SC200/200)S1 Operation Manual of construction hoist

徐工集团徐州建机工程机械有限公司
XCMG Xuzhou Construction Machinery Co.,Ltd
To users:

Great appreciations for purchasing our hoist!

Please carefully read and take care of the Operation


Instruction to correctly use and maintain the equipment.

The words marked with sign in the


Instruction should be paid attention for safety of
construction.

As our products are being improved constantly, it results in


certain changes of the Operation Instruction. Our company
reserves the rights to modify the interrelated contents without
prior notices. If any doubt, please contact us.

As our products are being optimized


Production No.:
and perfected continuously to satisfy
the value-added demands of market
Production Date:
and customers, and the attached
documents will be also updated
accordingly. The attached documents
and the product with the same number
shall correspond to each other. For
more relevant information during the
installation, please contact us.
Operation Instruction of SC Series Construction Hoist Content

Contents
1  Use principle ............................................................................................. 1-1 
1.1General principles ................................................................................ 1-1 
1.1.1 Weather and geographic conditions ........................................ 1-1 
1.1.2 Environmental conditions ........................................................ 1-3 
1.1.3 Design-related conditions ........................................................ 1-3 
1.1.4 Installation conditions.............................................................. 1-5 
1.2 General responsibilities ...................................................................... 1-6 
1.2.1 Provisions relating to the user ................................................. 1-7 
1.2.2 Provisions involving the use conditions .................................. 1-8 
1.2.3 Provisions associated with specific risks................................. 1-9 
1.3 Safety Signals ................................................................................... 1-11 
1.3.1 Description............................................................................. 1-11 
1.3.2 Terms ..................................................................................... 1-12 
1.3.3 Signboad ................................................................................ 1-12 
1.3.4 Audible signal ........................................................................ 1-14 
1.4 Safety Control ................................................................................... 1-14 
2  Safety Rules .............................................................................................. 2-1 
2.1 Safety responsibility of user ............................................................... 2-1 
2.2 Safety requirements of installation and removal stage ....................... 2-1 
2.2.1 Responsibilities ........................................................................ 2-1 
2.2.2 Safety measures for preliminary installation and removal ...... 2-1 
2.2.3 Security measures for installation and removal ...................... 2-2 
2.2.4 Safety measures after installation ............................................ 2-3 
2.2.5 Safety measures for acceptance tests and inspections ............. 2-6 
2.3 Periodic inspection and testing ........................................................... 2-6 
2.3.1 Requirements of periodic inspection and test.......................... 2-6 
2.3. 2 Routine security checks .......................................................... 2-7 
2.4 Operational safety ............................................................................... 2-8 
2.4.1 Responsibilities ........................................................................ 2-8 
2.4.2 Safety measures of operation................................................... 2-8 
2.5 Maintenance ........................................................................................ 2-8 
2.5.1 Responsibilities ........................................................................ 2-8 
2.5.2 Security measures of maintenance .......................................... 2-9 
3  Overview and technical features ............................................................ 3-1 
3.1 Overview............................................................................................. 3-1 
3.2 Performance parameters ..................................................................... 3-3 
3.2 Introduction to construction hoist principles ...................................... 3-3 
3.3.1Mast (rail rack): ........................................................................ 3-4 
3.3.2 Drive System ........................................................................... 3-4 
3.3.3 Electrical system: ..................................................................... 3-5 
3.3.4 Anti-fall safety device: ............................................................ 3-5 
I
Operation Instruction of SC Series Construction Hoist Content

3.3.5 Limit device: ............................................................................ 3-6 


3.3.6 Electric control box: ................................................................ 3-6 
3.3.7 Resistance Box ........................................................................ 3-7 
3.3.8 Cage: ........................................................................................ 3-7 
3.3.9 Power Box: .............................................................................. 3-7 
3.3.10 Brace fence: ........................................................................... 3-7 
3.3.11 Cable sleeve: .......................................................................... 3-9 
3.3.12 Cable retaining rack: .............................................................. 3-9 
3.3.13 Tie-in frame: .......................................................................... 3-9 
3.3.14 Cable bracket: ........................................................................ 3-9 
3.3.15 Installing boom: ..................................................................... 3-9 
3.3.16 Cable car system: ................................................................. 3-10 
4  Base configuration ................................................................................... 4-11 
4.1Calculation of base bearing capacity P .............................................. 4-11 
4.2 Selection of configurations of concrete foundation ......................... 4-12 
4.3 Base selection related to tie-in frame ............................................... 4-12 
4.4 Cautions for making concrete base................................................... 4-14 
5  Rail rack and tie-in frame ....................................................................... 5-1 
5.1 Configuration of guide frame ............................................................. 5-1 
5.2 Type and selection of tie-in frame ...................................................... 5-4 
5.3 Connection of tie-in frame and attached wall .................................... 5-8 
5.4 Maximum mounting pitch and maximum height of the boom end of
tie-in frames .............................................................................................. 5-9 
5.4.1 Installation ofⅠ-type, Ⅱ-type and Ⅳ-type tie-in frames and
cable retaining rack (cable car type) ................................................. 5-9 
5.4.2 Installation ofⅢ-type tie-in frame and cable retaining rack
(cable car type) ............................................................................... 5-10 
5.5 Calculation of force F of tie-in frame to wall ................................... 5-11 
6  Installation and debugging...................................................................... 6-1 
6.1 Installation .......................................................................................... 6-1 
6.2 Preparations before installation .......................................................... 6-1 
6.3 Installation .......................................................................................... 6-3 
6.3.1 Precautions for installation ...................................................... 6-3 
6.3.2 Installation of chassis, bottom mast and chassis fence............ 6-4 
6.3.3 Installation of lifting cages, drive system, roof rails and
installing boom ................................................................................. 6-6 
6.3.4 Counterweight installation (for hoist with counterweight) ..... 6-8 
6.4 Installation of electrical equipment, control system and overload
protection device ....................................................................................... 6-9 
6.4.1 Installation of electrical equipment and control system .......... 6-9 
6.4.2 Mounting of overload protection device ............................... 6-10 
6.5 Installing the limit cam at the bottom of rail frame and test run of

II
Operation Instruction of SC Series Construction Hoist Content

power-driven hoist .................................................................................. 6-11 


6.6 Hoist commissioning ........................................................................ 6-12 
6.6.1 Clearance adjustment of guide roller..................................... 6-13 
6.6.2 Clearance adjustment of gear and rack.................................. 6-13 
6.6.3 Clearance adjustment of back wheel and rack ...................... 6-13 
6.6.4 Adjustment of cable car ......................................................... 6-13 
6.6.5 Comprehensive lubrication for hoist ..................................... 6-14 
6.7 Drop test............................................................................................ 6-14 
6.7.1 Requirements of anti-fall safety device ................................. 6-14 
6.7.2 Drop test instructions ............................................................. 6-14 
6.7.3 Drop test methods .................................................................. 6-15 
6.7.4 Reset of anti-fall safety device .............................................. 6-16 
6.8 Heightening the rack frame (installing the tie-in frame at the meantime)
and installing the cam of top limit .......................................................... 6-17 
6.8.1 Heightening the rack frame ................................................... 6-17 
6.8.2 Mounting the cam of top limit of rack frame ........................ 6-18 
6.9 Installation of tie-in frame ................................................................ 6-19 
6.9.1 Installation of I-type tie-in frame .......................................... 6-20 
6.9.2 Installation of Ⅱ-type tie-in frame ....................................... 6-21 
6.9.3 Installation of Ⅲ-type tie-in frame ....................................... 6-22 
6.9.4 Installation of Ⅳ-type tie-in frame ....................................... 6-23 
6.10 Mounting of counterweight unit (for construction hoist with
counterweight) ........................................................................................ 6-24 
6.11 Re-heightening and mounting of rack rail frame with counterweight
assembly ................................................................................................. 6-25 
6.12 Installation of cable guide............................................................... 6-27 
6.12.1 Mounting cable sleeve and cable retaining rack ................. 6-27 
6.12.2 Installation of cable guide device of cable-pulley type ....... 6-28 
6.12.3 Installation procedures for cable guide device of special pulley
rail: .................................................................................................. 6-33 
6.13 Installation of Floor-call system ..................................................... 6-36 
7  Operations and Use .................................................................................. 7-1 
7.1 Security check before operation ......................................................... 7-1 
7.2 Operating ............................................................................................ 7-2 
7.2.1 Operation: ................................................................................ 7-2 
7.2.2 When the cage cannot start, check the following items. ......... 7-3 
7.2.3 .................................................................................................. 7-4 
7.2.4 .................................................................................................. 7-5 
8  Inspections / Lubrication ........................................................................ 8-1 
8.1 Safety Precautions: ............................................................................. 8-1 
8.2 Daily inspection: ................................................................................. 8-1 
8.3 Weekly inspection: ............................................................................. 8-2 
III
Operation Instruction of SC Series Construction Hoist Content

8.4 Monthly Inspection: ............................................................................ 8-3 


8.5 Quarterly Inspection: .......................................................................... 8-3 
8.6 Year inspection: .................................................................................. 8-3 
8.7 Special inspection ............................................................................... 8-4 
8.7.1Detection for transmission gear ................................................ 8-4 
8.7.2 Rack Detection ........................................................................ 8-4 
8.7.3 Detection of worm teeth .......................................................... 8-4 
8.7.4 Braking torque detection ......................................................... 8-5 
8.8 Lubrication .......................................................................................... 8-5 
8.8.1 .................................................................................................. 8-5 
8.8.2 .................................................................................................. 8-6 
9  Maintenance ............................................................................................. 9-1 
9.1 Check failure of electrical system ...................................................... 9-1 
9.1.1Troubleshooting methods for electrical system:.................... 9-2 
9.2Breakdowns and solutions of mechanical system: ........................... 9-3 
9.3 Common faults and solutions of transducer ....................................... 9-4 
9.4 Replacement of wearing parts ............................................................ 9-4 
9.4.1 Motor replacement ................................................................... 9-4 
9.4.2 Electromagnetic brake maintenance ........................................ 9-6 
9.4.3 Replacement of anti-fall safety device .................................... 9-8 
9.4.4 Replacing the guide rollers ...................................................... 9-8 
9.4.5 Replacing the side guide rollers .............................................. 9-8 
9.4.6 Replacement of upper double guide rollers ............................. 9-8 
9.4.7 Replacement of lower double guide rollers ............................. 9-9 
9.4.8 Replacement of transmission gear ........................................... 9-9 
9.4.9 Replacing masts ..................................................................... 9-10 
9.4.10 Replacement of rack ............................................................ 9-10 
9.4.11 Replacing the back wheel .................................................... 9-10 
9.4.12 Replacing worm reducer ...................................................... 9-11 
10  Removal of Hoist .................................................................................... 10-1 
10.1Principles for removal ..................................................................... 10-1 
10.2Preparations before removal ............................................................ 10-1 
10.3Carrying out the removal procedures .............................................. 10-2 
10.4 Removing procedures ..................................................................... 10-2 
Appendix I .......................................................................................................... 1 
Appendix II......................................................................................................... 2 
Appendix Ⅲ ....................................................................................................... 3 

IV
Operation Instruction of SC Series Construction Hoist Content

V
Operation Instruction of SC Series Construction Hoist Content

Limit cam
Installing boom
Rail frame

Drive system

Cable bracket

Lifting cage

Scaffold

Electrical
control box
Cable1retaining rack
f Tie-in frame

Limit cam Chassis fence

Power box
Cable drum

Hoist base

SC Series Construction Hoist Schematics (Cable-Drum Type)

VI
Operation Instruction of SC Series Construction Hoist Content

SC Series Construction Hoist Schematics (Cable-Pulley Type)


Limit cam Rail frame

Drive system

Cable1retaining
rack frame
Lifting cage
Installing boom

Cable pulley

Electrical control box

Tie-in frame

Cable1retaining
Limit cam rack frame

Chassis fence

Power box

Hoist base

VII
Operation Instruction of SC Series Construction Hoist Use Principle

1 Use principle
1.1General principles
The general principles cover the contents of conditions in Chapter 3 of
“Overview and Technical characteristic”, Chapter 4 of “Base configuration” and
Chapter 5 of “Mast and tie-in frame”. For unmentioned conditions, please consult us.
Other importance cases of operating hoist are illustrated by figures in the
Instruction.

1.1.1 Weather and geographic conditions

1.1.1.1Wind
The use conditions of hoist, such as standard height, reaction and pressure of base,
depend on the datum wind velocity of construction site of hoist. The datum wind
velocity (GB50009.2001) is the measured average wind velocity for ten minutes of
plane 10m above the ground.
1.1.1.1.1General condition
The datum wind velocity of running hoist can be confirmed referring to the
“Average Wind Velocity of Countries”.
For the datum velocity area of other places or countries except China, please
contact us.
1.1.1.1.2 Special conditions, such as:
□ No mean wind speed map;
□ The country or region has special provisions or certain circumstances;
□ Altitude higher than the indicated height in average wind speed diagram;
□ Basin, valley, Yamaguchi, mountain, etc;
It requires the user to design and determine the baseline average wind speed of
installation site of construction hoist. Or consult our company for relevant data.
1.1.1.1.3 Construction hoist running
Construction hoist is used only at the location with maximum wind speed
measured (gusts) less than 72km / h.
1.1.1.1.4 Installation, removal and change position of construction hoist
Installation, removal and change position of construction hoist can be carried out
only when the maximum wind speed (gust) measured is less than 45km / h.
1.1.1.1.5 Ambient temperature at shade

1-1
Operation Instruction of SC Series Construction Hoist Use Principle

The temperature is the temperature within a non-closed place, no wind, no rain


shelters, and 2m from the ground at lift construction site l00-meter radius.
The used temperature range of construction hoist is at operating (non-operating)
state: -20 ℃ to + 40 ℃, besides the special cases (e.g.: the country with special
reasons).
When the temperature is not in this range, stop the construction hoist, otherwise
there will be abnormal or dangerous work or abnormal heating to damage the
electrical components.
1.1.1.1.6 Humidity and precipitation
The humidity and precipitation for construction hoist use (active or inactive state):
maximum humidity of 95% non-condensing (except as the special case provided in
the contract).
The maximum humidity of construction hoist storage (after disassembly) is l00%.
1.1.1.1.7 Frost, ice and snow
Frost, ice or snow will increase the structure weight and frontal area and damage
the parts in operation, and worse cause the danger of falling people in job.
When the construction hoist is covered with frost, ice or snow, it is prohibited to
operate the construction hoist.
1.1.1.1.8 Lightning
Lightning causes structural components, such as the lift steel, with a wall frame
/ brace fence, of construction hoist energized and operating people with direct or
indirect contact with dangerous electric shock.
When storm occurs, you should stop the job of construction hoist. Do not board
or leave the construction hoist during a thunder storm!

As if it’s too late for the operator to leave the construction hoist
before a storm (sudden thunder storm), do not try to leave construction hoist
during a thunder storm. It is safer to remain in the hanging cage and do not
touch the console.
1.1.1.1.9 Sandstorm
After the storm, the sand will be drilling appliances and internal structures and
plugging gaps.
Before restarting, the inside of the electrical and structural parts should be
thoroughly cleaned. If necessary, remove the movable member of related mechanism.

1-2
Operation Instruction of SC Series Construction Hoist Use Principle

1.1.1.1.10 Floods and tidal


The construction hoist is designed without considering these factors. When
floods or tidal the stability of construction lift would be reduced so the job should be
stopped.
1.1.1.1.11 Earthquake
Except specially requested in contract, the construction hoist is designed without
consideration to earthquake, regardless of how much magnitude.
1.1.1.1.12 Special installation
Except specially requested in the contract, the construction hoist is designed
without consideration to be installed on movable base, such as drilling rigs, barges,
floating caisson and the like.
1.1.1.1.13 Tie-in frame of construction hoist
Tie-in frame of construction hoist is designed based on the set force in Technical
parameters of hoist so it should be fabricated strictly within the indicated tolerances.

1.1.2 Environmental conditions

1.1.2.1Environment with radioactive substances


Unless specified in the contract, the maximum concentration permitted in the
environment of using construction hoist should be consistent with the concentration
of industrial areas or high-traffic areas.
1.1.2.2 Explosive environment
Construction hoist cannot be used in explosive environments.
1.1.2.3 Electromagnetic field
Except as provided in the contract, the electromagnetic field of construction
hoist is less than 10V / m, such as: 100kW radio within 500m range from construction
hoists or TV transmitter / from a portable transmitter electrical box or console within
0.5m.
As all metal structure, construction hoist will terahertz wave transmitting and
receiving interference.
1.1.2.4 Radiation
Construction hoists is unacceptable to radiation.

1.1.3 Design-related conditions

1.1.3.1 Adaptability of construction hoist to construction site is responsible by the


user.

1-3
Operation Instruction of SC Series Construction Hoist Use Principle

1.1.3.2 Power
Power supply and fluctuation range of construction hoist design must be as
required. Failure to comply with a given value will result in the improper work of
construction hoist.
1.1.3.3 Operator workstation
Depending on the type selected, the operator can manipulate the construction in
the cab or hanging cages.
1.1.3.4 Safety devices
Safety device of construction hoist (limits) prohibit work beyond its scope.
Don’t arbitrarily change the adjustment range of safety devices, hindering its action
or making it lose of effect.
1.1.3.5 Protection Agency / protection device is used for prohibiting the hoist from
entering the danger zone. It shall not be canceled under any circumstances. Don’t
start the construction hoist before all protective devices (e.g.: safety shields, guard
fence, railing, cover, etc.) are in place.
1.1.3.6 Conventional life
Conventional life of construction hoist is the lowest life expectancy of
construction hoists to calculate the state of wear.
In addition to the special provisions of the contract, the conventional life of
construction hoist shall comply with Standard GB26557-2011 and other relevant
criteria in grading methods. The rating methods are provided for the life of the hoist
machine and its mechanism member.
1.1.3.6.1 Working level of structural parts
Conventional life of structural part is represented by a running life cycle (one
operating cycle = a rise and fall of the whole process work cycle of cage).
Working-level class of construction hoist is A6.
1.1.3.6.2Working level of mechanism
Conventional life of mechanism is represented by the working hours of
mechanism. The conventional life rating of mechanism member is based on the type
and operation of construction hoist. Loading condition of mechanism member decides
the life of mechanism part. Conventional life rating of mechanism is M5.
1.1.3.7 Advertising signs
In addition to the special provisions of the contract, users can not install advertising
signs without the written consent of construction hoist manufacturer.

1-4
Operation Instruction of SC Series Construction Hoist Use Principle

1.1.3.8 Fire extinguishers


Provision and installation of fire extinguishers in cage or cage hanging cab needs to
be borne by the user.
1.1.3.9 Modifications to construction hoist / lift manufacturer structure or welding
without the written consent of manufacturer (such as an increasing or modification of
components, cutting, welding, etc.).
1.1.3.10 It is prohibited to install accessory to change the adjusting device of
construction hoist (such as calibration, adjustment values, etc.).
1.1.3.11 Users should be responsible for consequences of matching or replacement
with parts not provided or recommended by construction hoist manufacturers.
It is prohibited to use the non-original or without construction hoist
manufacturers identified for replacement parts.
1.1.3.12 Monitoring / inspection
Construction hoist monitoring: storage and use in good condition, checked
according to the Instructions about inspection frequency, inspection cycle.
If the relevant standard regulations at the location of construction hoist are more
stringent than the provisions of the present specification, the former should be
complied for checking. And complete the tracking card of construction hoists
according to the instructions provided in this manual.
1.1.3.13 Clear waste
In accordance with the local standard regulations of construction hoist,
remove all waste, such as: dirty grease, oil and the like.

