation of work safety-related preventive measures
Supplies  Materials specifications
 Plans for materials deliveries to the site
 Gantt chart of the startup of the purchasing process (quotations)
 Materials/supplies purchasing rules
 Materials and services supplier qualification
 Guidelines for equipment purchasing or leasing
 Use of indices of material losses and wastage
Execution  Plan for the execution of work on the floors
 Documentation, implementation and maintenance of the information system
 Use of labor and equipment productivity indices
 Work safety and health rules

These tools should be prepared based on the The logistics plans development and implantation
principles for optimization of construction site request technical specialization and profissional's
efficiency through objective programming on the managerial training. It is advisable to assure the
operational level of execution. It is important that logistics manager's qualifications for not overloading
feedback of the process be provided through critical him with other functions. Moreover, the
analyses and reprogramming of the schedules and organization must have adequate computational
logistics plan, according to need. Experiences and tools for communication and information
information should be recorded and reused so as to processing.
ensure the continuous improvement of the
construction site management process.
5 CONCLUSIONS CARDOSO, F. F. 1996. Importância dos estudos de preparação
e da logística na organização dos sistemas de produção de
This paper, within its limitations, made an brief edifícios. In: 1º SEMINÁRIO INTERNACIONAL LEAN
review of the main concepts directly related with the CONSTRUCTION – A CONSTRUÇÃO SEM PERDAS.
logistics in the construction. Based on these Proceedings... São Paulo, Brazil.
concepts, it was made a reflection on its importance EDUM-FOTWE, F. T. et al. 2001. Information procurement
and basic guidelines were proposed for the first steps practices of key actors in construction suplly chains.
on the logistics plans implementation and its European Journal of Purchasing & Supply Management,
utilization in the building construction v.7, p.155-164.
Based on the precepts of the new production FERREIRA, E. A. M. 1998. Metodologia para elaboração do
philosophy (lean production), the construction projeto do canteiro de obras de edifícios. São Paulo, Brazil:
companies have been showing increasing interest in Escola Politécnica da Universidade de São Paulo.
the implementation of integrated management tools (doctorate thesis).
of production, and are beginning to realize the
KOSKELA, L. (1998). "Lean construction". In: VII
importance of identifying and managing the ENCONTRO NACIONAL DE TECNOLOGIA DO
different agents that participate in the enterprise. AMBIENTE CONSTRUÍDO. Proceedings... Florianópolis,
The adoption of logistics plans may render these Brazil.
companies more competitive, enabling them to
reduce activities that add no value to the product, MELHADO, S. B. 1994. Qualidade do projeto na construção
de edifícios: aplicação ao caso das empresas de
such as stocks, inspections, movement of materials, incorporação e construção. São Paulo, Brazil: Escola
etc. Politécnica da Universidade de São Paulo. (doctorate
The proposed subdivision between supply thesis).
logistics (external) and on-site logistics (internal)
allows for unequivocal identification of the main MUTHER, R.; WHEELER, J. D. 2000. Planejamento
logistics-related activities in the building sistemático e simplificado de layout. São Paulo: IMAM,
50p. Brazil.
construction, thus permitting more detailed planning,
in which the anticipation and adoption of modern NASCIMENTO, C. E.; FORMOSO, C. T. 1998. Método para
instruments for control should be basic premises. avaliar o projeto do ponto de vista da produção. In: VII
Also highlighted was the need for concern ENCONTRO NACIONAL DE TECNOLOGIA DO
regarding logistic management starting in the design AMBIENTE CONSTRUÍDO. Proceedings... Florianópolis,
Brazil.
phase, including a discussion of the dynamic design
concept and its constituents – production design and NOVAES, C. C. 1996. Diretrizes para garantia da qualidade
site design. These constituents supply a large part of do projeto na produção de edifícios habitacionais. São
the information required to carry out of the logistic Paulo, Brazil: Escola Politécnica da Universidade de São
plan and are therefore fundamental elements in the Paulo. (doctorate thesis).
planning and implementation of such plans.
OLIVEIRA, O. J. 2001. Influências do projeto de produção e
Application of the logistics guidelines and do projeto de canteiro no sistema logístico da construção de
instruments cited in this text is directly dependent on edifícios. In: WORKSHOP NACIONAL DE GESTÃO
a profound change in the culture and structure of DO PROCESSO DE PROJETO NA CONSTRUÇÃO DE
construction companies, which must perforce begin EDIFÍCIOS. São Carlos, SP. 2001. Proceedings... São
to use the lean thinking to guide decisions and to Carlos, Brazil. 5p.
execute activities at every organizational level, with SILVA, F. B.; CARDOSO, F. F. 1998. A importância da
special emphasis on top management. logística na organização dos sistemas de produção de
Finally, the development and implementation of edifícios. In: VII ENCONTRO NACIONAL DE
the logistics techniques and instruments in a simple TECNOLOGIA DO AMBIENTE CONSTRUÍDO.
and direct way are not enough for the logistics plans Proceedings... Florianópolis, Brazil.
success.
VRIJHOEL, R.; KOSKELA, L. 1999. Roles of supply chain
Above all, it is necessary the development of a management in construction. In: CONFERENCE OF THE
conscience and real commitment with the lean INTERNATIONAL GROUP FOR LEAN
thinking on the part of all company's employees. CONSTRUCTION (IGLC 7), 7th.,1999, Berkeley.
Proceedings... Berkeley, USA: University of California,
Jul., p. 133-146.
REFERENCES WEGELUIS-LEHTONEN, T. 2001. Performance
measurement in construction logistics. International
AGAPIOU, A. et al. 1998. The role of logistics in the materials Journal of Production Economics, n.69, p.107-116.
flow control process. Construction Management and
Economics, v.16, p.131-137.

View publication stats

You might also like