Control of Monitoring and Measuring Devices
Control of Monitoring and Measuring Devices
: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 1 of 14
1. Purpose
The purpose of this procedure is to provide a documented sytem for the Control of Monitoring and
Measurement Devices (alternatively called equipment).
2. Scope
This Procedure applies to all Measurement and Test Equipment and related services used to verify
conformance of product and processes. It sets out the responsibilities and process for the control of all
existing, new and archived equipment, including equipment owned by the Customer and personal gauges
that are used for the determiniation of product quality.
ECN - An Engineering Change Notice (ECN) is a document authorizing and recording design changes
throughout the prototyping and life-cycle phases of a product. ECN documentation contains the
justification for changes made to a component or system once the initial design is complete
4. Responsibilities
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 2 of 14
Ensuring that documented information as a result of this procedure is adquately identified and
controlled
Ensuring that the proper resources are available to ensure that this procedure can be carried out
effectively.
Review all PCRs and evaluate the potential risks prior to approval
Ensure the proper archiving of obsolete quality tools and fixtures.
Ensuring the scheduling and completion of Product Validation Inspections, including functional
and performance tests as applicable, at a minimum on an annual basis, with consideration of
Customer Specific Requirements
The direct maintenance and control of all the fixtures, gauges and other inspection equipment
(including Red Herrings/Challenge Parts) with related documentation of activities.
Provide advanced notice when measuring tools being used by Technicians need calibration
(provide a spare whenever possible)
Return calibrated measuring tools directly to the owner the same day of calibration request, as
available
Conduct Gauge R&R studies and maintenance as required.
Scheduling In-House Conditional Inspections and Dimensional Layouts of Fixtures & Gauges.
Ensuring that Inspection facilities meet appropriate requirements of certification
Participate in 8D analysis as required
Notification of Quality Engineer(s) and/or Quality Manager if equipment is found to be
defective of out of calibration during regular verification or calibration
5. Procedure
The Quality Engineer is responsible for reviewing all new or modified gauges (including prototype
gauges) for compliance to gauge specifications and Identification Requirements, with consideration to
Customer Specific Requirements.
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 3 of 14
All variable data measuring equipment is to have an appropriate Gauge Repeatability & Reproducibility
Studies conducted prior to release or initial usage according to commodity group, i.e. 0-25 mm
micrometer, 25-50mm micrometer, 0-15mm vernier, etc. This is conducted prior to release after which
they receive Calibration or verification controls as per the Inspection Equipment Schedule.
Where more than one operator or measuring device (gauge, check fixture, etc.) is routinely used to collect
variable data both gauge repeatability & reproducibility will be assessed. Where only one operator and
measuring device is used, only gauge repeatability will be assessed.
Report to
Calibration Remove from
no responsible person
required? database
yes No action
yes
Equipment ready Place into storage +
for use keep records
Equipment marked with a unique
reference, added to the equipment
list, calibration frequency specified
NOTE:
Responsible persons are
Equipment ready defined by each VAR site
for use itself
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 4 of 14
5.1.1.New Equipment
New Inspection Equipment is determined during the Process Development & Validation Process,
through customer input or other Engineering Change. Also included is any personal inspection
equipment used for qualification of product for the customer.
Inspection equipment and related documentation (Design Records, Calibration, etc.) are brought
to the Lab Personnel for control into the Inspection Equipment Management System (ex.
GageTrak or Intranet).
The Quality Lab Technician identifies and maintains the status of fixtures and gauges through the
use of unique ID numbers, permanently marking each so that Ownership can be easily determined,
ie. PROPERTY OF: __________”. Information maintained in the Fixture Management Software
should include:
Type of Equipment
Ownership of Equipment
Location of Equipment
Engineering Revision Level
Method and Frequency of Calibration / Inspections
5.1.2.Damaged Equipment
If equipment has been found to be faulty or otherwise defective it is to be reported to the Lab
Technician, who must remove it from use or otherwise clearly identify it as being out of service.