1.1.4 Installation conditions

Don’t install or uninstall the construction hoists in bad weather, like wind speed
over l2.5m / s, thunderstorm days, or snowy weather.
1.1.4.1 Distance to obstacles
The minimum distance of construction hoist outstanding part of rising and
falling to obstacles, if there is no special provision, it is at least 0.25 meters.
1.1.4.2 Distance between construction hoist and overhead power line
Ensure a safe distance between construction hoist part and overhead
transmission lines, and if there is no special provision, this distance is: 4m vertically
and 2m horizontally when it is less than or equal to 40kV voltage; if the voltage is
over 40Kv; the distance is added 5cm for additional 1kV.
1.1.4.3 Strength requirements of concrete foundation

1-5
Operation Instruction of SC Series Construction Hoist Use Principle

The concrete foundation of construction hoist before installation must meet


the technical requirements of installation and construction strength.
1.1.4.4 Power box and cable
Power box of construction hoist must use a dedicated power supply box and
not share with other electrical equipment. The voltage and current of cable of power
supply box should meet the requirements of construction hoist and be correctly
grounding.
1.1.4.5 Installation and acceptance
Before use the user should detect and check the installed construction hoist
together with local inspection agencies, in accordance with the all content of
“Construction Hoist Supervision and Inspection Regulations” (State Quality
Inspection 121.2002) of (Construction Hoists Acceptance Test Report).
1.1.5 Auxiliary handling conditions
1.1.5.1The auxiliary handling equipment of construction hoist is used to install and
uninstall mast loads with the help of installing boom at cage top. Prohibit the use of
all dynamic equipment for loading and unloading, such as an electromagnet, grapple
bucket and so on.
1.1.5.2 Mast load handling
a) Do not lift mast load not strapped firmly;
b) Do not load inclined mast;
c) The lifted mast load should be vertical to hook;
d) Do not increase weight on the lifted mast load;
e) Personnel should highly notice the installing boom in lifting or dropping
mast;
1.1.5.3 Manned prohibited
The installing boom of construction hoist cannot be used to carry person. If the
located country of the construction hoist allows the construction hoist manned, the
user should take full responsibility.

1.2 General responsibilities

This provision relates to all relevant personnel, especially suitable for


construction hoist managers and operators. Relevant personnel are required to comply
with it carefully.
The use of construction hoists please strictly comply with “l.1 General
Conditions of Construction Hoist Use”

1-6
Operation Instruction of SC Series Construction Hoist Use Principle

1.2.1 Provisions relating to the user

Construction hoist managers and operators shall observe the relevant local
installation / removal, manipulation, protection and accident prevention.
1.2.1.1 Provisions to construction hoist managers:
a) The construction work should be manipulated by a qualified operator:
□ Operator’s age is as required locally;
□ Physical condition of operator meets the requirements (vision, hearing,
reaction, flexibility, suitable for high-altitude operations, etc.);
□ Obtain qualifications through training by qualified agencies, and with
associated qualified and efficient certificate, and have a full understanding to the risk
of this type of work (electrical hazards, dangerous high altitude, etc.).
□Prohibit all persons not meet the above conditions to manipulate
construction hoist.
b) Clear responsibility of each hoist worker:
□ A qualified engineering and technical personnel for construction hoist
installation / removal / test / maintenance and other command is needed.
□ HR managers need to train and practice the operating personnel;
□ Management shall provide plans for special requirements for installation
and removal.
c) Ensure that the construction hoist staff is familiar with and understand the
safety requirements, regularly inspects the implementation of these provisions.
Construction hoist staff must:
□ Wearing appropriately (such as: hair coiled up, suitable clothing, etc.);
□ Wearing protective gear: safety helmets and safety shoes; wear gloves when
manual operation;
□When aerial work (ground> 3 meters), tie safety rope;
d) Define execution for specific recommendations in the manual:
□ Construction hoist operator before the construction hoist is off is not
allowed to leave the console;
□Install passage means for the construction hoist installation, removal or
maintenance, in accordance with the local relevant provisions, (escalators, walkways,
platforms, etc.);
□ Prepare appropriate tools of measuring and maintenance for maintenance
personnel;

1-7
Operation Instruction of SC Series Construction Hoist Use Principle

□ Construction hoist operator during operation should pay attention to the risk
of work-related (e.g.: people running up and down the cage area, run-up and down
whistle, etc.).
1.2.1.2 Regulation for construction site management:
□ Construction hoist construction workers should be informed of all relevant
dangers of construction hoist directly or indirectly (such as: site impact, load swing
caused by the wind, etc.).
□Construction hoist construction workers should be informed of the meaning
of construction hoist operation, sound and signal (referring to: “Safety Signals”
section).
□ Work together with construction site workers in an appropriate manner to
set isolation protection devices above hoist anti-fence and base chassis.
□ Prohibit the site workers climb over the mast section and tie-in supporting.

1.2.2 Provisions involving the use conditions

1.2.2.1 Provisions relating to the construction machinery and equipment


Comply with the local relevant provisions of construction machinery and
equipment in use:
□ Road transport;
□ Distinguisher and fire-fighting equipment;
□ Environmental protection;
□ Radio frequency transceiver control;
□ Periodic inspection
1.2.2.2 Climatic conditions
In exceptional weather conditions, construction hoist users should formulate
plans to be followed (such as: lower operating height, withdraw from the site, etc.).
The program plan can be established depending on the forecast system of
weather conditions by the local meteorological department.
1.2.2.3 Entering the construction hoists and cab
□ Enter into the construction hoist / cab after the construction hoist is stopped
through the prescribed channels.
□ Maintain the entering channel of construction hoist / cab tidy: remove all
waste, oil, spare parts, tools and other debris; and tools, materials, spare parts stored
at a predetermined position.
□ The weight of construction hoist cage carried with personnel, materials,

1-8
Operation Instruction of SC Series Construction Hoist Use Principle

tools, etc, must not exceed the maximum permissible load.


1.2.2.4 Abnormal operation of construction hoist
When construction hoist has abnormal operation, it should be stopped by
professionals to check and make an assessment of its danger; for dangers likely to
endanger the safety of unusual circumstances should be excluded immediately; and
anomalies be recorded in the track record of construction hoist.
1.2.2.5 Power Safety
Construction hoists is possibly charged so the user should be establish the
plans for power supply (direct contact or arcing), such as:
□ Do not leave construction hoist;
□ Do not touch the metal structure of construction hoist;
□ Inform outsiders do not close to and touch construction hoist;
□ Power off, then leave the construction hoist.
1.2.2.6 Visibility conditions
□ Use communication tools adapted to the site visibility conditions of
construction hoist, such as walkie-talkies or video system.
□ In the case of poor light, sufficient lighting should be provided.

1.2.3 Provisions associated with specific risks

1.2.3.1 Power supply


□ Cut off the power of construction hoist when the power supply is not
required.
□ Construction hoist power supply box should be turned off by application
key which is supervised by a specific person.
□ For the power box with frequency mechanism, wait at least 10 minutes after
a power failure. Then close the power box to start operation (capacitor within
frequency mechanism can discharge).
1.2.3.2 Hydraulics
□ Release pressure prior to the operations of hydraulic system of construction
hoist conduct, (Note: After the hydraulic unit is stopped, the pressure can still be
maintained). When there is injection oil spill, the immediate cessation of construction
work is required;
□ Do not manually check for leaks;
□ Do not smoke or use flammable devices near the unit with oil or grease
(reducer, gear drive systems, etc.);

1-9
Operation Instruction of SC Series Construction Hoist Use Principle

□ Do not fold or beat hydraulic hoses.


1.2.3.3 Chemicals
□ Chemical substances (grease, oil, paint, glue, solvents ...) storage and
operation should conform to the description of such products as well as special safety
requirements on the container. In particular, they cannot be stored in the cab.
1.2.3.4 Falling objects
Appropriate measures should be taken within the operational area of
construction hoist to prevent tools or fixed objects falling.
1.2.4 Provisions relating to the use of construction hoist at each stage
1.2.4.1 Transport
According to the conditions of transport and handling of construction hoist
and other components (such as: ground strength, climatic conditions, channel slope,
loading and unloading sites, etc.) determine the channel of construction hoist
installation site.
In road transport, for transport of ultrahigh parts like hoist cage and other
components should be set with warning device.
1.2.4.2 Site preparation
The used site should comply with all technical performance and installation
conditions of construction hoist.
1.2.4.2.1 Installation area of construction hoist
Before construction hoist installation, analyze the limits of the used site, such
as:
□ Air restrictions of the location, public buildings, other buildings, roads,
railways, rivers;
□ Other nearby tower crane, airport, power lines, electromagnetic launcher and
the like;
□ Site conditions, ground strength, ditch hole, slope, underground construction;
□ Air restrictions such as overhead transmission lines, telephone, cable and
other cables;
Determine the best location for construction hoist to ensure handling and use of
construction hoists.
1.2.4.2.3 Installation and removal
a) Preparation of installation and removal
□ Construction side of construction hoist should establish appropriate

1-10
Operation Instruction of SC Series Construction Hoist Use Principle

information management, listing the danger that might occur when installation /
removal, and adding masts, and the corresponding protective measures.
□ Before installation / removal and adding masts, know from the local
authorities about the weather situation. The wind speed does not exceed the
maximum allowable wind speed.
□ Map out some safety zone (storage area, tooling zone, etc.) during construction
hoist installation, removal, adding masts as well as testing, with clear signs
prohibiting unauthorized personnel from entering.
b) Installation / removal process
□ Install construction hoist in work lifting area, and don’t actuate the hoist
during the installation, removal, and adding masts.
□ For unconventional installation and removal (such as: the location and
construction of lift-related restrictions, when mounting and dismounting equipment
malfunction), please consult our company.
1.2.4.3 Repair and maintenance
a) Maintenance
□ During construction hoists abnormal operation or maintenance work, the
application clearly marked delineated safe area, prohibit unauthorized persons from
entering.
□ During construction hoist maintenance, the construction hoist should be
stopped work, and the establishment of appropriate warning signs on the main power
switch is demanded to prevent starting the construction hoist.
b) Maintenance
□ Do not use construction hoist during its maintenance.
□ For unconventional maintenance, please consult our company.

1.3 Safety Signals

1.3.1 Description

Safety or health signals with security or health-related instructions are for the
specific environment of construction hoist operation.
Depending on the circumstances, the signal may be a plate, a color / a light or
audible signal.
Safe signals are divided into five categories, and each category is indicated by a
color.

1-11
Operation Instruction of SC Series Construction Hoist Use Principle

□ Prohibition (red);
□ Warning (yellow or yellow / orange);
□ Provisions (blue);
□ Help and assistance (green);

1.3.2 Terms

Signal board: a description provided by a specific geometric shape, color,


symbol or graphic signal.
□Prohibition signal board: a prohibited act may cause or lead to dangerous.
□ Warning signal board: signal of a risk or danger.
□ Predetermined signal board: the provisions of a particular behavior.
□ Distress signal board or ask for help: to give or help with the rescue channel
recourse for instructions.
□ Prevent fire signal board: given the position of the fire extinguishing equipment
and instructions for evacuation routes when fire accidents.
□ Additional signal board: common use with signal boards, giving a supplementary
instruction to signal board.
□ Symbol or graphic: indicates a situation or a particular course of action shown,
with a signal on the board or a light-emitting surface.
□ Light signals: made of transparent or translucent material. Internal or rear
lighting, itself constitute a signal of a light emitting surface.
□ Audible signal: a particular sound signal issued by a special device, without the
use of artificial or synthetic sound.

1.3.3 Signboad
Warning signboard Table l.1
Signboard Implication Illustration

Danger Safety warning

1-12
Operation Instruction of SC Series Construction Hoist Use Principle

Attentions in operation
Attention
and use of hoist

Not entering before


Electrical danger
outage

Don’t cause spark or


flame and smoke near the
Fire danger
inflammable like paint, oil
or glue.

Not dropping objects from


Dropping objects
air in construction area

Prevent aerial personnel


Falling falling in construction
area

Not entering the rising


Crush
and dropping area of hoist

Enter the hoist after


Electric discharge ten-minute-waiting after
the hoist is discharged

1-13
Operation Instruction of SC Series Construction Hoist Use Principle

Read the Instruction


Use danger
carefully before use

Prohibition signboard Table l.2


Signboard Implication Illustration

prohibit unauthorized The authorized person is


persons from entering the qualified personnel

No starting No starting during


installation and
debugging

No closing the valve No closing the valve


during repair and
maintenance

1.3.4 Audible signal

The following dangers will be automatically prompted by the sound warning


device:
□ Construction hoists start: short sound;
□ Construction hoist up to the top limit switch: continuous tone.

1.4 Safety Control

Construction hoist console is equipped with a red mechanical locking


emergency stop button.

Press this button to stop all actions of construction hoist.


Emergency stop button can only be used in dangerous
situations.

1-14
Operation Instruction of SC Series Construction Hoist Use Principle

1-15
Operation Instruction of SC Series Construction Hoist Safety Rules

2 Safety Rules
For use of construction hoist, users should carry out safety supervision its whole
use process in accordance with the local relevant laws, regulations and safety
standards.

2.1 Safety responsibility of user

Before using construction hoist, managers, users and operators must carefully
read about, understand and master the entire contents of this manual. Besides, they
should exactly and seriously abide by and implement the provisions of this
Instructions considering safe production as the purpose.
User or operator of construction hoist must meet the following requirements:
□ Be qualified after training of relevant institutions and confirmed the relevant
certificate is qualified and effective.
□ Can understand and standards, regulations and safety procedures.
□ Be trained to understand, familiar with and master the entire contents of this
manual.
□ Have a wealth of operational experience, can endure high-altitude tension of
up-and-down running and manipulate safely and correctly.
□ Correctly and quickly respond to situations that may arise, to avoid accidents.

2.2 Safety requirements of installation and removal stage

2.2.1 Responsibilities

Construction hoist user should be responsible for safety of installation /


removal, and carry out it in accordance with the local laws, regulations and safety
standards.
Before installing construction hoists, workers should be carefully read,
understand and master the content of the Instruction and the install-and-uninstall
program details, as well as be familiar with the mechanical and electrical properties
and principles of construction hoist, especially should strictly abide by and implement
safety requirements for the whole process

2.2.2 Safety measures for preliminary installation and removal

□The construction team for construction hoist assembly / disassembly should


have an effective qualification certificate issued by related government departments

2-1
Operation Instruction of SC Series Construction Hoist Safety Rules

before they can undertake the assembly / disassembly operations of construction hoist;
operational personnel of various types post should also have the effective
qualification certificates issued by relevant government departments before taking a
job for construction hoist assembly / disassembly.
□The site for construction hoist installation / removal should be clean and
have warning signs to prohibit non-operating personnel to enter.
□ When construction hoist installation / removal, relevant departments should
arrange professional engineering and technical personnel to supervise and manage the
on-site safety and implementation of construction plan to ensure the implementation
of safety measures.
□ The lifting equipment used should be appropriate for the lifting load and in
excellent condition.
□The ground foundation for construction hoist installation should be capable
of bearing the prescribed load and in accordance with the local soil specifications for
construction.

2.2.3 Security measures for installation and removal

Install / disassembly operations of construction hoist are prohibited when


the wind speed exceeds l2.5m / s or a thunderstorm, snow and other
inclement weather.
□ One person is required to be responsible for commanding the installation /
removal process.
□ During installation / removal, someone should be responsible for controlling
/ monitoring the electrical control box.
□ During installation / removal, it is prohibited to operate construction hoist
by non-work-related personnel.
□ Drive box of cage must be moved to the top of the cage for cage running,
not in the cage.
□ For the installing boom on the top of cage, its max lifting load is 200kg, not
overloading. Cage load should not exceed the rated load of installation.
□ No one is allowed to stand under suspension.
□ Do not start cage when there is hung object on the installing boom.
□ In runtime of cage, the head of personnel, hands and shipped items are
prohibited protruding the cage fence.
□ Before total power is completely cut off, no one is allowed to be in the

2-2
Operation Instruction of SC Series Construction Hoist Safety Rules

undercarriage fence, guardrail or fell on top of or against the fence as well as in the
construction hoist channel, rack rails (standard section) and in the insecure area
surrounded by tie-in frame.
□ Don’t start the installation on cage top before the emergency stop button is
closed. Cut off the power supply at first.
□ Personnel who is not the qualified electrician should not perform electrical
wiring work. When carrying out such work, please ensure that power is removed.
□ After having installed the desired height of mast, all the connecting bolts must
be fully tightened and then start cage.
□ As required, construction hoist should be equipped with separate electrical
grounding and lightning protection devices.
□When the installation height of construction hoist is greater than l20m and
over a building; it should set the air obstacle lights.

