Chart for May Month Production-2022.

Sr.no Job No. Project Name Contract Value in


% of completion May % of completion June Remarks
Aed

1 1516 Royal Atlantis 65,000.00 100 NA completed and installed at site -


Variation work of Atlantis
2 1615 Arabain Park Hotel 328,000.00 25 34 WIP

3 1619 Villa Frond-beach home 457,394.00 100 NA Variation work of Aed 94125.28
only done month of may2022
4 1626 Royal Atlantis (AHK) 425,000.00 20 65 WIP
5 1627 Abrahamic Famaly 143,330.00 NA NA Only mock up work done
6 1630 Future School Gayathi 41,162.00 75 25 Site completed
7 1630/1 Future School Gayathi 23,850.00 75 25 WIP
8 1631 Future School Madinat 30,017.00 75 25 Site completed
9 1631/1 Future School Madinat 42,729.00 75 25 WIP
10 1632 Wow Properties 313,273.00 25 40 WIP
11 1633 Surivilla 163,916.00 100 NA Site completed
12 1635 Arabain Park Hotel 3,779,250.00 10 25 WIP
13 1636 Sar Villa 21,204.00 80 20 Site completed
14 1637 Ajmal Villa 219,000.00 80 20 Site completed
15 1638 Royal Mirage 590,000.04 5 10 WIP
16 1639 Centerl Park Tower 19,203.00 80 20 Site completed
Total 6,662,328.04
In House Projects
17 1585/13 Sheikha Villa 5,937.00 100 NA
18 1585/11 Sheikha Villa 4,475.00 100 NA
19 1623 Sheikh New Villa 14,190.00 100 NA
20 1640 Grand Atana, Artline 60,000.00 80 20
21 Wooden Partition
Total 84,602.00