If applicable the inspection equipment should be removed from the point of use and placed in the
lab.
The Lab Technician is to notify the responsible Quality Engineer who may notify the Customer
depending on ownership or impact.
If the equipment is repairable, it must be done so and then re-qualified / verified for use. If the
equipment is not repairable, the Fixture Management software should be updated and the fixture
archived or scrapped, with records maintained.
5.1.3.Obsolete Equipment
If equipment becomes obsolete, the Lab technician is to remove it from use or otherwise clearly
identify it as being out of service.
The Lab Technician is to notify the responsible Quality Engineer who may notify the Customer
depending on ownership or impact.
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 5 of 14
The fixture Management software should be updated and fixture archived, with records
maintained.
5.2. Laboratory
5.2.1.Internal Laboratory
The internal laboratory (or lab) of vRSC / vRSM shall have a current Laboratory Scope with a
posted copy available in the Laboratory.
The Laboratory Scope shall outline the defines the capability to perform required tests, inspections
or calibration services with applicable standards.
Where deemed necessary, technical procedures of the lab are documented, with consideration
given to Customer Specific Requirements as applicable.
Receipt, identification, handling, protection and retention or disposal of test samples shall be
retained until final data is complete throughout the life of the item in the laboratory, enabling
traceability from final data to raw data.
Only individuals with the appropriate background and experience will be responsible for making
judgement on testing and calibration.
5.2.2.External Laboratory
All measuring and test equipment that is in service is coordinated by the Quality Technician and if
outside calibration is required, certified by an approved sub-contractor that meets and is accredited
to ISO/IEC 17025 (or national equivalent) with a defined laboratory scope that includes the
capability to perform the required inspection, test or calibration.
The Certificate of Calibration or test reports must include the mark of a national accreditation
body.
If the external lab does not meet the requirements noted above, and no alternative is readily
available the Customer must be notified and give Documented approval. Records of this approval
must be maintained with the Vendor Information.
Records of current accreditation and Laboratory Scope for external Labs are maintained by Lab
Personnel.
The Lab Personnel schedules the verification and calibration (if necessary) according to the
schedules established and contained in the Fixture Management Software in cooperation with
equipment user, as appropriate.
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 6 of 14
All instrument inspections results reflect “as found” conditions. Identification of calibration /
usability status are reflected in these inspection results and the Calibration Tags, as illustrated in
relevant Work Instructions.
The Laboratory Technician will ensure that calibration/verification activities and records shall
include following details, as applicable:
5.3.1.In-House Fabrication
At times, the tool room may be relied on to make additional gauges in house. It is important a
print or detailed sketch is provided before the fabrication begins.
Note: Fabrication WILL NOT begin if a print or detailed sketch does not accompany the
Toolroom work order
Once the item has been made, the drawing and gauge are delivered to the Lab technician for
validation, calibration and internal registering.
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 7 of 14
6. Applicable Documents
Mexico:
MXM-SP3- 013 Programa de Calibración
MXM-SP3- 017 Grafica de Control X-R
MXM-SP3-008 Reporte de Inspección Recibo
MXM-SP3-009 Etiqueta Fuera del Programa de Calibración
MXM-SP3-010 Dimensional Report
MXM-SP3-011 Etiqueta de Calibración
MXM-SP3-012 Competencia de Personal en Laboratorio
MXM-SP3-013 Programa de Calibración
MXM-SP3-014 Informe de Calibración
MXM-SP3-015 Verificación de Red Rabbits
MXM-SP3-016 Hoja de Registro para Pruebas Destructivas
MXM-SP3-018 Registro de Datos
MXM-SP3-019 Alcance de Laboratorio
8. Change Notices
1. Proposito
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 8 of 14
2. Alcance
Este procedimiento aplica a todos los equipode de medición y prueba y servicios relacionados utilizados
para verificar la conformidad del producto y los procesos.