2.2.4 Safety measures after installation

Construction hoist should not be put into normal use before acceptance test is
not adopted.
2.2.4.1Acceptance tests and inspections of construction hoist
Acceptance testing and inspection is necessary after installation is complete and
before being put into regular use in order to ensure the safe use of newly-installed and
greatly-changed construction hoist.
User of construction hoist should make sure that tests and inspection the
instructions for installing program are in line with the local relevant laws of
construction hoist, regulations and safety standards and regulations.
Inspectors should be present for all tests and inspections which should be carried
out under supervision of relevant departments.
2.2.4.1.1General tests and inspections of construction hoist
a) Inspections for mast and tie-in frame needs to satisfy:
□ Use and fixe mast for the set lifting height;
□ Position, size and carrying capacity of ground base should meet the requirements;
□ Mast and the rack are in good condition;
□ Installation of mast meets the requirements;
□ Rack is fastened as required;
□ Tie-in installation and tightening of bolt connection are as required;
□Free height of mast meets the requirements;

2-3
Operation Instruction of SC Series Construction Hoist Safety Rules

□ Installation of each limit device (touch block) meets the requirements.


b) Inspections for brace fence need to satisfy:
□Inner and outer position of fence meets the requirements;
□Each member of fence meets the requirements, without rust, damage or
deformation
□Electromechanical interlock device of fence gate is sensitive and reliable to meet
the requirements;
□Fixing bolts of race meet the requirements;
□Installation location of cable sleeve meets the requirements.
c) Checking the cage must meet:
□ Size and carrying capacity meet the requirements:
□ Structure meets the requirements without corrosion, damage or deformation;
□ Cage door and its door frame size, strength, electrical and mechanical interlock
which should be opened freely, meet the requirements;
□ Guide rollers and hook are installed in accordance with the requirements;
□ Cage floor meet the requirements without damage, non-skid;
□ Security fence at the top of the cage meet the requirements;
□ Installing boom is in good condition, and its mounting position o and strength to
meet the requirements.
d) Drive system checks must meet:
□ Drive system is mounted on the cage frame as required;
□ Drive gear is in good condition and engaging well with the rack as required;
□Fastening of rear wheel and gap at the back of the rack meet the requirements;
□ Worm and its group are in good condition. Lubricating oil type and level meet the
requirements;
□ Brake meets the requirements for specified functions.
e) Checking the cable guide must meet:
□ Cable retaining rack is installed in the correct position and the pitch meets the
requirements;
□ Rubber and spring sheet fixed on mast rack are in good condition as required;
□ Cable arm fixed to the cage meets the requirements;
□Models, specifications and connection and installation of cable meet the
requirements.
f) The electrical equipment must meet:

2-4
Operation Instruction of SC Series Construction Hoist Safety Rules

□ The voltage and frequency of used power supply meet the requirements;
□ Grounding resistance meets the requirements;
□ The device is in a good state of security as required.
g) Control system:
□ The main control system in good condition to meet the requirements;
□ All control components have suitable installation location, sensitive, reliable and
safe as required.
h)Full stroke condition of cage must be met:
□ The distance of the highest point of cage to mast top meets the requirements;
□The distance of the lowest point of cage to the ground meets the requirements;
□During operation, each limit switch of cage is sensitive and reliable and meets the
requirements.
2.2.4.1.2 Particular safety testing and inspection:
When general test and inspection procedures for construction hoist meet the
requirements, some special tests and inspections are still required to ensure the safe
use of construction hoists. Check the contents as follows:
a) The tests and inspections for anti-fall safety should meet:.
□ The anti-fall safety device should meet the requirements within the valid
calibration (anti-fall safety device is required to be tested at the testing calibration
once a year, and to be replaced every five years based on the date of manufacture on
the label.
□ Anti-fall safety device is installed in accordance with the requirements;
□ Drop test needs to be carried out for the rated load. Cage stopping slippage
distance at drop test should meet the requirements;
□After drop test, you must reset the anti-fall safety device;
□ Anti-fall safety seals meet the requirements.
b) Indicating symbols and manuals
□Warnings and indicating symbols of construction hoist are complete and meet
the requirements;
□ The driver should be equipped with a copy of this manual to consult at any
time;
□ Drivers should read, understand and grasp the meaning of warnings and
indicating symbols.
c) Final run test

2-5
Operation Instruction of SC Series Construction Hoist Safety Rules

Carry out the final run test and inspection according to this manual, which
should meet the requirements.
d) Final Report
After acceptance tests and inspections, submit the final report which should
contain concise summary trials and all faults found in tests, and explain all the work
required to do and before construction hoist is put into use.

2.2.5 Safety measures for acceptance tests and inspections

In the construction hoist during acceptance tests and inspection, you must take
certain security measures to ensure the safety of operating personnel and testing
personnel, especially when drop test, no one is allowed to be in the cage or brace
fence and ground manipulation is needed.

2.3 Periodic inspection and testing

2.3.1 Requirements of periodic inspection and test

Construction hoists should be regularly inspected and tested in accordance


with the local relevant laws, regulations and safety standards. In addition to these
criteria (or no such standards), the following requirements shall also be necessary for
periodic inspection and testing.
2.3.1.1 Responsibilities
a) Inspectors
Inspection and testing should be done by a qualified engineering and technical
personnel.
b) Security measures for inspection and test
Before function test, you must take certain security measures to ensure the
safety of operating personnel and testing personnel, especially when drop test, no one
is allowed to be in the cage or brace fence and ground manipulation is needed.
c) General inspection and test for construction hoists
□ All parts should be regularly tested. Test is required, when necessary, to
make sure all parts are safe for use.
□ Inspection and testing are carried out according to the time intervals in
“maintenance and repair” in the Instructions.
□ Adjustable wear parts should be adjusted timely; for wear parts and other
damaged parts which has been reached wear limit should be replaced using spare
parts or components produced by our company, and ensure that all replacement parts

2-6
Operation Instruction of SC Series Construction Hoist Safety Rules

have passed qualification safety inspection.


□ Any consequences caused by replacement of spare parts from other
manufacturers without our written confirmation, should be responsibled by the user.
d) Drop test for anti-fall safety device is required for inspection and testing at
least once every three months to confirm the anti-fall safety functions meet the
requirements. During the test, cage stopping slippage distance at drop test should
meet the requirements. Safety must be ensured in the drop test.
□ Before test, the motor brake function is intact.
□ Before test, hoist cage shall rise to a safe height to ensure it does not hit and
buffer spring during the test.
□ In test, no one is allowed to be in the cage or brace fence and ground
manipulation is needed.
□ After test, the anti-fall safety device must be properly and timely reset.

2.3. 2 Routine security checks

2.3.2.1 Responsibilities
User should be responsible for checking construction hoists daily.
The work undertaken should be performed in accordance with laws, regulations
and safety standards related to the country of construction hoist.
Before routine safety checks, personnel should be read carefully strictly abide by
the details in “daily security checks”.
2.3. 2. 2Security measures of daily security checks
□After a storm or strong typhoon, the construction hoist should be checked
about its key parts by professionals before the daily security check, and take the
necessary security measures.
□ Don’t operate the construction hoist if the wind velocity> 20m / s or mast or
cable is freezing.
□Don’t operate the construction hoist before confirming the “periodic
inspection and test” and “maintenance and repair” are finished.
□Don’t operate the construction hoist before confirming there is no obstacles
and staff within or nearby construction hoist channel.
□Don’t operate the construction hoist before confirming the routine safety
inspection for cage is finished.
□ Great caution is necessary when the cage running and routine security
check.

2-7
Operation Instruction of SC Series Construction Hoist Safety Rules

2.4 Operational safety

2.4.1 Responsibilities

User should be responsible for checking construction hoists daily.


The work undertaken should be performed in accordance with laws, regulations
and safety standards related to the country of construction hoist.
Before routine safety checks, personnel should be read carefully strictly abide by
the details in “daily security checks”.

2.4.2 Safety measures of operation

□Don’t operate the construction hoist if the wind velocity> 20m / s.


□Don’t operate the construction hoist if mast or cable is freezing.
□Don’t operate the construction hoist before confirming the “periodic
inspection and test” and “maintenance and repair” are finished.
□ Cage load and number of passengers must not exceed the rating value on the
label.
□ Not let the goods go beyond the cage.
□ After having added masts, the installing boom on cage top should be
removed.
□Other people other than the driver or cargo carrier are not allowed in cab.
□Don‘t operate the construction hoist before confirming all protection and
safety devices work properly.
□ Don’t operate the construction hoist before confirming there is no obstacles
and staff within the construction hoist channel.
□ When construction hoist is operated in cage, no people is allowed on top of
the cage.
□ When there is a failure or danger, you shall immediately report to the site
supervisor and don’t operate the construction hoist before the failure and danger is
not excluded.

2.5 Maintenance

2.5.1 Responsibilities

User should be responsible for checking construction hoists daily.


The work undertaken should be performed in accordance with laws, regulations

2-8
Operation Instruction of SC Series Construction Hoist Safety Rules

and safety standards related to the country of construction hoist.


Before routine safety checks, personnel should be read carefully strictly abide by
the details in “daily security checks”.

2.5.2 Security measures of maintenance

□ When carrying out any maintenance and repair work on the construction hoist,
in the channel or near these areas, the main power must be turned off.
□ When repairing the cage, drive system or security device, the cage needs to be
safely parked on the buffer spring. If there are counterweights, the cage needs to be
locked on the mast.
□ When testing the motor brake torque, the cage needs to be locked on the mast
and the main power to be cut off.

2-9
Operation Instruction of SC Series Construction Hoist Base Configuration

3 Overview and technical features


3.1 Overview
SC-type construction hoist is a construction hoist driven by gears and racks,
mainly for the people and cargo transport for construction of high-rise buildings. Its
working-level is A6.
This construction hoist is easy to be installed and removed and can be increased
in height with the increase of the building height.
SC-type construction hoist has a very reliable mechanical and electrical safety
system and is safe and efficient vertical transportation equipment.
Construction hoist model is composed by a group, type, characteristics, main
parameters and variations and updating code.

Model described as follows:

变型更新代号:用大写汉语拼音字母表示
主参数代号:额定载重量×10- 1 ,kg
特性代号:对重代号或导轨架代号
型代号:C-齿轮齿条式
组代号:S-施工升降机

Main parameter code: single-cage construction hoist is only marked with a


number and double-cage construction hoist with two numbers which are separated by
the symbol “/”. Each number shares a rated load code of cage;
Characteristics Code: symbols that represent the two main characteristics of
construction hoist.
a) Counterweight code: the construction mast is marked with a D if it has
counterweight; if it doesn’t, the D is omitted;
b) Mast code: pitched or curved racks of mast are marked with Q, and when the
mast is two columns, it is labeled as E;
Model designation Example:
SC100 represents a general single-cage construction hoist, with load capacity of
1000kg;

3-1
Operation Instruction of SC Series Construction Hoist Base Configuration

SC200/200 represents a general double-cage construction hoist, with load


capacity of 2000kg of each cage;
SC200/200BZ represents a medium-speed frequency construction hoist with
double cages and each cage load capacity is 2000kg;
SC series construction hoist is a new generation of construction hoist products
designed by XCMG Construction Machinery Co., Ltd. It has the advanced technical
performance, safety and reliability, easy maintenance and other notable features. It is
the best vertical transportation equipment for modern construction.
Based on computer-aided design, the hoist product is more excellent for its
advanced technology performance, safe and reliable work and compact rigid structure,
compared with conventional construction hoists. It is also featured with a beautiful
shape, components lightweight, easy accessibility, high applicability, widely used and
so on. The product can be combined into a variety of types according to the needs of
users, including: standard and non-standard cross-section; weight ranging from
1000kg to 2000kg; its running speed is 36m / min. Especially after the installation of
frequency control functions and PLC control program, it can achieve the advantages
of 0 ~ 96m / min variable speed and automatically selecting the layer, leveling, so as
to meet the different demands of users.
The product has the following salient features:
It has complete and reliable safety device, an anti-falling safety device with
national patent technology, and its high reliability contribute to rank it first among
similar products.
Modular design: different combinations can be combined into construction hoist
with different speeds and weights. Standard, practical degree of common product has
been greatly improved.
It run smoothly and is comfortable for ride. Due to its drive unit is placed above
the top of the cage, so the hanging cage space is increased. And the mechanical
vibration reduced so that it is more stable for transmission and creates construction
workers a comfortable and spacious working environment.

3-2
Operation Instruction of SC Series Construction Hoist Base Configuration

3.2 Performance parameters


Table 3.1performance parameters of SC200/200FS1
No. Item Unit Parameter Remark

1 Rated load Kg 2×2000

2 Rated erection load Kg 2×1000

3 Rated speed m/min 0~50

4 Maximum lifting height M 260

5 Cage size (L×W×H) m×m×m 3.2×1.5×2.2

6 Power voltage V 380±5% 50Hz

7 Motor power kW 2×2×11/18.5

8 Power supply power kVA 2×2×39.5

Main chord
weight
thickness
9 Mast weight Kg 650×650×1508mm
4.5 145
6.0 160
Cage weight (including
10 Kg 2×1400
electrical control system)

11 Drive system Kg 2×450

12 Type of safety device SAJ40-1.2

3.2 Introduction to construction hoist principles

SC series construction hoist is commonly divided into two types: cable-drum


and cable-pulley. The product mainly includes: mast (rail racks), drive system,
electrical system, anti-dropping security device, limit devices, electrical control box,
resistance box, hoist cage, power boxes, brace rails, cable sleeve, cable retaining rack,
tie-in frame, cable bracket, installing boom, cable car system.

3-3
Operation Instruction of SC Series Construction Hoist Base Configuration

3.3.1Mast (rail rack):

Rack rail, the running track of construction hoist, is the bolted masts (each
1508mm high) by the 8.8-class M24 × 230 high-strength bolts (installing
pre-tension torque of bolt not less than 300N • m). The mast section is welded from
seamless steel tubes or pipes, angle iron, or cold-formed steel, welded steel pipes. It is
equipped with removable racks (one rack for the single-cage and two racks for the
double-cage) each of which is tightened by three inner hexagonal screws. According
to the different mounting height the main chord thickness of mast section is also
different.
For easy installation and positioning of mast, there are spigots welded at the
lower end of four main chords of mast, and the rack has a cylindrical pin at its bottom.
Main chord center section of mast is 650 × 650mm square cross-section. Rail rack is
attached to the building by tie-in frame.

3.3.2 Drive System

Drive system includes a drive body and the drive unit. The drive body is a
component to connect the driving devices into an overall structure, and it will
transmit the driving force of drive unit to the cage to make it run up and down.
Connecting bolts for drive body and drive unit are 8.8-class high-strength bolts.
As the power part of running construction hoist, the drive unit is working is a
group or several groups at the same time to run the construction hoist weight and
hanging cage load (or construction workers) up and down.
The drive unit is composed by the drive gear, reducer, coupling (plum-shaped
elastic member), motor (with brake) and other components.
The reducer is arc cylindrical worm reducer, with a compact structure, high
carrying capacity, high mechanical efficiency, long life, smooth operation and so on.
Its coupling is flexible jaw type and between the couplings there are two elastic
elements (polyurethane rubber) to reduce the impact and vibration in runtime.
Motor is the disc brake three-phase asynchronous motor for crane. Its brake
electrical magnet can automatically track the wear of brake disc torque of which is
adjustable.
Drive system of variable-frequency construction hoist is equipped with
frequency control system, improving the braking stability; stepless speed can be
achieved within a certain range; the control system can lower the starting current,

3-4
Operation Instruction of SC Series Construction Hoist Base Configuration

reduce the mechanical wear and extend the life of wearing parts, with increased work
efficiency and energy conservation.

3.3.3 Electrical system:

Electrical system is a control port of mechanical operation of construction


hoist and all the actions are manipulated by the electrical system. Electrical system
includes an electrical control box, resistance box, power supply box, cab console, the
main control cables and various limit switches.

3.3.4 Anti-fall safety device:

It consists of a circular cone, brake cone, spring, and centrifugal block and so on.
When a cage over speeds, the centrifugal weight will overcome the pressure of spring,
causing the brake cone to rotate and the shaft joined to brake cone will forward
spirally. The friction force between the brake cone and crust will be increased
gradually ensuring that the cage is stopped smoothly. Meanwhile the stoke switch
acts to power off the cage to keep personnel and equipment safe.
Anti-fall safety device are two kinds: single-tooth and tri-teeth one. The of
tri-teeth anti-fall safety has same brake principle as the single-tooth’s, but has a
relatively large braking torque.
The safety device is adjusted for the required excitation speed and sealed with
lead so it is prohibited to open the safety device without authority.
Security nameplate is marked with the period use, not exceeding one year.
The safety device needs to be sent to the manufacturer or to testing organizations to
re-check and calibrate. Its service life is five years.

Figure 3.1

3-5
Operation Instruction of SC Series Construction Hoist Base Configuration

3.3.5 Limit device:

Limit device includes up and down limit switches and extreme limit switches. For
frequency construction hoist it also includes up and down limit switches of
deceleration.
The up-and-down limit switches act automatically to cut off the power to ensure
the cage to run at a specified location. Up and down limit switches of deceleration
make sure that the speed of construction hoist is reduced from high to low.
Limit switches guarantee the cage be stopped during running to the up and down
limit, through immediately cut off the main power supply leading to failure of the
limit switch, so that the cage not running over-roof and hitting bottom.
Limit switch is not the auto-resetting type, so it must be reset manually.
Users should always check the position accuracy of all limits, to ensure that the
limit and limit switches are accurate in action.

Figure 3.2

3.3.6 Electric control box:


Electric control box is the heart of construction hoist electrical system, and
inside it are components shown in Figure 3.3: running contactor, control transformer,
thermal protection, inverter (VVVF construction hoist) and off-phase and phase
sequence protection relays. Electronic control box is mounted inside the cage. The
electrical control box of variable-frequency construction hoist is usually installed on
the top of the cage.

3-6
Operation Instruction of SC Series Construction Hoist Base Configuration

3.3.7 Resistance Box


Resistance box is generally fixed on the cage top fence, and the resistance is
used to consume energy reacted to transducer when the frequency construction hoist
runs up and down.

3.3.8 Cage:
Cage is a steel structure, run along the mast rail frame by cage rollers. It has
entrance and exit door which are vertical drawer door.
On cage top is equipped with a movable door, through a dedicated ladder,
personnel can be easily climb to the top of the cage for installation and maintenance
in which the cage top can be considered as a working platform, surrounded by the
guardrails.
Fitted with an electrical interlock, the cage will stop working when the cage
door is open to ensure the safety of personnel in hanging cage.
There is a cab for the driver at one side of the cage. All operation switches are
located in the cab.
There are 14 guide rollers running along the mast rail frame cage.

3.3.9 Power Box:

Power Box is the power supply portion of construction hoist control and
mounted on the brace fence.

3.3.10 Brace fence:

Brace fence includes two parts: chassis and guard rail:


Brace is a welded structure of profile steel and steel plate, surrounded by
protective fence coupled with the ground, and the central part is the base seat of mast
frame. It can withstand all the loads from the construction hoist. In installing, the base
chassis fastened together with base by embedded bolt parts.
Guard rail: a welded structure of profile steel, steel plate and steel mesh will
surround the host part of construction hoist to form a closed area, so that there is no
one enters the area during operation. At the entrance of protective fence there is a
fence door which is equipped with mechanical and electrical interlocks.
The current chassis fence is the combined type. The cable reel and cable car type
chassis fence can be interchanged by increasing the bending steel shown in the
following Figure. The doorsill height of 450 and 900 can be adjusted to each other.节

3-7
Operation Instruction of SC Series Construction Hoist Base Configuration

Figure 3.4 Assembly of brace rails

3-8
Operation Instruction of SC Series Construction Hoist Base Configuration

Figure 3.5 Overlook view of brace rails

3.3.11 Cable sleeve:

Cable sleeve is used to collect and release cable part. Due to the great impact
of wind, it is usually used only for installation height of not more than 100m and the
wind force is small.
When the cage is running upward, the cage drives the main cable inside the
cable sleeve upward;
When the cage is running downward, the main cable is slowly collected into
cable sleeve, to prevent accident caused by the main cable scattered on the ground to
be rolled.

3.3.12 Cable retaining rack:

Cable retaining rack is used to ensure the safe operation of cable. When the hoist
is in operation, please ensure that the cable is in the retainer of cable retaining rack to
prevent the cage is twined with other equipment nearby during operation.
When installing the cable retaining rack, make sure that the cable retaining rack
and cables can be wound smoothly through the retainer.

3.3.13 Tie-in frame:

The tie-in frame is the coupling member between mast fames and buildings, in
order to maintain the stability of mast frame and the whole structure of construction
hoist.

3.3.14 Cable bracket:

Cable bracket is the drag device carrying the main cable to run up and down.
The main cable is drawn by the cable bracket, safely through cable retainer to prevent
the cable from being scratched to any accident.
Cable bracket can pick the main cable out the fence so that the main cable is
securely collected into cable sleeve.

