Professional Documents
Culture Documents
CMC Daeep Ms 01 For Test Pile
CMC Daeep Ms 01 For Test Pile
PROJECT:
DHAKA ASHULIA ELEVATED EXPRESSWAY-BANGLADESH
(FROM CH0+000 TO CH 23+971)
CONTRACT:
DAEEP/01
CONTRACTOR: CMC
CHINA NATIONAL MACHINERY IMPORT AND EXPORT
CORPORATION (CMC)
DOCUMENT TITLE:
METHOD STATEMENT OF TEST PILE CONSTRUCTION
1
Document Title Method Statement of Test Pile Construction
LIST OF CONTENTS:目录
1. Project Overview………………………………........3
2. Introduction…………………………………………...3
3. Scope of works……………………………….......….4
4. Responsibilities……………………………………....4
6. Quality Control…………………….…………........15
9. Materials……………………………………..........…18
10. Manpower……………………………...........…... 18
2
Document Title Method Statement of Test Pile Construction
2.0 INTRODUCTION
The purpose of this document is to outline the proposed methodology for the
construction of the Cast-in-Situ Pilot Test Piles.
The purpose of pilot test pile is to establishing the suitability of the chosen
type of pile and conforming its design, dimensions and bearing capacity.
The design basis of this project is according to AASHTO LRFD Bridge
construction specifications 2017, 4th edition and the technical specifications of
standard tender documents of RHD, Bangladesh. June 2016, 3rd edition
The aim is to detail the sequence and method of construction, identify the
hazard, assess the associated risks involved, develop and implement adequate
control measures and to provide a safe place for work.
ensure that documentation is generated to record the installation activities
and to monitor the quality assurance.
3
Document Title Method Statement of Test Pile Construction
All personnel will receive a site-specific induction. Before any works commence
a method of statement briefing will be conducted by the site management.
3.0 SCOPE OF WORK
The main test pile of the working platform project is 24. The first batch of first
nine test piles (TP01, TP02, TP03, TP04, TP05, TP06, TP07, TP08&TP09). The
second batch of 15 piles will be tested according to the actual situation. This
construction scheme describes the working method of test pile construction.
4.0 RESPONSIBILITIES
Subcontract project manager of each section shall be responsible for overall
operation activities inclusive of ensuring that all safety measures are
implemented.
The Project Engineer shall be responsible for the coordination and supervision
of construction activities and coordinate with other agencies and ensure that
the work is done as per specification and approved drawings and all safety
measures are implanted
4
Document Title Method Statement of Test Pile Construction
According to the pile test layout, the work area shall be laid out in accordance
with the location shown on the drawing or approved by the Employer's
Engineer.
5.1.4 During the preparation of the Working Platform and prior to the start of
the drilling, an investigation should be carried out to assure the absence of any
obstructions at the pile locations. All utility services, old foundations, existing
pavement, obstacles or any objects interfering with the drilling works shall be
removed or diverted.
5.1.5 If the pilot pile construction area existing level is lower than the pile cut
off level, then the area shall be backfill with the suitable materials up to at
least 1m higher than the cut off level of pile.
5.1.6 For the stability the working area shall be well compact, layer by layer
with the suitable roller compactor.
5
Document Title Method Statement of Test Pile Construction
Length of the temporary steel casing will depend on the depth of the soft
upper-layer and the water level.
6
Document Title Method Statement of Test Pile Construction
The condition of these casings shall be free from significant distortion and shall
have a uniform cross-sectional dimensions throughout the length.
The temporary casings shall be installed by vibration using a vibro-hammer of
sufficient power or by rotation using the drilling rig machine.
The temporary Casing will be installed within a maximum deviation from the
center point of the pile of 100 mm in any direction. A surveyor with the
necessary equipment’s shall be present full time during the operation. The
location of the temporary protective container shall be inspected and
approved by the Employer's Engineer (Hold point).
7
Document Title Method Statement of Test Pile Construction
8
Document Title Method Statement of Test Pile Construction
9
Document Title Method Statement of Test Pile Construction
10
Document Title Method Statement of Test Pile Construction
11
Document Title Method Statement of Test Pile Construction
The tubes shall be watertight, free from corrosion with clean internal and
external faces to ensure good bond between the concrete and the tubes.
