Professional Documents
Culture Documents
Cabling
Cabling
0 OBJECTIVES
This method statement is to outline the procedure of Concrete works in Existing Plaza For Ancasa
Residences Port Dickson On Part Of Lot 526 - 529 Mukim Si Rusa, Teluk Kemang,Port Dickson,Negeri
Sembilan.
This method statement shall apply for all concrete works in Existing Plaza For Ancasa Residences
Port Dickson On Part Of Lot 526 - 529 Mukim Si Rusa, Teluk Kemang,Port Dickson,Negeri Sembilan.
The intention of this work method statement is to give general guideline for the concrete work.
Details of the procedures contained herein may be modified based upon actual ground condition
and site requirements.
3.0 REFERENCES
Concreting of foundations has to come next after the rebar works. The concrete to
be poured should be properly vibrated for the concrete especially the aggregates to
fully spread into the footing. Installation of column reinforcement on previously
installed column starter bars should be continued. A proper concrete cover should
consider before closing the formworks. For substructure columns, an additional
concrete cover (mm refer to drawing) has to considered up to plinth level to protect
the rebar possible corrosion due to sulfate attack.
Formworks with standard concrete cover is also included in this stage. Once
reinforcement works have been complete we can start the concreting. Installing of
grade slab mesh (BRC) and concrete work is then to be follow.
5.9 Rebar works and Concreting of Columns
At this stage, the substructure component of our project has been completed. It is
now time for the project to go up. The next thing to consider is the rebar works,
shuttering or formworks and concreting to be done. Prior to concreting, we see to it
that the columns followed the structural schedule, the form works should be
vertically level and a standard concrete cover has to maintain prior to the closing of
forms.
Once the ground floor columns have been cast, it is time to prepare the project of
beams and suspended slab reinforcement activity. Like any other structural
members, beams and reinforcement should be followed strictly. Shuttering or
formwork for slab and beams should be properly anchored and checked prior to
concrete pouring. The shuttering is generally detached after 24hr of casting and
curing is conducted.
After the concreting process is done for 24hr, curing process will take in place.
Curing process is to maintain an appropriate temperature and moisture content in
concrete for a defined period of time so the concrete will develop in such a way that
the desire material properties can obtained.
The curing process onsite will be conducted by using a curing compound in which
helps to prevent shrinkage cracking by reducing the evaporation of water from the
concrete. A curing compound will be applied with a spraying equipment for evenly
spread. The ratio compound mix depends on the material used.