3.3.15 Installing boom:

Installing boom is an indispensable component to achieve adding and reducing


mast.
Having installed the foundation, you can use the boom to add masts on the top of

3-9
Operation Instruction of SC Series Construction Hoist Base Configuration

the installed mast.


The boom, the boom can be used to remove the mast frame sequentially from
top to bottom in the demolition work.

1. The rated load of installing boom is 200kg. Don’t overload;


2. Don’t hanging heavy objects when the construction hoist is in operation.
3. After the construction hoist has been installed or dismounted, the
installing boom must be removed from the top of the cage.

3.3.16 Cable car system:

When the construction hoist is high, it will be greatly influenced by supply


voltage, wind and gravity so it can adopt a cable car system, which is mounted on at
the bottom of the cage, simple in structure and easy in installation. The mast rack is
the running track not only of cage but also of cable car so the wind impact on it is less.
Hence it is used widely and there is still a kind of combined type of cable car and the
right and left cages are interchangeable.

Figure 3.6 Cable car

3-10
Operation Instruction of SC Series Construction Hoist Base Configuration

4 Base configuration
Before use, calculate the load on base and base configuration according to the
Item 5.1.10 “Base of construction hoist should be capable of bearing all load at the
worst condition.” in Standard (GB/Tl0054-2005): Construction Hoist.

4.1Calculation of base bearing capacity P

P  nG
In formula P: foundation bearing capacity (N)
n: the safety factor n = 2, considering the running dynamic load, wind load
and impact of counterweight error on the base
G = cage weight (including drive system) + cage rated load + chassis frame
fence weight + rack rail weight + accessory weight + tie-in frame weight +
counterweight weight (kg)
When converted into gravity: 9.8 · G (N) that is:
P=0.02·G(kN)
Calculation example:
Example: Installing SC200 / 200-type construction hoist to erection height: 150m;
ⅡD type tie-in frame;
Base Model CM6238
Cage weight (including drive system): 2000 × 2 = 4000 kg
Cage rated load: 2000 × 2 = 4000kg
Chassis guardrail weight: 1300kg
Rail frame weight: l45 × 100 = 14500kg
The weight of power cable, the cable guide, fasteners and other accessories is
approximately 2000 kg,
ⅡD tie-in frame weighs approximately 146 × 16 = 2336kg
Counter weight: O kg (None)
Therefore: P = (4000 + 4000 + 1300 + 14500 ++ 2000 + 2336) · 0.02
= 562.72kN
Conclusion: The maximum load can be carried by the concrete foundation and
ground foundation is 563kN;
Area set according to CM6238 type base is 23.56 m 2 , so the maximum bearing
capacity of concrete foundation and ground foundation is 562.72 /
23.56≈23.88≈0.024 MPa.

4-11
Operation Instruction of SC Series Construction Hoist Base Configuration

When the rail frame height ≤100m, bearing capacity ≥0.10MPa;


100m <rail frame the height ≤300m, bearing capacity ≥0.15MPa;
300m <rail frame the height ≤500m, bearing capacity ≥0.2MPa;

4.2 Selection of configurations of concrete foundation


Alternative configurations of concrete foundation:
Alt. 1:
High门坎高
sill
Concrete slab on the ground
Ground
地面
Advantage: no draining required
Disadvantage: high sill 方案1
Alt. 1
Alt. 2:
Ground
地面
High门坎高
Concrete slab level with ground. sill

Advantage: draining required.


Disadvantage: Sill, used in combination with a
simple wooden bridge which is built up to the level of 方案2
Alt. 2
the sill. Ground
地面

Alt. 3: High 门坎高


sill

Concrete slab below ground level。


Advantage: no sill between the ground and cage
Disadvantage: high corrosion if water remains 方案3
Alt. 3
on the foundation. Requires careful draining.

When choosing the base configuration, users should make decisions


dependingon the actual situation at construction site.

1. The sill height is subject to the changes of cable guide devices. The
sill height is 450mm and the sill height of cable car type is 900mm.
2. Base should be produced by users at least one week before the
installation of hoist.

4.3 Base selection related to tie-in frame


a) Base model: CM3238 (applicable to I-Type tie-in frame)

4-12
Operation Instruction of SC Series Construction Hoist Base Configuration

Figure 4.1
Distance from
Model Specification A(mm) B(mm) C(mm)
base to wall L
I -Type tie-in Left Right
SCl00 3.2×1.5m
frame: 3200 3800 cage cage
SC200 3.0×1.3m
1800~2500 2200 1000

b) Base model: CM4438 (applicable to Ⅱ –Type and Ⅲ–Type tie-in frame,


without cab)

Figure 4.2
Distance from
Model Specification A(mm) B(mm) C(mm)
base to wall L
ⅡD, Ⅲ-type Left Right
SCl00
tie-in frame: 3200 3800 cage cage
SC200
3.2×1.5m 3000~3600 2200 1000
3.0×1.3m Ⅳ-type tie-in
SCl00/100
frame 4400 3800 2200
SC200/200
1800~2100

4-13
Operation Instruction of SC Series Construction Hoist Base Configuration

c) Base model: CM6238 (applicable to Ⅱ –Type and Ⅲ–Type tie-in frame, with
cab)

Figure 4.3
Distance from base A(mm
Model Specification B(mm) C(mm)
to wall L )
ⅡD, Ⅲ-type tie-in Left Right
SCl00
frame: 4000 3800 cage cage
SC200
3.2×1.5m 3000~3600 3000 1000
3.0×1.3m Ⅳ-type tie-in
SCl00/100
frame 6200 3800 3000
SC200/200
1800~2100
d) Middle pre-embedded frame figure of concrete base

Figure 4.4

4.4 Cautions for making concrete base

a) The ground endurance under the concrete foundation should satisfy:


When the rail frame height ≤100m, bearing capacity ≥0.10MPa;
100m <rail frame the height ≤300m, bearing capacity ≥0.15MPa;

4-14
Operation Instruction of SC Series Construction Hoist Base Configuration

300m <rail frame the height ≤500m, bearing capacity ≥0.2MPa;


If it fails to reach this requirement, the ground under the foundation should be
reinforced.
b) Beside the concrete foundation, the gutters should be set up according to
conditions of the construction site.
c) The embedded seat (the base bolt hook) of concrete foundation should be fixed
with steel mesh piece in the foundation.
d) During pouring concrete foundation, the bolt hole of embedded frame should
be temporarily covered with boards or plastic plugs or other fillers to prevent
the concrete into it, and the bolt end surface is 1mm higher than the concrete
surface.
e) The production of concrete foundation should be performed in accordance with
“Construction and Acceptance of Reinforced Concrete” (GBJ204).
□ The steel bar of concrete foundation shall not be less than l2mm, its grid is
200mm, and its material: HPB235 or HRB335.
□ The level of concrete foundation poured should be greater than C30 grade.
□The construction technology and strength of concrete foundation should meet
the requirements of construction hoist in “Construction and Acceptance of
Reinforced Concrete” (GBJ204).
f) Besides, the users should also fabricate the concrete foundation referring to the
relevant norms and standards of local country-or-region.

4-15
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

5 Rail rack and tie-in frame


5.1 Configuration of guide frame

If the erection height of hoist is different, the configuration of masts is also


different as well as the thickness of mast main chord. Conversion section is
needed to connect masts with different thickness of main chord.
Examples for selection of mast specification:
If the mounting height of rack rails is 500m, according to “5.1
Configuration of Thickness of Mast Main Chord”:
Φ76 × 4.5, mounting height of 140m, mast section number is 93 (including a
conversion section)
Φ76 × 6.0 mounting height of 120m, mast section number is 80 (including a
conversion section)
Φ76 × 8.0 mounting height of 120m, mast section number is (including a
conversion section)
Φ76 × 10.0 mounting height of 120m, mast section number is 500 / 1.508- (80 +
80 + 93) = 79
If the height of the rail frame exceeds 500m, the standard
configuration of the main chord thickness is as the one provided
by us.

In order to distinguish the masts of different thicknesses conversion section, it


has a number and a small piece with different colors on the non-rack mounting
surface at each intermediate section of mast. So please be careful in installation!
Specifically identified as follows:
1. Mast section of Φ76 × 4.5 makes no treatment
2. Blue paint around the number 6 of thickness is required for mast section of
Φ76 × 6.0;
3. Orange paint around the number 8 of thickness is required for mast section of
Φ76 × 8.0;
4. Green paint around the number 10 of thickness is required for mast section of
Φ76 × 10.0.
Conversion section:
1. On conversion section of 4.5 ~ 6.0mm, around number 4 is red paint

5-1
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

(galvanized mast) or white paint (painted mast), and around number 6 is blue.
2. On conversion section of 6.0 ~ 8.0, around number 6 is blue paint and number
8 is orange paint.
3. On conversion section of 8.0 ~ 10.0, around number 8 is painted with orange
color and around number 10 is green.
Take the Φ76 × 6.0 mast and 4.5 ~ 6.0mm conversion section as the example,
specifically identified as follows:

The number is
colored

The number is
colored

The number is colored

Mast with wall thickness of 6mm Conversion section of 4.5mm-6mm

Figure 5.1

5-2
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

Configuration of main chord thickness of mast:

Conversion section

Conversion
Conversion section
section

Conversion
Conversion
section
section
Conversion section

Figure 5.2
Note: H is the erection height of rail frame

5-3
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

5.2 Type and selection of tie-in frame

The tie-in frame of construction hoist has four types to meet the user's actual
needs for construction site (each type also has a variety of specifications can be
combined) .Various types of tie-in frame are suitable for:
a) Ⅰ-type tie-in frame: only for single-cage construction hoist.
b) Ⅱ-type tie-in frame: for single-cage or double-cage construction hoist, either
with counterweight or without counterweight, and either with cab or without cab.
When there are scaffolds or connection platforms, the tie-in frame can replace the Ⅲ
–type to use.
c) Ⅲ-type tie-in frame: use scope is same as the type Ⅱ. The tie-in frame must
be configured with vertical rod of passage, short front support and bridge link (effect:
to place the connection platform directly on rack rails).
e) Ⅳ-type tie-in frame: for single-cage or double-cage construction hoist without
counterweight and cab.
For special demands, please contact us.
Tie-in frames figure
Ⅰ-type tie-in frame

Chassis fence

Lifting cage

5-4
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

Mainly suitable for: the wall attached is close and the cage load of single-cage hoist is
not too large
Cage
L(mm) A1(mm) A2(mm) B(mm)
specification

3.2×1.5m 1640 1800 1000~1570


1800~2500
3.0×1.3m 1540 1700 1000~1570

Ⅱ-type tie-in frame(ⅡD-type tie-in frame is recommended)


Chassis fence

Lifting cage

Lifting cage

5-5
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

Cage
Type L(mm) A1(mm) A2(mm) B(mm)
specification
ⅡA 2800~3200 1500
ⅡB 3000~3600 1750
3.2×1.5m 1640 1800
ⅡC 3400~4200 2000
ⅡD 3000~3600 1500
ⅡA 2800~3200 1500
ⅡB 3000~3600 1750
3.0×1.3m 1540 1700
ⅡC 3400~4200 2000
ⅡD 3000~3600 1500

Ⅲ-type tie-in frame

Lifting cage

Lifting cage

Chassis fence

5-6
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

Cage
L(mm) A1(mm) A2(mm) B(mm)
specification

3.2×1.5m 3000~3600 1640 1850 1200~1600

3.0×1.3m 3000~3600 1540 1750 1200~1600

Ⅳ-type tie-in frame

Lifting cage

Lifting cage

Chassis fence

Cage
L(mm) A1(mm) A2(mm) B(mm)
specification
3.2×1.5m 1800~2100 1640 1800 650
3.0×1.3m 1800~2100 1540 1700 650

5-7
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

5.3 Connection of tie-in frame and attached wall

Sample
[例1: 1]
to connect
与 墙上 的 with
预 pre-embedded
埋 件相 连 接 parts on wall Sample 2: to fix with bolts across the wall
[例 2 ] 用 穿 墙 螺 栓 固 定

[ 例 33:] 预
Sample to 埋
fix螺with
栓 pre-embedded bolts [例
Sample 4: to 4 ] with
weld 与钢 结 构structure
metal 焊接

Figure 5.3
1. If necessary, the users need to select the connection form of
tie-in frame and wall and to prepare connecting bolts the
strength of which should be able to withstand force F calculated
according to formula in Section 5.5 (optional: M24 bolts strength
of 8.8 class);
2. Do not use expansion bolts for connection of tie-in frames and walls;

5-8
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

5.4 Maximum mounting pitch and maximum height of the boom end of tie-in
frames

5.4.1 Installation ofⅠ-type, Ⅱ-type and Ⅳ-type tie-in frames and


cable retaining rack (cable car type)

Figure 5.4
1. The maximum distances of Ⅰ, Ⅱ, Ⅳ-type tie-in frames should
be in accordance with Table 5.1
2. When the mounting height of rail frame is more than 150m, it’s
better not to use Ⅰ and Ⅳ-type tie-in frames

5-9
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

3. The mounting pitch of the cable-drum tie-in frame is identical with the
cable-pulley type.

5.4.2 Installation ofⅢ-type tie-in frame and cable retaining rack


(cable car type)

Figure 5.5
1. The maximum distance of Ⅰ-type tie-in frames should be in
accordance with Table 5.1
2. When the mounting height of rail frame is more than 150m, it’s
better not to use Ⅲ-type tie-in frame
3. The mounting pitch of the cable-drum tie-in frame is identical with the

5-10
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

cable-pulley type.

All kinds of tie-in frame should be attached to the wall at specified intervals. The
largest interval of tie-in frames L1 and the maximum height of the boom end L2 are
shown in Table 5.1:
Table 5.1 The largest interval of tie-in frames L1 and the maximum height of the
boom end L2

Tie-in frame type


Ⅰ-type Ⅱ-type Ⅲ-type Ⅳ-type
Item
Rack rail height≤100m 9 10.5 10.5 10.5
Max 100m<Rack rail height ≤150m 7.5 9 9 9
interval
L1 (m) 150m<Rack rail height≤300m 9

Rack rail height≥300m 7.5

Rack rail height≤100m 7.5 7.5 7.5 7.5


Max 100m<Rack rail height≤150m 6 7.5 7.5 7.5
height
L2(m) 150m<Rack rail height≤300m 7.5

Rack rail height≥300m 6

5.5 Calculation of force F of tie-in frame to wall

Users should also confirm the force of tie-in frame on pre-embedded parts and
bolts of building to select right parts and bolts (generally high-strength M24 bolts of
8.8 class) when planning the configuration of construction hoist according to Table
5.1 of The Largest Interval of Tie-in Frames L1 and The Maximum Height of Boom
End L2 and L and B values of tie-frames. At the same time, it is required to collate
the force on attached walls, beams or cylinders to ensure that the adhesion is safe and
reliable.
Its force F is calculated according to the following formula:
F=L×60/B×2.05(KN)
For example:
ⅡD-type tie-in frame,

5-11
Operation Instruction of SC Series Construction Hoist Rail Rack and Tie-in Frame

Tie-in interval B=1500,Tie-in distance L=3200,


So F=3200×60/1500×2.05=62.44KN

5-12
Operation Instruction of SC Series Construction Hoist Installation and Debugging

6 Installation and debugging


Prior to installation, you should learn more about the operating instructions
and installation personnel must be trained and have the related operating certificate.

6.1 Installation

a) Basis production (referring to Chapter 4 Base);


b) Preparation before installation;
c) Safety training before installation;
d) Installation of chassis, buffer spring and four bottom masts;
e) Installation of chassis guardrail;
f) Installation of cage, drive system, roof rails and cage boom;
g) Increasing the height of the rail frame to 15m (install a set of tie-in frame at the
same time);
h) Installation of electrical control system and overload protection;
i) Installation of limit cam at the bottom of rail frame and commissioning of
power-driven hoist;
j) The whole debugging;
k) Drop test;
l) Heightening the rail frame (install tie-in frame at the same time) and installing
of limit cam at the bottom of rail frame;
m) Installation of counterweights (for hoist with counterweight);
n) Installation of cable guide device;
o) Installation of floor call system;

6.2 Preparations before installation

The following preparations are needed to ensure fast installation:


a) To ensure that the selected construction site meet the relevant safety standards
and specification requirements and have been tested and qualified by relevant
organizations and obtained permits to detect.
b) To ensure that the power, lighting, lifting equipment and other necessary tools
and instruments needed by construction hoist at the construction site are ready;
roads and venues are as required for transport and park.
c) Users should use the embedded parts of tie-in frame and related standard parts
provided by us.

6-1
Operation Instruction of SC Series Construction Hoist Installation and Debugging

d) Before installation, users should check that whether there are collisions or
deformations occurred in storage and transportation process, and if there are,
repair or replace instantly to make sure there is no defect.
e) As relevant regulations and requirements, protective grounding device is
needed and the grounding resistance ≤4Ω.
f) Keep the distance from power supply box to power box on construction hoist
chassis fence as short as possible, not exceeding 20m generally. Each cage is
equipped with a copper cable ≥25 ㎜ 2. If the distance is too long, increase the
cross-sectional area of cable to the appropriate to keep quality of power
supply.

The power supply voltage of construction hoist in use should be


controlled within the range of 380V ± 5%.

g) When starting the repeatedly used construction hoist, users should maintain
all the parts to a good condition according to Chapter 9- “Maintenance”.
Specifically: to conduct a comprehensive inspection for all structural parts for
deformation, damage and the like; to repair and replace the parts needed to be.
h) Before installation, users shall prepare 2 to 3 sets of attachment and the
cable guide devices with complete fittings and standard parts.
i) If there are other crane equipment assistant for installation (such as tower
cranes, mobile cranes, etc.), it needs to assemble four to six rack rail sections
(mast) on the ground at first by special bolts of M24 × 230, cleaning the pipe
ends and rack ends and lubricating with grease for pipe ends.
j) Necessary auxiliary equipment: one truck crane of 5t or above (available in
site), one theodolite.
k) Parts require to be prepared by users:
□ Produce the base in accordance with the requirements and some steel
gasket of 2 ~ 12mm thick inserted into the chassis frame to adjust its
verticality;
□ Prepare dedicated power supply box and box on chassis fence, the
matching cables as f);
□ In addition to special tools attached with construction hoist, users also
need a set of installing tools.

