Project Daily Monitoring Sheet: Equipment Qty
Project Daily Monitoring Sheet: Equipment Qty
Activities
1.) Hauling of Scaffold Materials
2.) Erection of Scaffolding for Gin Pole
3.) Final Check of Lay-out of Shell Nozzle( N3, N4, N5, N6, N1)
4.) Final Check of Lay-out of two units of Sump
5.)
Accomplishment
1.) Hauling of Materials
2.) Erection of Scaffold for Gin Pole (continuous)
3.) Final Check of Lay-out of Shell Nozzle( N3, N4, N5, N6, N1)
4.) Final Check of Lay-out of two units of Sump
5.)
Remarks
1.) Unexpected weather condition
2.)
Manpower List
Sn Name Designation Sn Name Designation
01 F. DOROMAL FOREMAN 10 A.ENRIQUEZ TENDER/RIGGER
07 J. PONTE WELDER 16
08 R. SALARDA WELDER 17
09 J. SALIBAY WELDER 18