The access tubes shall be secured to the inside of the main axial reinforcement
of the steel cage at frequent and regular intervals along their length to
maintain the tube alignment during cage lifting, lowering and subsequent
concreting of the pile.
During tubes installation, care shall be taken to ensure that all access tubes are
parallel to each other as possible. After installation of the reinforcement cage
into the pile, the top end caps shall be temporarily removed and the tubes
shall be inspected by the contractor engineer to verify they are clear of
obstructions.
The access tubes shall be filled with water prior to, or within one hour of,
concrete placement to assure good bonding of the concrete to the tubes after
the concrete cools.
The tubes length, joint details and their nominal position shall be recorded to
the neasest 10 mm.
If extension of tubes is necessary due to long tube length, access tube
couplings shall be used which prevent slurry or grout ingress during
construction.
As per ASTM D 6760 a typical access tubes layout configurations are as below
12
Document Title Method Statement of Test Pile Construction
13
Document Title Method Statement of Test Pile Construction
14
Document Title Method Statement of Test Pile Construction
completion of concreting. The bottom of the tremie pipe shall be kept at least
2 metres under the surface of concrete once that amount of concrete has been
placed. Workability of the concrete shall not be less than 150 mm.
The pile shall be concreted with a certain over height to allow for chiselling off
the top concrete down to sound hard concrete.
After concreting, the temporary casing shall be withdrawn by rotation using the
piling rig or a vibro-hammer. When the casing is being extracted, a sufficient
quantity of concrete shall be maintained within it to ensure that pressure from
external water or soil is exceeded and that the pile is neither reduced in section
nor contaminated.
15
Document Title Method Statement of Test Pile Construction
The diameter of pile shall not be less than the specified diameter
The centre of pile shall not deviate more than 100 mm at any direction
Vertical alignment shall not deviate more than 1:100
Pile clear cover shall be 75 mm
Reinforcement of test pile shall be deformed bar with minimum yield stress
500 N/mm2 and shall conform to ASTM A615
Minimum lap length of helix shall be 500mm
Laps shall be staggered and not more than 50% of bars are lapped in any cross
section
Joints in longitudinal bar shall be maintain proper welding’s
Steel tubes/pipe for sonic test shall be 40mm inside diameter with 4mm wall
thickness
The sonic test tubes installation position shall be check as drawings
The strain gauge installation position shall be check as per drawing
Ensure the strain gauge numbers and positions, 4 nos per section @ 5 m
vertical interval
The concrete of pile shall be 30 Mpa
Workability(slump) of concrete shall be minimum 150 mm
9 nos Cylinder(150x300) sample per pile shall be taken for strength check
test per 25m3 concrete shall be maintain
Ensure the tremie pipe bottom always penetrate 2m into the concrete during
the casting
After construction of the pile, axial load test, lateral load test and acoustic test
shall be carried out in accordance with the Code and ASTM standards and a
report shall be submitted to the Employer Engineer for approval. A separate
test plan shall be submitted for approval.
16
Document Title Method Statement of Test Pile Construction
8.1 All Operative shall be made aware of the HSE requirement for drilling, steel
fixing and concrete casting works.
8.2 Appropriate Personal Protective Equipment’s (PPE) shall be available and
worn by all operatives
8.3 All non-motorized equipment’s and tools will be mechanically lifted into the
work area
8.4 Only trained and skill operatives shall be involved in this activity.
17
Document Title Method Statement of Test Pile Construction
9.0 MATERIALS
1. Concrete Strength = 30 N/mm2 or as per test pile drawings and
specification
2. Steel Reinforcement as per test project specification section 5.2.
3. Binding Wire as per requirements
4. Concrete Spacers (75mm) or equivalent
5. Flooring Steel Plates as per requirements
10. MANPOWER 人力
For the non-stop operation adequate manpower shall be present at site.
SL No. Type of sonnePerl Quantity Remarks
1 Piling Engineer 06
2 Supervisors 06
3 Rigger 03
4 Welder 06
5 Operator 06
6 Driver 08
7 Steel Fixer 16
8 Mechanics 04
9 Electrician 03
10 Surveyor/Survey Helper 09
11 Flagmen and Traffic Management 12
Staff
18
Document Title Method Statement of Test Pile Construction
19