6-2
Operation Instruction of SC Series Construction Hoist Installation and Debugging

Figure 6.1
Note: the tools prepared by users

6.3 Installation

6.3.1 Precautions for installation

a) Comply with Ten Disciplines for Safety Producing after access to the site;
b) Safety warning area at construction site should be set up with someone to
guard;
c) Installing and operating personnel are not allowed to wear hard-soled shoes or
high heels and should wear tight clothing and safety belts;
d) Personnel for aerial operations like installation and removal of guide frame
(mast), must find a secure and proper position, fasten the
safety belt and hang up the insurance hook;
e) In installation process of construction hoist, the bolts,
axle pins, cotter pins and other fasteners should not have
defects and scrapped ropes, cranes and other equipment shall
not be used;
f) Before installing, you must be familiar with the entire
contents of the chapter 2.2 “Safety Requirements of
Installation and removal” and comprehensively understand
the mechanical and electrical properties of each part of
construction hoist;

6-3
Operation Instruction of SC Series Construction Hoist Installation and Debugging

Figure 6-2
g) Don’t replace electrical wiring of hoist without permission;
h) Before installation, clear up the rust and burrs at connections of mast, tie-in
frame, such as interfaces, pin holes, screws, etc. and lubricate these parts and racks
with the appropriate greaser to ensure rolling members adequately lubricated and in
flexible rotation;
i) Don’t install or uninstall the construction hoists in bad weather, like wind
speed over l2.5m / s, thunderstorm days, or snowy weather.
j) It is prohibited to install at night or relevant personnel is drunk;
k) In runtime of hoist, the head of personnel, hands and shipped items are
prohibited protruding the cage fence. Installation personnel and goods are prohibited
rely on the cage top fence;
l) If someone is working in the rail rack or tie-in frame, it is prohibited to start
hoist.
m) When installing the hoist, the control box must be
placed at the top of the cage. It is prohibited to operate it
in the hanging;
n) For the installing hoist, don’t overload.
o) In installation hoist by using the boom, no
overloading is allowed and the boom can be only used to
lift parts of installation and removal, not for other
purposes. During the hoist is running it is prohibited to
hang object on the installing boom;
Figure 6-3
p) Don’t forget to tighten the bolts for mast and tie-in frame;
q) The concrete foundation used must be finished the specified concrete
strengthening and solidification cycle.

6.3.2 Installation of chassis, bottom mast and chassis fence

a) Clean the base surface;


b) Place the chassis to its installation location, determine the installation position
and direction leveling the chassis plane (with leveling instrument), and
connect the chassis with the embedded parts of foundation block by M30 ×
180 bolts but not tightening temporarily;
c) Install one mast (usually without the rack and before installation clean the

6-4
Operation Instruction of SC Series Construction Hoist Installation and Debugging

joints and pins of pipe ends of mast and add a small amount of grease; please
note the direction of the rack in installation);

bolt

Main chassis

Pre-embedded frame of base


Figure 6-4
d) Install three to four mast sections in the same way and insert the steel gaskets
between base chassis and concrete base as
shown in the figure. Adjust the level of the base
chassis (with a gradienter for correction) and
measure and adjust the rack rail verticality using
a theodolite and gradienter to ensure the
verticality of each riser of rail rack in the two
adjacent directions ≤1 / 1500. After inspection,
tighten the connection bolts of chassis and
pre-embedded parts of base with 600N · m
pretention force; Figure 6-5
e) Connect the main chassis with assistant chassis
by the M16 bolts, using the same method fill up the assistant chassis with steel
gasket;
f) Bolt the buffer spring device on the buffer seat.
g) Connect the rear fence of chassis fence, the side rails, door frames and the
middle case respectively with main chassis and the assistant chassis by M10
bolts and don’t tighten temporarily.
h) Install the door support and adjust the verticality of the door frame so as to the
verticality in the two adjacent directions ≤1 / 1000; adjust the verticality of
rear and side fences and tighten all bolts.
i) Install the fence gate, door counterweight and door counterweight slide way;
j) Install the cam of hanging cage door and the fence door lock. Adjust the

6-5
Operation Instruction of SC Series Construction Hoist Installation and Debugging

distance between the outer fence and the door lock so that the door lock can
lock the outer fence.
k) Install the power box on middle case of the chassis fence.

Door Side fence


support

Rear fence
Outer fence door

Side fence

Door frame

Power box

Hoist base

Figure 6.7

6.3.3 Installation of lifting cages, drive system, roof rails and installing boom
a) Put a sleeper or other steel materials on the chassis fence (height greater than
the height of the spring cushioning device);
b) A mounting staff needs to stand on the top of rack rails rail rack, directing
and guiding the alignment of cage and drive systems. Place the lifting cage from
the top of rack rails slowly on the prepared sleep or steel material using crane
equipment (truck crane or tower crane). Then install another cage in the same
way.
c) Release the brakes for three motors on the drive system, and the method is:
tighten the two nuts on the brake (be sure to make the two nuts parallel
precession) until the brake disc can be easily pulled up if the brake is released;
use the lifting equipment to drop the drive system slowly from the cage top.

6-6
Operation Instruction of SC Series Construction Hoist Installation and Debugging

Loosen the nuts for three motors of drive systems to reset it when the
connection ear plate on the drive system is 400mm from that of cage, using the
same method to position another drive system.

Tighten the nut

Motor brake

Figure 6.8 Figure 6.9


d) Insert the long fence, short fence, the fence at both ends, on cage top, into
corresponding cannulas, connected by bolts. It is notable that the baffle ends of
fences are mounted inside the cage when the fences are installed.
e) The electrical control box and resistance box of frequency construction hoist
should be mounted on the cage top and bolted on the cage fences.
f) Assemble the installing boom on the ground and hoist and insert it into the
hole for it using the lifting equipment. After installation, the rotation axis of
boom should be flexible;
g) Install the cable bracket.

6-7
Operation Instruction of SC Series Construction Hoist Installation and Debugging

Figure 6.10

6.3.4 Counterweight installation (for hoist with counterweight)

a) For construction hoist with counterweight, install and position the


counterweight on rack rails before increasing the height of rack rail frame.
b) Mount the buffer spring device directly below the counterweight and then lift
up the counterweight device to put the guide rollers into the rack frame from the top
of counterweight rack frame so that the counterweight device would stably be placed
on the sleeper. As for a single-cage construction hoist, the column tube of rack rail
frame to the opposite of cage is regarded as the guide rail frame of counterweight.
Adjust the eccentric shafts of four guide rollers of counterweight so as to get that the
total gap of each pair of guide rollers and the column tube is 0.5mm.
6.3.5 Increasing the height of the rail frame to 10.5 meters. After installation of
tie-in frame, increase the height to 15 meters.
Assemble three masts on the ground with bolts by tightening torque 300N · m
and lift them onto the installed mast connecting them together by bolts of tightening
torque 300N · m.
After the rail frame is heightened to 10.5 meters, set up the first tie-in frame at
the position of 9m off the ground (conduct the installation according to the
requirements described in section 6.6) and check the verticality of the frame in two

6-8
Operation Instruction of SC Series Construction Hoist Installation and Debugging

vertical directions with a theodolite or other detection equipment. If the verticality


error of rack rails ≤5mm, continue to heighten it to 15 meters.
When the rack frame is too high, the wall thicknesses of mast
main chord are different. Referring to Figure 5.1 for standard
configurations of thickness of mast main chord wall for the
installation.

6.4 Installation of electrical equipment, control system and overload protection


device

6.4.1 Installation of electrical equipment and control system

a) Installation of power cable of construction hoist is related to the adopted cable


guide. Normally, there are two forms: cable sleeve type and cable car type which is
divided into one-cable car and two-cable type
b) Use the site-supplied cable (≥25 ㎜ 2) to connect the power supply boxes on site
and of chassis fence. Fix one end of cable on the power supply box of chassis fence
and the other end to the terminals of junction box in cage via cable bracket.
□ For cable sleeve type, put the cable directly in cable sleeve according to
the cable sleeve installation;
□ For cable car type, there are two situations in the following:
1. If it has one power cable for power supply directly perform the above steps;
2. If it has two cables of different cross-sectional size for power supply, (the
larger cross-section cable is the fixing cable on mast rail frame and the smaller
one is the attached cable running up and down together with the cable car)
then take the attached cable to perform the above procedure.
c) Connect the motor wire of drive system to its corresponding position in electronic
control box and insert the cage top operation box (7-core plug) into its corresponding
position in electronic control box (in normal operation, the cage top operation box
cannot be removed).
For frequency construction hoist, its electrical control box is mounted on top of
the cage and the operation button assembly of cage top is on the electronic control
box.
d) Switch on the power switch of power box of chassis fence and close the outer
fence and skylights doors for operation on the cage top. Turn the switch of the cage
top operation box to cage top position and joggle the operation box to test whether the
power phase sequence is correct (when jogging the UP button, if the drive system

6-9
Operation Instruction of SC Series Construction Hoist Installation and Debugging

rises it means the phase sequence is correct, otherwise the phase sequence is reversed,
thus you need to exchange the wiring position of phase sequence).
f) Install a limit switch on the chassis fence
g) Check the safety control switches: including switches of hanging cage door limit,
skylight door limit, up and down limit, deceleration limit (inverter construction hoist),
extreme limit, chassis fence door limit and rope-breaking protection. All switches
should be can sensitive in action and flexible to open and close.
h) Use a ground resistance tester to measure the grounding resistance of steel and
metal casing and electrical equipment of construction hoist must not be greater than 4
;
With a 500V megger measure the insulation resistance of motors and electrical
components should be not less than 1 M .

During all the wirings, you must cut off the power.

6.4.2 Mounting of overload protection device

a) Operate the drive system for running up-and-down taking advantage of


operational box at cage top and to align with connection ear plates of drive car
and cage, inserting overload sensing pin and cotter pins which need to be
opened.
b)Connect the wire connect terminals of sensor pin and overload host machine.
Figure 6.14

Drive system

Sensor pin
Overload host

Cotter pin

6-10
Operation Instruction of SC Series Construction Hoist Installation and Debugging

c) Refer to “overload protection Manual” for overload protection setting. When


the actual weight of cage reaches up to 95% of its rated load, the warning
function is achieved and the warning lamp is lit, with intermittent buzzer
sounds; when the actual weight of cage reaches up to 110% (the parameter
cab be set) of its rated load, the warning function is achieved and the warning
lamp is lit. Consequently the relay will act and the buzzer produces
continuous sounds.

Overload host
Over load
sensor pin

Overload bell

Figure 6.15

Don’t connect the power until connecting the sensor plug, otherwise
it may cause false alarms

Figure 6.16

6.5 Installing the limit cam at the bottom of rail frame


and test run of power-driven hoist

a) Operate in the cage and the frequency construction


hoist operation must be carried out with a low
speed. Drive the hoist (with rated load) to the cage
bottom level with the outer cage threshold. Press
the emergency stop button to install the cams of
down limit and extreme limit switches (fasten the

6-11
Operation Instruction of SC Series Construction Hoist Installation and Debugging

cams by hook bolts on mast frame of rail frame; the installation position of
extreme limit switch cam cage must ensure the cage will move before the
buffer spring acts).
Frequency construction hoist must install a deceleration cam at the bottom
surface of deceleration limit, 200mm lower than the top surface of down limit, as
Figure 6.17.
b) After having finished the steps in 6.4 and a), power on the hoist to do the
commissioning. A full-time driver is needed to operate the operating handle carefully
to run the empty cage along the guide rail rack for several times with stroke not more
than 5m. During the process, the cage should be smooth and
stable in running, no beating and no failures and brake works
well. Meanwhile further examination is necessary for contact
condition of guide rollers and rail frame, as well as the
engagement of gear and rack.
□ The engagement clearance of gear and rack should be
0.2 ~ 0.5mm;
□ The clearance of gear and back side of rack should be
0.5mm;
□ The clearance of rollers and mast vertical pipes is
0.5mm.
c) After confirming the load test is normal, load the cage
with rated load to commission the hoist, checking the
heat condition of motor and reducer;

Figure 6.17
Be careful during the commissioning due to the up limit baffle on
top of rack rails is still not installed yet.
In the inspection, you must press the emergency stop button or
turn off the power to avoid misuse.

6.6 Hoist commissioning

After positioning the construction hoist (rail rack height less than 15 meters),
power it for commissioning inspection.
Before the inspection, make sure that the power supply and voltage of
construction site should meet the requirements; leakage protection device should be

6-12
Operation Instruction of SC Series Construction Hoist Installation and Debugging

sensitive and reliable. Rotation direction, starting and braking of motor in hanging
cage should be properly and effectively; supply phase protection, power limit, upper /
down limit, upper / down limit of deceleration, the doors and emergency power-off
limit switch should be sensitive and reliable.

6.6.1 Clearance adjustment of guide roller

Adjust the drive system and eccentric shaft of cage roller to place the two
vertical rods and drive system symmetrically set with respect to mast. The clearance
of rollers and the vertical pipe of mast is 0.3~0.5mm. All bolts must be tightened
after adjustment.

Figure 6.18

6.6.2 Clearance adjustment of gear and rack

The clearance of gear of hoist and its running rack should be guaranteed as
required. Check the engaging clearance using the lead law to make sure it is between
0.2 ~ 0.5mm. Specifically, adjust the positions of drive plate and the safety board (i.e.:
engagement clearance), and tighten bolts after the relevant adjustments.

6.6.3 Clearance adjustment of back wheel and rack

Each back wheel on construction hoist should be symmetrically


set with respect to the back center. The mounting clearance of back
wheel and the back of rack is 0.5mm. Specifically, it needs to adjust
the eccentric sleeve of back wheel and then bolts of back wheel
should be tightened after adjustment.
Figure 6.19

6.6.4 Adjustment of cable car

Place the cable car of hoist on the ground to adjust the eccentric shaft of its
guide wheel so that the corresponding track clearance of guide wheel is 0.5mm. Make

6-13
Operation Instruction of SC Series Construction Hoist Installation and Debugging

sure that the manual cable car or electrical cable car are in good condition and flexible,
without blocking.。
When installing or adjusting at the cage bottom, you must
disconnect the main power supply at first and support the cage bottom with a
rigid support to avoid the occurrence of cage falling.

6.6.5 Comprehensive lubrication for hoist

According to the present specification in Chapter 8-“Inspection and


Lubrication” do the lubrication as required.。

Contents of 6.6.4 - 6.6.5 shall be carried out after the completion of


whole machine installation

6.7 Drop test


6.7.1 Requirements of anti-fall safety device

a) The safety device is sealed with lead during production so it is prohibited to


open the safety device without authority.
b) At the time of drop test, if the security device is not normal operation, that is,
not in a predetermined distance when braking, you should identify the reasons
or readjust the safety device;
c) If the safety device has anomalies (such as damaged parts), it should be
immediately stopped and replaced;
d) After the safety is functioned, adjust it according to the requirements otherwise
don’t start the hoist.
e) Don’t inject any oily matters into the safety device, including lubricant.

6.7.2 Drop test instructions

a) A drop test is necessary for the newly installed hoist or reinstalled after being
transferred from other site. After the hoist is entering into normal operation, carry out
the drop test each three months regularly.
b) Security nameplate is marked with the period use, not exceeding one year.
The safety device needs to be sent to the manufacturer or to testing organizations to
re-check and calibrate. Its service life is five years.

6-14
Operation Instruction of SC Series Construction Hoist Installation and Debugging

6.7.3 Drop test methods

a) Heighten the rail frame to about 15m (install one tie-in frame at 9m);
b) Load the construction hoist with rated load weight;
c) Cut off the main power for power box of chassis fence, temporarily connect
the inch switch of anti-off device using test cable as shown in the Figure and
insert the drop test box (four-core air plug) on the port beside the electrical
control box;
d) Pass the drop test button box through the door and place it on the ground to
ensure that the cable will not be stuck during the drop test. Then close all doors;
e) Close the main power switch; press the “upward” button on the drop test button
box to make the drive system rises from the ground about 10m (Note: the drive
system should not over the roof);
f) Continue pressing the “fall” button to let the cage freely fall and lock the cage after
it falls to some distance that is, under normal
circumstances the braking distance, 0.15 ~
1.40m. (Braking distance should be counted
after having heard the “bang Lang” sound.
The safety device can brake the cage and at
the same time cut off the power through the
electromechanical interlock)
Under special circumstances, such as braking
distance is too long, please contact our
company;
No one is allowed on the cage
during the drop test.
If the cage is still not stopped
about 3m from the ground in free
falling, you should immediately
release the button to brake the
cage, and then press the “fall”
button to make the cage slowly fall
to the ground. Then find out the
reason.
g) Press the “Upward” button to drive

6-15
Operation Instruction of SC Series Construction Hoist Installation and Debugging

the cage to rise about 0.2m to reset the eccentric block of anti-fall safety
device;
h) Press the “fall” button to drop the cage slowly to the ground. Remove the
test cable, thus the cage cannot be started. Remove the drop test box and
reset the safety device according to 6.7.4;

The gliding distance of cage after each jog should not


exceed 0.2m; otherwise the speed limit will act again. After the
drop test, the test cable must be removed.

6.7.4 Reset of anti-fall safety device

a) After anti-fall safety device is in operation, the safety device must be adjusted
to recover. It is prohibited to continue to operate the construction hoist until the
safety device is reset;
b) In addition to the drop test, before its recovery, you should identify the reasons
for operation of the safety device, and be sure about:
□ Electromagnetic brake of motor works normally;
□ Worm gear pair and the coupling should be intact;
□ Cage guide rollers, back wheel and the rack should work properly;
□ Gear and rack should be intact, and they should be properly engaged with each
other;
□ Micro switch inside the anti-falling safety should work properly (before reset,
issue instruction of upward, and the cage should not start).
c) After confirming the inspections before reset are correct, you should firstly cut
off the power and reset the anti-fall safety device in the following order:
□ Loosen the screw 1 and cover 2;
□ Remove the screw 3;
□ Release nut 7 as the marked direction at the tail of safety device by a special
wrench 5 and prying lever 4 until the end of pin 6 is flush with the end of safety
device, when the circuit of limit switch is turned on;
□ Mount the screw 3 and the cover 2;
□ Remove the cover 9;
□ Try to tighten the stud 8 by hand, then use tools to continue tightening the stud

6-16
Operation Instruction of SC Series Construction Hoist Installation and Debugging

8 another 30 °. Release the stud 8 until there is “Goo” sound inside the safety
device;
□ Mount the cover 9;
□ □ Power on to drive the cage run upward 0.2m to recover the safety device.

Remove the connection plug of button box after the drop test is
finished.

6.8 Heightening the rack frame (installing the tie-in frame at the meantime) and
installing the cam of top limit

6.8.1 Heightening the rack frame

It is allowed to heighten the rack frame unless the installation and debugging
process is completed and the “drop test” at rated load is qualified for
acceptance.
6.8.1.1 Before installation, place the mast-to-be-installed and the matching tie-in
frame and cable guide device on the dry ground next to the fence;
6.8.1.2 If masts have different specifications, heighten the mast according to the
thickness configuration of mast main chord in Figure 5.1;
6.8.1.3 Heightening steps of rail frame
a) Insert the plug of installing boom into the socket in cab, and drop down the
boom hook to hook up the spreader of mast;
b) Use the mast spreader to hook one mast section, with tapered end of the sleeve
downward. Lift up the mast to the top of the cage and put it in stable (at most three
masts are allowed on each cage);
c) Start the hoist and when the top of drive system is near to the top of rail frame,
joggle the hoist until the top of drive system is 300mm from the top of rail frame.
d) Press the emergency stop button to prevent accidents.

No one is allowed on the cage during the drop test.