Establece las responsabilidades y el proceso para el control de todos los equipos existentes, nuevos y
almacenados, incluidos los equipos propiedad del cliente y medidores personales que se utilizan para la
determinar la calidad del producto.
3. Términos y Definiciones
ECN – Un Aviso de Cambio de Ingenieria (ECN) es un documento que autoriza y registra los cambios
de diseño a lo largo de las fases de creación de prototipos y ciclo de vida de un producto. La
documentación de ECN contiene la justificación de los cambios realizados en un componente o Sistema
una vez que se complete el diseño inicial.
4. Responsabilidades
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 9 of 14
El ingeniero de Calidad es responsable de revisar todos los medidores nuevos o modificados (incluidos
los prototipos) para cumplir con las especificaciones de los medidores y los requisitos de identificacion ,
teniendo en cuenta los requerimientos especificos del cliente.
Todos los equipos de medición de datos variables deben tener una repetición del calibre y estudios de
reproducibilidad adecuados antes del lanzamiento o del uso inicial segpun del grupo de productos, es
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 10 of 14
decir, 0-25 mm micrómetros, 25-50 mm micrómetros, 0-15 mm vernier, etc. Esto se realiza antes para
liberar, después de lo cual reciben controles de calibración o verificaciónsegpun el Programa de Equipos
de Inspección.
Report to
Calibration Remove from
no responsible person
required? database
yes No action
yes
Equipment ready Place into storage +
for use keep records
Equipment marked with a unique
reference, added to the equipment
list, calibration frequency specified
NOTE:
Responsible persons are
Equipment ready defined by each VAR site
for use itself
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 11 of 14
El Técnico de laboratrio debe notificar al Ingeniero de Calidad responsible que puede notificar al
Cliente dependiendo de la propiedad o el impacto.
El técnico de laboratorio debe notificar al Ingeniero de Calidad responsible que puede notificar al
Cliente dependiendo de la propiedad o el impacto.
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 12 of 14
El software de Fixture Management debe actualizarse y el dispocitivo debe almacenarse, con los
registros actualizados.
5.2. Laboratory
5.2.1. Labortorio Interno
El laboratorio interno (o laboratorio) de vRSC/vRSM tendrá un alcance de laboratorio actualizado
con una copia publicada disponible en el laboratorio.
Solo personas con los antecedentes y la experiencia apropiados serán responsables de juzgar las
pruebas y la calibración.
Si el laboratorio externo no cumple con los requisitos señalados anteriormente, y no hay otra
alternativa disponible, se debe notificar al cliente y obtener su aprobación documentada. Los
registros de esta aprobación se deben mantener con la información del vendedor..
Los registros de la acreditación actual y el alcance del laboratorio para laboratorios externos son
mantenidos por personal de laboratorio.
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 13 of 14
Todos los resultados de las inspecciones de instrumentos se reflejan en las condiciones “tal como
se encontraron”. Ña identificación del estado de calibración/usabilidad se refleja en estos resultados
de inspección y las etiquetas de calibración, como se ilustra en las instrucciones de trabajo
relevantes.
Una vez que se ha realizado el artículo, el dibujo y el calibre se entregan al técnico de laboratorio
para su validación calibración y registro interno.
MXM-SP3-0007 Rev. 00
Document No.: MXM-SP3-0018
Control of Monitoring and Measuring Revision / Date: 00 / 22.08.2021
Devices Document Owner: Group-QM
Page: 14 of 14
2 Las inspecciones de diseño se realizarán en un minimo de 3 piezas, sobre una base anual, a
menos que el cliente requiera lo contrario. Los registros de la inspección de dispocision
dimensional están disponibles para la revisióndel cliente previa solicitud.
3 Se mantiene un cronograma para asegurar la naturaleza planificada de esta actividad.
MXM-SP3-0007 Rev. 00