If the cage is still not stopped about 3m from the ground in free falling, you
should immediately release the button to brake the cage, then press the “fall”
button to make the cage slowly fall to the ground. Then find out the reason.

e) Suspend a mast to the top of the rail frame and its main chord interface should

6-17
Operation Instruction of SC Series Construction Hoist Installation and Debugging

be coated with grease. Align with the lifted mast with the mast below it and insert
is into the interface hole. Then tighten all bolts with no less than 300N · m
torque;
f) While heightening the rail frame, you should install the tie-in frame;
□ For construction hoist without counterweight, the pipe ends of four main
chords of its top mast must be installed with rubber sealing sleeve;
□ If there is suitable lifting equipment on site, it is alternative to assemble three to
four masts into a whole on the ground and then directly install the whole to the
top of the rack frame.
g) You should check the verticality of whole rack frame in two perpendicular
directions using a theodolite or other testing equipment after increasing the height of
the guide frame about every 10m. The vertical deviation requirement of rail
rack-mount is shown in Table 6.1. Adjust the rack frame as long as any tolerance is
found.
Table 6.1 Deviation table of installing verticality of rack rails
Rack rails height
h≤70 70﹤h≤100 100﹤h≤150 150﹤h≤200 h﹥200
(m)
Not larger
than the
Verticality deviation
0.5/1000 of ≤35 ≤40 ≤45 ≤50
(mm)
rack rails
height
When docking the mast, please ensure that the
dislocation differential at column pipe butt of upper and
lower masts ≤0.5mm.
For mast with guide rail for counterweight, you
should ensure the dislocation differential at rail butt of
upper and lower counterweight rail ≤0.5mm.

6.8.2 Mounting the cam of top limit of rack frame

After heightening the rack guide frame, install the


cams for up limit switch and the limit switch (as shown in
Figure 6.22). The installation location of iron touch of
limit switch should meet the following requirements:
Figure 6.22

6-18
Operation Instruction of SC Series Construction Hoist Installation and Debugging

When the rated speed is smaller than or equal to 0.85m / s, the mounting position
of limit switch cam should ensure that after the limit switch triggers its cam, the top
of the cage should still have a safe distance of at least 1.8m In addition, for any part
or equipment higher than the cage, there should be a safe distance of at least 0.3m
above it;
When the rated speed is greater than 0.85m / s, the mounting position of limit
switch cam should ensure that after the limit switch triggers its cam, the top of the
cage should still have a safe distance of at least 1.8m + 0.1V2 (V is the rated speed).
In addition, for any part or equipment higher than the cage, there should be a safe
distance of at least 0.3m above it;
Installation position of up limit switch cam Up limit switch cam
should meet the following requirements: under
Extreme limit switch cam
normal operating conditions, after the up limit
switch triggers its cam, the distance from the boom
of limit switch to the bottom end of its cam is
150mm;
Frequency construction hoist should be
adopted with cams for up limit switch, limit switch Deceleration limit
as well as for deceleration limit. Top end of switch cam
deceleration limit cam should be higher than the
bottom end of up limit cam about 200mm, as
shown in Figure 6.23.
Figure 6.23

6.9 Installation of tie-in frame

Installation of tie-in frame should be synchronized with the heightening and


installation of rack rails. Workers must be familiar with the entire content of Chapter
5 “Rack Frame and Ti-in Frame” to understand the requirements of mounting pitch of
tie-in frame and largest free height of rack frame and to master the connection
requirements of mounted components of tie-in frame as well as the regulating
methods.
Methods for lifting tie-in frame may refer to that of mast. Use the installing with
boom on cage for installation on use the cage for transport. When using the cage to
transport tie-in frame, you need to operation on the top of the cage.

6-19
Operation Instruction of SC Series Construction Hoist Installation and Debugging

Users can choose the right tie-in frame among type I, Ⅱ type (including ⅡA,
ⅡB, ⅡC, and ⅡD), Ⅲ type, and Ⅳ type depending on site requirements; Tie-in
frame can be fixed on the building’s concrete slab, force-bearing wall, force-bearing
beam or steel structure, but never allowed to be installed on non-load-bearing
structures like scaffold. Installation procedures for tie-in frames are as follows:
When tie-in frame is installed, all cotter pins must be open.
All bolts must be tightened.
When installing, you must always press the emergency stop button.

6.9.1 Installation of I-type tie-in frame

a) Use four M16 bolts or M16 U-bolt to fix the rear connecting rods of tie-in
frame onto the angle steel of upper and lower frames of mast (the rear
connecting rods must be placed symmetrically) while rotating pin is installed
between the rear connection rods. Don’t over-tighten the bolts at first so as to
adjust the position;
b) Fix the tie-in frame to the building by with 8.8-class M24 bolts.
c) Use the M20 bolts to connect the connection tube and the rear connecting rods,
the rotating pin and mounting seat together.
d) Correct the verticality and horizontality of rack frame and tie-in frame as
required.
e) After correction, tighten all bolts. Then slowly start the lift making sure that the
cage and counterweight does not collide with the tie-in frame.

6-20
Operation Instruction of SC Series Construction Hoist Installation and Debugging

Rear connecting rod

Bolt
Connecting pipe

Bolt

Drive pin

Tie-in seat

Figure 6.24
The maximum allowable level inclination angle of tie-in frame is ±
8 °, i.e. 144: 1000;
I -Type tie-in frame applies only to single-cage hoist and the mounting height
of rail rack is not more than 300m.

6.9.2 Installation of Ⅱ-type tie-in frame

a) Use four M16 bolts or M16 U-bolt to fix the rear connecting rods of tie-in
frame onto the angle steel of upper and lower frames of mast (the rear
connecting rods must be placed symmetrically). Don’t over-tighten the bolts
at first so as to adjust the position;
b) Fix the tie-in frame to the building by with 8.8-class M24 bolts.
c) Use the M24 bolts to connect the small frame and rear connection rod
together;
d) Use theφ20 connection pins to connect the big and small frames together;

6-21
Operation Instruction of SC Series Construction Hoist Installation and Debugging

e) Use the M24 bolts to connect the front and tie-in seat, and connect the front
connection rod together with tube clamp of connection frame.
f) Install adjustable connecting rod between the seat and the connecting tie-in
frame, with φ20 pins;
g) Correct the verticality and horizontality of rack frame and tie-in frame as
required.
h) After correction, tighten all bolts. Then slowly start the lift making sure that
the cage and counterweight does not collide with the tie-in frame.

Figure 6.25

The maximum allowable level inclination angle of tie-in frame is ± 8 °, i.e.


144: 1000;

6.9.3 Installation of Ⅲ-type tie-in frame

a) Install the φ76 riser and the end with a gap is upward. Insert the tightening pipe
clamp between the two tubes to tighten the bolts;
b) Mount the 2nd bracket between the frame rails and φ76 riser approximately 9m
off the ground and mount one bracket for each 9m-interval upward;
c) At the position of 300mm above or below the 2nd bracket, between φ76 risers
and buildings, mount a 1st bracket and diagonal support every 9m;

6-22
Operation Instruction of SC Series Construction Hoist Installation and Debugging

d) Install a channel connection frame at each stop layer as a support for the bridge
platform. Measure the horizontality by a gradienter. If the distance between
the two stop layers is too long, install a channel connecting frame for each t
3m interval;
e) At the position of 300mm above or below the channel connecting frame, mount
a 2nd and 3rd bracket;
f) Correct the verticality of rack rails by adjusting the 1st frame which can be
adjusted using tensioning device like steel wire rope.
g) All bolts must be checked after installation to ensure that they have been
tightened.
h) Check to make sure there is no interference or collision between the cage and
the other moving parts with the tie-in frame.

Figure 6.26

When the total mounting height of rack rails is greater than 150m,

it is not advisable to use the Ⅲ-type tie-in frame.

6.9.4 Installation of Ⅳ-type tie-in frame

a) Use four M16 bolts or M16 U-bolt to fix the rear connecting rods of tie-in
frame onto the angle steel of upper and lower frames of mast (the rear

6-23
Operation Instruction of SC Series Construction Hoist Installation and Debugging

connecting rods must be placed symmetrically). Don’t over-tighten the bolts


at first so as to adjust the position;
b) Fix the tie-in frame to the building by with M24 bolts.
c) Use bolts to connect the connection frame and the rear connecting rods and
mounting seat together.
Use the M16 bolts to connect the connection frame and tie-in seat together; and
connect connection frame together with tie-in seat by M24 bolts.
d) Correct the verticality and horizontality of rack frame and tie-in frame as
required.
e) After correction, tighten all bolts. Then slowly start the lift making sure that the
cage and counterweight does not collide with the tie-in frame.
Rear
connecting
rod Connection Tie-in seat
frame

Figure 6.27

The maximum allowable level inclination angle of tie-in frame is ±


8 °, i.e. 144: 1000;

6.10 Mounting of counterweight unit (for construction hoist with counterweight)

For construction hoist with counterweight, as its rack frame is installed to


required height, before normal operation it shall be fitted with a counterweight
assembly, wherein the counterweight and its guide rail brackets should be in place
before the heightening (Referring to Chapters of 6.3.4). This section is the installation

6-24
Operation Instruction of SC Series Construction Hoist Installation and Debugging

of top-wheel frame, eccentric rope and steel rope.


a) According to the requirements in section 6.3.4 check on rail installation of
counterweight. To reduce the wear to counterweight rail frame and its guide
rollers during operation, the dislocation bias at rail butt ≤0.8mm, otherwise
correct it.
b) Lift up the top wheel, eccentric rope and rope disc apparatus wound with two
ropes of sufficient length to the cage top and prepare wire rope clips.
c) Fix the wire rope disc device at the cage top.
d) Fix the eccentric rope onto the hanging plate at the cage top (or end of cage
vertical cylinder).
e) Lift up the cage to the point with distance of 500mm to the rack frame top.
Then install the top wheel by the installation boom onto the top of rail frame
and fix it by M24 bolts.
f) Release the rope from the rope disc. At that time you should be careful to avoid
the rope being twisted or damaged.
g) Wind the steel rope to bypass the top wheels and place it on the counterweight
device on the ground. The connection and fixation methods of rope end should
be consistent with GB 26557-2011 and other relevant standards.
If the installation is encountered instantaneous gusts, pull the soft
traction rope from the cage to guide the rope to the ground.
h) Fix another end of rope on to the eccentric rope device in the same way and adjust
the length of the two ropes to let the rope-releasing limit switch in the middle
position of baffle. Please ensure that when the counterweight meets the buffer
spring, the distance from cage top to top-wheel frame should be at least 500mm.
i) Make sure that the passage of counterweight rail is unblocked.
When using the cage to transport the components like counterweight
assembly, top-wheel frame and others, you should operate the running at
the cage top;
When installing the cage roof, you must press the emergency stop button. The
strength level of connection bolts is not less than 8.8-class.

6.11 Re-heightening and mounting of rack rail frame with counterweight


assembly

6-25
Operation Instruction of SC Series Construction Hoist Installation and Debugging

For construction hoist with counterweight, there is


already counterweight assembly installed on rack rail
frame, so remove the top-wheel frame of counterweight
assembly before re-heightening.
Specific procedures are as follows:
a) Prepare for the running operation at cage top
according to contents of the mounting and
heightening program of rack rail frame in section
6.8.1.
b) Remove the cams of up limit switch, limit switch,
deceleration limit switch (Frequency construction
hoist) from the top rail frame
c) Carefully manipulate the cage to rise up and drop the
counterweight slowly onto the buffer spring on the
ground, and balance the weight of two ropes by
unloading device between counterweight and
top-wheel frame. Figure 6.28
d) Remove the protective cover for pulley of top-wheel frame. Get off the steel
tope from the eccentric rope device and top-wheel frame and hang it on the
rail frame (Referring to Figure 6.28). Also, you can put the rope to the top of
the floor (together with rope disk device).
e) Remove the fixing bolts for top-wheel frame and guide rail. And then dismount
the top-wheel frame using installing boom.
f) According to the requirements of section 6.8, heighten the rack rail frame to the
desired height and re-install the top-wheel frame
according to the requirements in section 6.10.
g) Lower the cage and install rope winding disc
device to the top of the cage again. After
releasing steel rope of length 2 times to the
heightened height, fasten the wire rope and cage,
and remove the unloading ropes.
h) Carefully manipulate the cage to rise up to the
top of the cage and reinstall the steel rope for
counterweight assembly according to the

6-26
Operation Instruction of SC Series Construction Hoist Installation and Debugging

requirements in section 6.10. And install the cover for pulley of top-wheel
frame.
i) Make sure that the passage of counterweight rail is unblocked.
j) Re-install and adjust the cams of up limit switch, of limit switch and of
deceleration limit switch (Frequency construction hoist) at the top of rack rail
frame as required in section 6.8.
k) Tighten all butt bolts for masts of rack frame with tightening torque not less
than 300N · m. Figure 6.29
You should operate the running of cage at the cage top and prevent it
from colliding with steel rope on rack rail frame;
When installing the cage roof, you must press the emergency stop button. The
strength level of connection bolts is not less than 8.8-class.

6.12 Installation of cable guide


Cable guide types: cable sleeve and cable car.

6.12.1 Mounting cable sleeve and cable retaining rack


a) After installation in 6.1 ~ 6.3, install the cable sleeve;
b) Hang the cables onto the cable sleeve using lifting equipment;
c) Release about 5.2m cable to connect it to the power supply box;

Figure 6.30
d) Pull out the cable from the drum and draw it to the power supply box.
Temporarily do not connect;
e) Put the cable into the drum clockwise circle by circle and try to make each
circle is same, slightly smaller than the diameter of the cable sleeve;
f) Fix the cable on the cable bracket and connect the cable connector to the
corresponding terminal;
g) Connect the cable to the power supply box and start the hoist to check whether

6-27
Operation Instruction of SC Series Construction Hoist Installation and Debugging

the cable is twined;


h) During the process of heightening rack frame, install the cable retaining rack.
i) Adjust the positions of cable retaining rack and cable bracket, making sure the
cable is in the center of the “U”-type retaining rack.

Figure 6.31

Figure 6.32

6.12.2 Installation of cable guide device of cable-pulley type

6.12.2.1 Installation of cable guide device of single-cage cable-pulley type


6.12.2.1.1 When only a cable for power supply, the installation procedure is as
follows:

6-28
Operation Instruction of SC Series Construction Hoist Installation and Debugging

a) Having completed the procedures in 6.4, power the


cage. Because the cage is installed with a freely
suspended cable, it needs someone to drag the cable
on the ground so that the cable is not reversed or tied;
Figure 6.33
b) Drop the cage down to the bottom and cut off the
main power supply of external power supply box and
remove the connection for the cable and an external
power connection box;
c) Put all the cable rolled up on the cage top and drop down one end of the cable
from the cage along the vertical surface of the chassis and drag it to the power
box;
d) Turn on the power to drive the cage to rise up,
dropping down the cable which should be fixed on
the rail frame by cable clips every 1.5 meters;
e) If the mounting height of rail frame is less than the
height of half the total predetermined height plus
another 3 meters, operate the cage open to the top of
rail frame. Mount the cable retaining rack on the top
mast of rail frame.
If the mounting height of rail frame is reaching to or over
the height of half the total predetermined height plus
another 3 meters, operate the cage open to the height
of half the rail frame. Mount the cable retaining rack
at 1m beyond the half of rail frame. Figure 6.34
f) Mount the cable onto the cable retaining rack (Figure 6.35);
g) Slowly decline the cage and mount a cable retaining rack every 6 meters; when
mounting cable retaining racks make sure both side boards of cable car frame
and cage boom can pass through the rubber sheet of U-shaped notch of cable
retaining rack;
h) When the cage is dropped to the level of threshold, support it with rigid
supports (ensure it is safe to install the cable car under the cage);
i) Cut off the power and remove the end of cable plugged in cage from the cable
bracket to keep it in a free state (if it cannot be free suspended, you should

6-29
Operation Instruction of SC Series Construction Hoist Installation and Debugging

straighten it).
j) Remove two rollers from one side of the cable car and mount the cable car
below the cage bottom;
k) Reinstall the rollers and tighten the screws by hand;
l) Adjust the gap between rollers risers to be 0.5mm;
m) Try to pull the cable car to confirm it is flexible
without blockage;
n) Drag the free end of straighten cable in the step i) to
cross the cable car and then reconnect it in the
terminal box of the cage, making sure that the cable is
not twisted; Figure 6.35
o) Removal the support under the cage;
p) Drag the cable on cage top to straighten it, without
raising the pulley frame. And then draw up the cable
again to make the pulley frame touches the cage bottom.
Then, drop half of the length of the cable drawn up again
and tighten the clamp plate on inlet wire rack of cage and
fix the cable;
q) Roll up the remaining cables and fix it on the security
fence of cage top;
r) Open the main power and confirm that the phase of cable
wiring is correct;
s) Run the hoist to install the remaining cable retaining rack; Figure
6.36
6.12.2.1.2 Installation procedures of two cables for power supply are as follows:
a) At installation, the power supply for cage uses the attached cable;
b) Lower the cage to the bottom and place the fixing cable on cage top using the
installing boom. Then insert a shaft or pipe into the cable volume to fix the
volume on cage top, so that the cable is easy to let go;
c) Carry out the step e) in 6.12.2.1.1;
d) Additional installation personnel needs to remove the attached cable connected
with the chassis removed power supply box and collect it onto the cage top;
e) Connect one end of the fixed cable to the middle junction box and drop the
other end vertically to the outer cage chassis and then lead the cable along the

6-30
Operation Instruction of SC Series Construction Hoist Installation and Debugging

surface of the chassis to the power box. Fix the remaining cable on rail frame
(fixed rack position) to ensure that the cable does not interfere with the cage
and other moving parts;
f) Connect one end of the attached cable (from the removed end of power box) to
the middle junction box;
g) Decline the cage slowly and install a clamp every 1.5m. Fix the fixed cable to
the rail until the cage is to the bottom, installing a cable retaining rack every
6m. Meanwhile make sure both side boards of cable car frame and cage boom
can pass through the rubber sheet of U-shaped notch of cable retaining rack;
Figure 6.3
h) Carry out the steps of h) ~ s) in 6.12.2.1.1, and the cable mentioned in these
steps is the attached cable;
6.12.2.2 Installation of cable guide device of double-cage cable car:
6.12.2.2.1 When only a cable for power supply, the installation procedure is as
follows:
a) Drive the two cages to the bottom and support the right cage at its bottom by
rigid support (ensure it is safe to install the cable car under the cage);
b) Remove the right-cage cable and place it using lifting equipment onto the left
cage;
c) Drive the left cage to conduct step e) in 6.12.2.1.1;
e) Pass one end of cable through the cable fixing frame at right side and drop it
vertically to the outer cage chassis and then lead the cable along the surface of
the chassis to the power box. Drop the other end vertically to the ground;
f) Decline the left cage slowly and install a clamp every 1.5m. Fix the cable
segment of right cage from the fixing frame to the outer cage power box onto
the rail frame, installing a cable retaining rack every 6m. Meanwhile make
sure both side boards of cable car frame and cage boom can pass through the
rubber sheet of U-shaped notch of cable retaining rack;
g) Drive the left cage to the bottom to carry out the steps of j) ~ s) in 6.12.2.1.1 to
complete the installation of right cage guide device of cable car;
h) According to 6.12.2.2.1, complete the left cage guide device of cable car taking
use of the right cage;
6.12.2.2.2 Installation procedures of two cables for power supply are as
follows:
a) Drive the two cages to the bottom and support the right cage at its bottom by

6-31
Operation Instruction of SC Series Construction Hoist Installation and Debugging

rigid support (ensure it is safe to install the cable car under the cage);
b) Remove the right-cage cable and place the attached and fixed cables of right
cage using lifting equipment onto the left cage;
c) Drive the left cage to conduct step e) in
6.12.2.1.1;
d) Conduct step e) in 6.12.2.1.2;
e) Connect one end of the attached cable (from the
removed end of power box) to the middle
junction box and drop the other end slowly to
the ground;
f) Carry out the steps of f) ~ h) in 6.12.2.2.1 to
complete the installation of right cage guide device of
cable car;
g) According to 6.12.2.2.2, complete the left cage
guide device of cable car taking use of the right cage;
6.12.2.3 Heightening the guide device of cable car
type:
If after the rail frame has been heightened, the
mounting height of cable retaining rack frame is less
than the height of half the total predetermined height plus another 3 meters, move up
the cable retaining rack frame before heightening the rail frame, the method is as
follows:
a) Release the remaining cable wound on cage top
(when releasing, drive the cage to the bottom) and lock the
cable again;
If all the cable of hoist is in one specification, the
length to be release is equal to 3 times the increased
height of cable fixing frame;
If all the cable of hoist is in two specifications, the
length to be release is equal to 2 times the increased
height of cable fixing frame;
Figure 6.38
b) Drive the cage upward until it arrives at the
position where its distance to cable fixing frame is equal to

6-32
Operation Instruction of SC Series Construction Hoist Installation and Debugging

the released lenght. Fix the bottom end of cable


and the cable car frame onto the cable bracket
to prevent the cable fixing frame from being
forced.
c) Continue the running to the fixed
position of cable fixing frame and confirm the
cable segment from its fixing frame to outer
cage power box is fasten firmly. If the cable of
hoist is in two specifications, release the
remaining static cable wound at cable fixing
frame for a length equal to the height of the
fixing frame increased.
d) Remove the cable fixing frame and drive
the cage to the new fixing position to mount the
cable frame.
e) Fix the cable onto its frame.
f) Relax the cable and the cable car slowly
to be free.
g) Drive slowly the cage for test run to
check whether there is interference or collision
between components. Figure 6.33
6.12.3 Installation procedures for cable guide device of special pulley rail:
a) Release all of the attached cable from the cable sleeve on the ground.
b) Bolt the cable bracket to its mounting position on the cage.
c) Cross one end of the attached cable through the cable bracket to connect it onto
the junction box in cage; the other end into the power box of chassis fence
(Referring to Figure 6.33).
Cut off main power supply during wiring!
d) Turn on the main power supply.
Heighten the rail frame and mount tie-in frame and the cable guide.
Figure 6.39
e) Fix the first section of the cable car guide rail by two connecting bars to the
bottom of rail frame. One end of connecting rod should be bolted with pulley rail
and the other end with mast frame by a hook bolt. Mount the cable car frame on

6-33
Operation Instruction of SC Series Construction Hoist Installation and Debugging

pulley rail and stop it at the bottom of the rail frame (Referring to Figure 6.39).
f) Install the pulley rail upward and bolt the pulley rails with each other and fix
them by connecting bars together with mast rail frame every 4.5m (connecting ways
as previous). If adjustment is needed, place gaskets between the connecting rod and
the rail frame. Before tightening of upper and lower pulley rail frames by bolts, check
the gaps at joints of pulley rail to make sure the gap is at the range of 1mm to 3mm.
g) Previously tighten the guide piece of cable retaining frame individually and the
contact pressure is 10.20N (using plate spring).
□ Double-cage hoist, bolt the cable retaining wire frame A / B on rail frame
about every 3 m (Referring to Figure 6.40);
□ Single-cage lifts, the mounting pitch of each pair of cable frame A and B on
the cable car is about six meters.
□ The mounting of cable frame A and B shall ensure the cage boom can pass
through between the two guide pieces.
□ Heighten the pulley rail frame to the position of 4.5 m beyond the half of the
maximum predetermined height.
h) Place the fixing cable on cage top and release some
cable of length sufficient connected to ground
power box. Then drive cage upward gradually to
release the required fixing cable which should be
fastened every 1.5 meters with a cable clamp to the
rail frame until about 1.5 meters above the top of
the cable car rail. Fix the cable end on the rail
frame and bundle the rest cable. Then hang the
bundle on the rail frame and fasten it firmly.
i) Mount the cable fixing frame on the position l.5
meters above the pulley rail and connect the upper
end of cable to the junction box of the fixing cable
frame.
j) Cut off the main power supply on the ground.
Remove the attached cable end from the terminal of
junction box in cage and then insert the cable end
into cable fixing frame with fastening by clamps
and then connect it to the junction box of cable fixing frame. Afterwards,

6-34
Operation Instruction of SC Series Construction Hoist Installation and Debugging

release the attached cable hung on entry frame of cage to suspend it down
from the fixing frame slowly.
Figure 6.41
k) Let the cage fall down slowly based on its gravity using the method of
manually releasing brake. Collect the suspended cable into the cable retaining
rack frame B / C.
l) Remove the other end of the attached cable from power supply box on the
ground, and as a replacement, connect the fixing cable.
m) Lead the removed end of attached cable from the power box on the ground to
bypass the cable disk. Fasten the cable by clamps and connect its end to
terminals of junction box in cage. Stop the trolley at about 0.5 meters from the
ground and bind the spare attached cable on the fence of cage top. Turn on the
main power (Referring to Figure 6.41).
n) Mount a cable retaining rack frame A every nine meters on guard rail frame
above the pulley rail frame.
o) Lubricate the rail frame and pulley shaft with grease.
6.12.3.2 Phased heightening and installation of cable guide of pulley rail
When construction hoist is erected in phased process, if the rail rack frame is
less than half its pre-erected height, the mounting height of pulley rail should be 4.5
meters lower than the top of the rail frame.
That is: If the first erection height of rail frame is 30 meters, pulley rail should
be installed to 25.5 meters. Install the cable guide for pulley rail with such height.
When the rail frame is heightened to 25.5 + 25.5-4.5 = 46.5 meters, you need to
install a cable wire frame every 6 meters on rail frame above the pulley rail. And the
fixing cable and attached cable are not necessary to be lengthened. When the rail
frame height is over 46.5 m, the fixing cable and attached cable are necessary to be
lengthened. Similarly, the block must be heightened to guide rail brackets at the top
of 4.5 m or less. Namely: the pulley rail should be heightened to 4.5m below the mast,
i.e. the installing height of pulley rail is 4.5m
less than the half of the maximum set height
of mast rail frame.
Heightening procedures of cable guide as
follows:
a) Stop the cage at the pulley rail top and

6-35
Operation Instruction of SC Series Construction Hoist Installation and Debugging

slightly loosen the cable clamp of cable bracket of the cage to pull out the
segment of attached cable originally placed on cage, with its length equal to
the height of rail frame to be heightened. Then, fasten the cable clamp.
b) Drop the cage and release the strapped cable on the rail frame and drag the
previous left cable to cage top. Mount the uninstall tools on the attached cable
under cable fixing frame and then hang the cable on the cable bracket. Later
remove the cable fixing frame from the rail frame and place it on the cage top
(Referring to Figure 6.42). Figure 6.42
c) Drive up the cage in several steps and fix the every 1.5m segment of fixing
cable onto the rail frame by cable clamps until 3m to the top of rail frame.
Then install the cable fixing frame to hang the spare cable bundles onto the
rail frame.
d) Remove the dismantling tools for attached cable on the entry frame of cage.
e) Heighten the pulley rails to 1.5 meters under the cable fixing frame and install
the wire frames A, B and C as required.
When driving the cage up and down, operators should be at the cage
top and stand in safe place;
When installing, if you need to press the emergency stop button all the time you
must cut off the main power supply on the ground.

6.13 Installation of Floor-call system

Each floor should be set with the floor call system for communications of hoist
operators. If users need to configure the floor call systems, install it in the following
manner, with reference to the specific installation methods in “Hoist Floor Call
System Operating Instructions”.
a) Connect three wires from the red, yellow and blue terminals of extension unit
in power box, and along the building height direction fix the wires on the building.
b) Install extensions on each floor to connect with the wires of three colors.
c) Install a transmitter head every 50 to 80 meters on the building close to the rail
frame and connect its red, yellow and blue wires together with the three-colored wires
of extension unit.
The red, yellow and blue sheets should be supplied by users and
the specification is copper wire of cross-section > 1mm2.

6-36
Transmission head
Operation Instruction of SC Series Construction Hoist Installation and Debugging

Lifting cage

Host

Extension work unit

Horizon

Figure 6.43

6-37
Operation Instruction of SC Series Construction Hoist Operations and Use

7 Operations and Use


7.1 Security check before operation

Hoist operators must be trained and obtain the operating certificate, familiar with
the performance and operation technology of the various components.
Before operating, carry out daily inspection for construction hoist;
a) Conduct routine daily inspection and lubrication in accordance with
requirements in Chapter 8;
b) Check the baffles and their positions of limit switches on the rail frame, which
should be sensitive and reliable, safe and effective;
c) Check the fence door and electrical and mechanical interlock of hanging cage
to be good;
d) Stop the cage at the ground station, open and close the door of outer fence, the
entry and exit doors of cage and the top door one by one to confirm all doors are in
good performance, and at this time the cage cannot be started;
e) Raise the cage about three meters and at this time the entry door of cage and
the door of outer fence should be locked;
f) Check the functions of switches of up and down limits, up and down
deceleration limits and the power supply limit: disconnect switches of up and down
limits and the power supply limit, the cage should not be started; disconnect the
deceleration limit, the cage should be in the deceleration state;
g) For construction hoist with counterweight, you need to check the
rope-releasing switch function of eccentric rope device on cage top and it the switch
is off, the cage cannot be started;
h) Check to confirm that there should be no obstacle in the cage and the
counterweight channels;
i) Remove the installation boom on cage top and it’s prohibited to operate the
installation boom with load;
k) In installation condition, conduct the operations on cage top;
l) Before starting the cage, notice everyone on site. If there is any abnormal
condition, press the emergency button;
m) If there is any abnormal condition to hoist, inform related repair personnel in
time. A person who is not the repair people is not allowed to move the hoist;
n) During repair and inspection, you must cut off the main power supply and

7-1
Operation Instruction of SC Series Construction Hoist Operations and Use

inspect or repair 10 minutes later;


o) Operational personnel and goods are prohibited rely on or extrude the cage top
fence;
p) Construction hoist after heavy rains or strong typhoon needs to be inspected for
all key components by professional engineering and technical personnel;
q) Do drop test and repair and inspection according to the specified period;
In the chassis fence, don’t operate the construction hoist when there is
people working inside the rail frame, tie-in frame or on cage top;
Do not overload; goods and man head or hands are prohibited to extend out
of the cage;
In addition to the driver, the cab is prohibited to carry goods or other
persons;
When the wind speed is greater than 20m / s, the operation of construction
hoist is prohibited;
When the rail frame and cable is freezing, don’t start construction hoist!

7.2 Operating

Before operating the construction hoist, the operator should inspect it according
to “7.1 Inspections before Operation”. After the inspection result is as required, you
can put it into normal operation.
a) Power on;
b) Load the goods or persons in cage;
c) Close all doors, including the entry and exit doors of cage, top door and outer
fence door, making sure the exit door is locked;

7.2.1 Operation:

a) Confirm the operational platform, the emergency stop button on operation box
on cage top, switch of operation table, are already open. The cage top control box
switch is turned into the cage;
b) Press the bell at first and then pull the joystick in the desired direction to start
the cage. When the cage reaches to the desired height, put the joystick in the “zero”
position, the cage will be stopped.
c) Operational approaches of frequency construction hoist are as follows:
□ Confirm the operational platform, the emergency stop button on operation
box on cage top, switch of operation table, are already open. The cage top control box
switch is turned into the cage;

7-2
Operation Instruction of SC Series Construction Hoist Operations and Use

□ Jog the “Power” button on operating table so the drive will be energized;
□ Jog the “Bell Start” button on operating table, the PLC system will check
the limits, if normal, the “Ready” indicator on operating table lights;
□ When operating press the micro switch on the handle to ensure the micro
switch in operation remain active. Handle have four shifts of speed: upward at
low-speed, upward at high-speed, down at low-speed and downward at high-speed.
Pull the handle in the desired direction to start the cage and when the cage is going to
reach the desired high speed, switch the handle to low-speed. Then set the handle in
the “zero” position, thus the cage will be stopped
□ During switching actions of up and down, interval of more than three
seconds is needed otherwise the PLC will determine the situation as abnormal
operation and the hoist cannot move.
Operate the operational box of cage on the cage top (operation button assembly
of top cage of frequency construction hoist is installed on the electrical control box on
cage top of the);
As an exception occurs during operation, such as the electrical system loses
control, immediately press the emergency stop button and don’t open it the fault is
excluded;

7.2.2 When the cage cannot start, check the following items.

a) The ground power switch is in the "on" position. Cage electrical lines should
be energized;
b) “Emergency stop” button have been released or
electric lock have been opened;
c) The power limit switch should be in the on
position;
d) The outer fence door, cage door and top door
should be closed.
e) For construction hoist with counterweight, you
need to check the rope-releasing switch position of
eccentric rope device on cage top is right. Figure 7.1
f) Fuse should be intact (or circuit breaker should be switched on).
After the above checks and taking appropriate actions, if the hoist still cannot
start, deal with the situation according “maintenance” section in Chapter 9.

7-3
Operation Instruction of SC Series Construction Hoist Operations and Use

7.2.3

When the cage of construction hoist is stopped suddenly in running due to a


power failure or other electrical failures (fuses, motor thermal relay), it’s better to
manually release the brake if there is no good solution, and the manual operation
must be performed by trained professionals, as follows:
When the drive system is adopted with only one motor, pull out slowly the
manual release handle or rod of brake at the
tail of motor to lower the cage slowly.
When there are two or more motors
for drive system, you need to use the
jacking rod to jack up and release the brake
of one motor or brakes of more motors, left
one motor for manual release operation. Figure 7.2
During the process to release brakes, do it set by set; if you find the cage fell
during the releasing process, cancel releasing immediately to recover the braking. At
this time the situation may be:
1. After releasing the brake of one motor or brakes of more motors, the
combining torque of rest brakes is not sufficient to stop the cage, especially in the
case of full load.
2. There may be some part of rest brakes badly worn, or even lost the ability to
brake.
If encountering this situation, you can exchange the brake or the order of release.
If encountering the following situation, you need to release several brakes at the same
time, for example: if drive system has three motors, the cage decline occurs upon
release of the second motor, it requires the operator to manually release the two
brakes simultaneously to decline.
Manually release brake in discontinuous way and the cage falling at each
time should be short, not exceeding the normal speed limit of hoist. If
over speed, the anti-fall safety device will act to stop the cage. In this case
the anti-fall safety device must be reset before cage falling again. After
falling every 20 meters, stop l minute to allow the motor brake to be
cooled. In the job on cage top you should pay attention to safety.

7-4
Operation Instruction of SC Series Construction Hoist Operations and Use

7.2.4

If the construction hoist bear heavy loads and the motor brake is worn (insufficient
braking torque) to let the cage down to the power limit switching position, and the
three-phase power supply is cut off so as to the cage cannot run up based on the
power, you should rotate the boom of limit switch to a certain distance to reset the
limit switch to drive the cage rise up and re-adjust the boom distance of limit switch
so that it can effectively contact with limit cam.

7-5
Operation Instruction of SC Series Construction Hoist Inspections/Lubrication

8 Inspections / Lubrication
Inspections for construction hoist are divided into daily inspection, weekly
inspection, monthly inspection, quarterly inspection, annual inspection and
special inspection.

8.1 Safety Precautions:

a) Inspectors of construction hoist must be qualified, such as electrical


inspectors must have the electrician operation certificate, and have been
trained for relevant knowledge;
b) Inspector must wear insulated shoes when conducting electrical inspection;
c) During motor inspection, you must cut off the main power supply and inspect
10 minutes later;
d) Inspector should meet the aerial work requirements, including the need to
wear a helmet, seatbelt, wear non-slip shoes, overalls etc., and not wear
loose clothing;
e) It is prohibited to install at night or relevant personnel is drunk;
f) During the running of hoist, head or hands of operator must not extend the
security fence;
g) For connections of top wheels and tie-in frames and masts and inspection for
the cable guide device, the cage needs to be parked at corresponding
inspection position. For other inspections, the cage should be stopped at the
bottom;

8.2 Daily inspection:

a) Visually inspect the exterior condition of trailing cable and fixed cable to be
good, no twist or breakage.
b) Visually inspect the condition of the fastening bolts which should be well
fastened.
c) Visually inspect the guide rollers and back wheels which should be good, no
run yaw.
d) Inspect according to the requirements in “7.1 Inspections before Operation”
and conduct routine daily inspection as required.
e) Check the interlock switch of door of the outside fence. If you open the door
the cage will not be started.

8-1
Operation Instruction of SC Series Construction Hoist Inspections/Lubrication

f) Check the switches of up and down limits up / down deceleration limit


(frequency construction hoist) and limit switches should be sensitive and
reliable, safe and effective.
g) Carry out each of the following safety tests for switch. In test, the cage cannot
start:
□ Open the cage door or the material gate;
□ Open the door of the outside fence;
□ Touch rope-breaking protection device;
□ Press the emergency stop button;
h) Check to confirm that there should be no obstacle in the cage and the
counterweight channels.
i) Check whether there is cement or stone on the cables, cable wheels, mast riser
or gear, or rack. If there is, clear up instantly.
j) Check that whether the cooling fan of the electrical control box on cage top of
frequency hoist cage is working properly, and whether the transducer and the
resistance heating is normal.

8.3 Weekly inspection:

a) Check the bolts of drive plate which should be a good situation.


b) Check the connection bolts for gear, rack, the guide wheel, back wheel and all
tie-in frames and masts, which should be in good condition.
c) Check the connection bolts for cable bracket and retaining rack, which should
be good, no loose or movement.
d) Check all lubricated parts should be well lubricated. The temperature rise of
worm reducer should not exceed 100 ℃. Check the fluid condition of drive system. If
there is any oil leak or spill or inadequate oil level, replenish oil in time.
e) Check the counterweight guide wheel which should be flexible in rotation.
Connection at rope end is in good tightening.
f) Check the counterweight guide wheel which should be flexible in rotation.
Counterweight rope should have no broken wires, deformation and serious wear and
tear and so on. Connection at rope end is in good tightening.
g) Check the motor and reducer which should be without abnormal heat and
sound.

8-2
Operation Instruction of SC Series Construction Hoist Inspections/Lubrication

8.4 Monthly Inspection:

a) Check the hanging door to prevent it departing from the door. Adjust the
position of the door wheel to let the gaps between the door and the two tracks are
consistent;
b) Check whether the locks for cage and the outer fence are loose or deformed;
c) Check the engaging clearances of gear rack to be 0.2-0.5mm (Referring to
Figure 6.18);

8.5 Quarterly Inspection:

a) Check the bearing operations of guide rollers, back wheel and pulley, and
replace according to actual situation.
b) Check the wear of guide rollers (Referring to Figure 8.1). Adjust the required
clearance between guide rollers with risers of masts, which should be 0.5mm
(Referring to Figure 6.18).
c) Check the wear of brake discs and brake pads. (With a feeler) The minimum
size limit: 0.3mm.
d) Check the reliability of anti-fall safety device and do drop test according to the
specified test period for the safety device.
e) Check the connection of attachment parts which should be well fastened.
f) Checks each of the cooling fans which should be without abnormal vibration or
noise.
g) Check insulation resistance of motor, and the grounding resistances of
electrical equipment and metal, steel to meet the requirements.
g) For the frequency construction hoist
the following tests are demanded:
Check whether the external terminal
of inverter, mounting screws of unit
and connectors are loose or not;
Check if there is dust on resistance, if
there is, blow it off with the dry air
with pressure of\ 4-6kg / cm2; Figure 8.1

8.6 Year inspection:

a) Check the appearance of accompanying / fixed cables, if being severely twisted,


damaged or aged; the cables should be replaced immediately.

8-3
Operation Instruction of SC Series Construction Hoist Inspections/Lubrication

b) Check elastic elements (polyurethane rubber) of coupling between the motor


and reducer, and if there is damage or aging, the elements should be replaced
immediately.
c) Check structural parts and parts possibly being all corroded or worn and
conduct specific identifications; structural parts and parts being severely
corroded or worn should be replaced.
d) Check the filtering dielectric capacitor of inverter of frequency construction
hoist whether there is abnormal, such as discoloration, stench, etc.

8.7 Special inspection

8.7.1Detection for transmission gear

Use the gear normal line micrometer to check the wear of gear: new gear
dimension is 37.1mm; wear limit size is 35.1mm.

Figure 8.2

8.7.2 Rack Detection

Check the wear of rack by special measuring gauge for


rack: the new tooth thickness is l2.56mm; wear limit size is
10.6mm; if the measuring gauge can touch the bottom of
thickness section of the tooth, replace the rack.
Figure 8.3

8.7.3 Detection of worm teeth

Check the wear of worm teeth by special measuring gauge: open the inspection
holes on the side of the worm reducer (Referring to Figure 8.4), and vertically
measure the worm teeth by the end of measuring gauge marked with 100. If the
measuring groove of measuring gauge for worm teeth can be inserted into the worm
gear, that means the worm is worn seriously and should be appropriately replaced;
otherwise, in general, measure it the 50% end of the measuring gauge to detect

8-4
Operation Instruction of SC Series Construction Hoist Inspections/Lubrication

whether the wear exceeds or is less than 50%, as a reference for normal use.

Figure 8.4

8.7.4 Braking torque detection


Use a lever and spring scales to detect the braking torque of motor:
Determination of specific motor torque considers the distance of lever (m) by the
tension of spring scales (N) as the unit of measurement: Nm (Referring to Figure 8.4).
□ Torque of 11kW motor: l20N.m ± 10%;
□ Torque of 15kW motor: l70N.m ± 10%;
□ Torque of 18.5kw motor: 190N.m ± 10%;
Other motor torque values refer to Instructions of corresponding motor.

8.8 Lubrication
A comprehensive lubrication is necessary for
each installed construction hoist before official use.
The lubrication during normal operation is carried
out according to the cycle in the table.
Before lubrication, lubricating parts must be cleaned for stained gray sand,
particularly gears, rack and wheels and other components.

8.8.1
After one week use of newly installed construction hoist, clean it and replace the
lubricating oil for its worm reducer. After this, lubricate it every six months.
Worm reducer oil should be lubricated in accordance with the nameplate on
reducer or the operating table 8.1, without mixing.

Table 8.1 Reference table for lubricating oil or grease


Viscosity
Name Type Working range Domestic Mobil SHELL
40℃
Worm Lubricatin 0℃~40℃ 288~352 L-CKE/P Mobil gear 636 ShelI Omala

8-5
Operation Instruction of SC Series Construction Hoist Inspections/Lubrication

Gear g oil 320 worm GXl40 0il680


box (SH0094) gear oil
L.CKE/P
Mobilgear 630 SheII Omala
—20℃~25℃ 198~242 220 worm
GXl40 Oil220
gear oil
Lubricatin
135~165 L.CKB Mobil ShelI Tivela
g oil 0℃~40℃
Normal 150 gear oil Glygoyle 30 Oil WB
(GB5903)
use
Lubricatin Albany grease (GB491) ShelI AIvania
Mobilux 3
g grease Lithium grease(GB7324) Grease R3

8.8.2

Lubricating positions of structural parts and parts of construction hoist are shown in
Table 8.2 and Figure 8.6.
Table 8.2 Lubricating positions of structural parts and parts
Period Item Lubricating position Lubricant Amount Remark
Details in table Add oil when
1 Reducer
8.1 necessary
2 Gear rack 2# Albany grease Brushing
Weekly
3 Counterweight rail 2# Albany grease Brushing
Main chord of rack rail
4 2# Albany grease Brushing
frame(Φ76)
5 Safety device 2# Albany grease Oil gun filling
6 Roller 2# Albany grease Oil gun filling
7 Back wheel 2# Albany grease Oil gun filling
Guide wheels and
Monthly 8 2# Albany grease Brushing
pulleys of door
Guide rollers of
9 2# Albany grease Oil gun filling
counterweight
Slides of door and door
10 2# Albany grease Brushing
counterweight
11 Hinge of skylight 2# Albany grease Oil gun filling

Quarterly 12 Hinge of electrical box 20# gear oil Instilling


Taper sleeve of motor Instilling, not on
13 20# gear oil
brake friction disc
After cleaning,
Details in table
Half year 14 Reducer 1.5L replace the
8.1
lubricating oil

8-6
Operation Instruction of SC Series Construction Hoist Inspections/Lubrication

Lubrication schematic diagram

Figure 8.6

8-7
Operation Instruction of SC Series Construction Hoist Maintenance

9 Maintenance
Construction hoist maintenance is divided into maintenance for electrical and
mechanical systems.
Maintenance personnel for construction hoist must have relevant qualification
certificate.

9.1 Check failure of electrical system


When carrying out maintenance for cage, you should cut off the power
supply;
For frequency construction hoist, start the repair for it only after 10
minutes since the main power off.
Construction hoist maintenance personnel should use a multimeter to check the
electrical system. Specific inspection procedures are as follows:
a) Before the diagnosis of electrical system failure, maintenance personnel must
understand all of the principles of electrical schematics and the structures and
functions of components should have on the electrical schematics. At the same time
confirm the following procedures:
□ Confirm stop control circuit is not disconnected; Namely the thermal relay has
not been activated;
□ Contacts of safety devices, such as micro-switch of anti-fall safety device,
hanging cage door switches, outer fence door switch and others, should be closed;
□ Confirm the emergency stop button is not pressed;
□ Make sure the power limit switch is not off;
□ Confirm the up and down limit switches are intact and correct in action.
b) At the stop on the ground, confirm the three-phase power supply of power box
on the ground is powered.
c) Confirm that when the main switch (automatic air switch) of power box on the
ground is turned on, the main contactor inside the box is switched on and the output
cable is energized.
d) Identify the breakdowns of electrical system in cage after the power is turned
on.
e) Connect the voltmeter between the zero terminals and the terminal indicated in
electrical schematics, check to make sure all parts required to be powered is energized.
Check the terminals one by one to find out the fault using exclusion method.
f) Check the manipulation buttons and controls to confirm the commands of “up”
and “down” (voltage) should be properly sent to the electrical control box.

9-1
Operation Instruction of SC Series Construction Hoist Maintenance

g) Test run the cage to ensure that the main contactor solenoid of up and down
running is energized (started) and that the brake contactor is activated (brake coil is
energized) and brake is in operation.
h) In terms of lighting and other auxiliary circuits, clear the troubles according to
the above procedures.

9.1.1Troubleshooting methods for electrical system:

Table 9.1 Common breakdowns of electrical system


Breakdown Cause Solution
a switch of main Inner damage of circuit, short Find out the short circuit or
power supply trips circuit or ground short circuit of grounding position. Repair or
after it is closed phase line replace.
Damage of cable or limit switch, or Replace the damaged cable and
b Safety breaker trips
ground short circuit limit switch
Release the “Emergency Button”;
c Construction hoist The shutdown circuit and the limit
Recover the function of
suddenly stops or switch is activated, the safety
thermorelay;
cannot start breaker starts.
Recover other safety devices
Close the door or release
“Emergency Button”; check 52
d The cage cannot run Open circuit of interlock interlock control circuit, namely:
after starting (referring to electrical schematics) each circuit of limiting devices of
terminals stall should be in good
situation.
e power supply Individual limit switch is not reset; Reset limit switch;
normal,main the sequence is wrong; Reconnect the phase;
contactor not in Component damaged or circuit Replace the element or repair the
engagement open or broken. circuit
Recover the function of brake
Motor brake is not opened or no
(adjust the working gap) or recover
f Difficult to start DC voltage (rectifier element
the direct current voltage(replace
motor, with abnormal damaged);
rectifying elements)
sound Serious overloading;
Reduce the cage load;
Supply voltage well below 380V
Recover the power voltage to 380V
g In running, upper /
The switches of up and down limits Replace the up and down limit
down limit switches
are damaged; switches;
have failure, the
The cam positions of up and down Recover the cam positions of up
power limit switch
limit switches are changed and down limit switches
effective.
The line is in bad contact or Recover the contact performance of
h operation is not
terminal connection is loose; circuit, tighten the terminal wiring;
normal now and then
contact adhesive or reset blocked. repair or replace contactor
i After shutdown, Control devices (buttons, handles) Repair or replace control
are in bad contact or loose; device( buttons and handle)
cage can be
Phase sequence relay loose; Tighten phase relay
restarted, but then Door limit switch and the shutter in Recover the baffle position of door
stops again. dislocation. limit switch
Up and down limit switches are in Repair or replace the up and down
j The cage stops bad contact or damaged; limit switches;
automatically during
Serious overloading; Reduce the cage load;
up and down running
Control device (buttons and handle) Repair or replace control

9-2
Operation Instruction of SC Series Construction Hoist Maintenance

is in bad contact or damaged device( buttons and handle)


Voltage decrease of power supply Shorten the distance from power
k Contact is easy to e
is and the starting current is too supply to construction hoist or
burned
much. increase the power cable section
Brakes are not working
Adjust or replace brake;
synchronously;
Reduce the cage load and carry out
l Motor overheating Overload running for a long time;
Starting and braking too frequently; proper adjustment;adjust power
Supply voltage is too low. voltage

m No high speed in Check whether the deceleration Adjust or replace deceleration limit
limit switch is reset switch
running(frequency
Check the wire connection of Confirm the wire connection of
construction hoist机)
master handle main commanding handle

9.2Breakdowns and solutions of mechanical system:


Table 9.2 Breakdowns and solutions Table of mechanical system

Breakdown Cause Solution

Connection bolts for guide rollers Tighten the bolts of rollers;


are loose; Adjust the clearance or add lubricant;
Clearance of gear and rack is too Adjust the clearance.
A Cage is shaking too
much or there is lack of
much in running
lubricating oil;
Clearance of guide rollers and
back wheel is too much
Braking torque of motor is too Readjust the braking torque of motor;
B Cage throbs in much; Replace the rubber pad in coupling
starting or stopping Rubber pad in coupling is
damaged
Fixing device of motor is loose; Tighten the fixing device of motor;
The rubber pad of motor is Replace the rubber pad for motor;
c Motor throbs in
damaged or lost; Tighten the connection bolts for reducer
cage running
Connection bolts for reducer and and drive board
drive board is loose
Butt difference of rack rail frame Adjust the butt tube of rack rail frame
(mast) is too large; (mast);
d Cage throbs in
Rack bolt is loose and the butt Tighten the rack bolts and the butt
running
difference is too large: difference;
Gear is worn seriously. Replace the gear
Connection bolts of guide rollers Tighten the connection bolts of guide
e Cage shakes in are loose; rollers;
running Bolts of supporting board are Tighten the bolts of supporting board
loose.

9-3
Operation Instruction of SC Series Construction Hoist Maintenance

Braking torque of motor is too Readjust the motor braking torque;


F Cage shakes
much; Readjust clearance
seriously in starting
Clearance between gear and rack
or stopping
is inappropriate
Lubrication of stop bearing of Lubricate or replace bearing
reducer is bad and cannot working Reduce the distance from power supply
in synchronization; to hoist or increase the power cable
G Brake pad is worn
The voltage of power supply section to enhance the working
too fast
decrease too much and braking (braking)voltage
voltage is not enough so that the
brake cannot be opened.
Stop bearing of brake is damaged;Replace the stop bearing;
h Noise of brake is
The rotating disk of brake is Adjust or replace the rotating board of
too loud
moving brake

The type of lubricant is not Replace the lubricant;


I Worm gear of
proper or replaced in time; Adjust the worm gear and center
reducer is worn too
The worm gear or the distance of distance of worm rod
fast
worm rod have skewing
J Cage is sliding Adjust the adjustable sleeve at the tail of
The braking torque of motor is too motor
down ward too much
small Replace brake pad (brake disk)
in braking

9.3 Common faults and solutions of transducer


When the inverter fails, systematically the contactor KM2 at the output end will
be disconnected. At this time the hoist cannot move and it will display the fault code
on the drive.
When such a failure occurs, refer to the following table to find out the
corresponding fault type and problem-solving approach.
When you start the hoist again, firstly cut off the main circuit power supply.
After three minutes turn on the power, thus you can reset the drive.

9.4 Replacement of wearing parts

Cut off the main power supply during repair and maintenance of the
cage!
In the inspection, the cage must be parked at the buffer spring at bottom!
For hoist with counterweight device, the cage must be locked on the rack rails!

9.4.1 Motor replacement

a) Remove the hole cover at the top of the cage. (Put the hook of lifting device

9-4
Operation Instruction of SC Series Construction Hoist Maintenance

into the top hole)


b) Remove the electrical wiring of motor and mark it for connection after motor
replacement.
c) Set the lifting equipment or appliances (crane, hoist and other gods) of lifting
weight> 200kg lifting over the motor to be replaced.
d) Remove the reducer on the drive board and the connecting bolts of motor
bearing seat. Remove the reducer unit and the motor assembly.
e) Remove the connecting bolts of the motor and around flange of motor, and then
remove the motor.
f) Loosen the stop screw and use jaw die to remove the half-coupling from the
motor shaft.
g) Lubricate the spindle of new motor with lithium grease and mount the half
coupling using the installation tool into the new motor shaft and insert stop
screw.
When installing the coupling, you cannot use the hammer to knock it,
but using rubber.
h) Place the wedge below the handle of brake-releasing of motor (or use the
method in Figure 6.9) to release the motor brake.
i) Match the right and left half-couplings and the clearance should meet the
requirements. Bolt the motor and reducer. After installation, the concentricity error of
motor shaft and worm shaft ≤0.05mm.
j) Lift up the motor with a reducer and fix it with bolts and motor seat onto the
drive backplane. The tightening torque for backplane connecting bolts and reducer is
l70N · m.
k) Removal of lifting equipment or appliance.
1) Connect the cable and mount the motor case, and remove the wedge below the
brake-releasing handle (or reset the nut).
m) Check and adjust the brake torque according to Chapter 8, “Inspections and
Lubrication”.
n) Mount the removed cage hole cover.
o) Turn on the total power supply, and test run to ensure that the brake is working
properly.

9-5
Operation Instruction of SC Series Construction Hoist Maintenance

All newly replaced motor types and specifications should be same with
the originals.

9.4.2 Electromagnetic brake maintenance

The main component of an electromagnetic disc brake is a DC electromagnet,


mounted with a movable brake disc with brake pads which can freely move axially.
Two fixed brake disc (in which are the solenoid / armature automatically tracking the
brake pads).
The distance between the electromagnet and the armature is for maintaining a
constant (Referring to Fig. 9.1).
□ When the solenoid coil (3) is not energized, the brake is applied to the brake
torque so that the brake spring (7) via the axially-free armature (5) press the
brake pad (10) against the fixed brake disc (17). When the solenoid coil is
energized the brake will be released.
□ With the wear of brake pad (10), the brake can be sustainable for automatic

9-6
Operation Instruction of SC Series Construction Hoist Maintenance

adjustment, i.e., automatically close to the rotatable brake disk (8) by the
armature (5) and the electromagnet frame. The distance between the
electromagnet and the armature is constant.
□ You must replace the brake disc and the brake pad when they are worn to a
certain extent. (Referring to Figure 9.1)
9.4.2.1 Manual brake-releasing of brake
When necessary, the brake can be manually brakes. The brake-releasing
program:
a) Pull the brake-releasing handle at the end of brake to a certain extent, the brake
can be loosed.
b) Tighten the bolts at tail of brake in the method in Figure 6.9 until the brake
spring (7) fails to press the armature (5). Then the brake is loosed.
We have been adjusted the braking torque of brake for delivery.
Therefore, do not easily change it when manually releasing brake.

9.4.2.2 Replacing brake pad


The brake pad (10) must be replaced when the gap is less than 0.5mm between
the rotatable brake disk (8) and the armature (5). Replace the pad as follows:
a) Removing the protective cover (1);
b) Measure and mark the position of adjustment sleeve (6) in order to reposition it
after having replaced the pad;
c) Remove the adjustment sleeve (6) and take out the brake spring (7);
d) Loosen the nut (12) and screw it to the end of the bolt (11);
e) Pill out the end frame (2) close to the nut (12);
f) Pull out the magnet frame (4) near the end cap;
g) Using a special tool to remove the old brake pad (10) and mount anew brake
pad;
h) Push away the magnet holder (4) along the bolt (11) to attach the armature (5)
to the new brake pad;
i) Push back the end cap (2) and tighten the nut (12);
j) Reload the spring (7), and position the adjustment sleeve (6) to its original
position as required in b);
k) Try the brake several times and confirm it works properly. Then put it into use;
l) Install the protective cover (1);

9-7
Operation Instruction of SC Series Construction Hoist Maintenance

Replace the brake pads as a group of ten. For the brake pad of same
group, its thickness error is less than 0.0lmm and its surface cannot be
stained with oil.
9.4.2.3 Checking brake procedures of brake without operation (released):
a) The rectifier should be normal;
b) The brake contactor should work properly;
c) Measure the solenoid coil voltage (rated DC 195V);
If there is any problem found in the above three inspections, replace the
corresponding electrical components.

9.4.3 Replacement of anti-fall safety device

a) Open the cover under safety device and remove the wire to micro switch.
b) Loosen the fixing bolts of safety board and remove the anti-fall safety device.
c) Install the new anti-fall safety device, and tighten the bolts for safety device
board after attaching the flange to the safety board.
d) Connect the wire to micro-switch and carry out the drop test.
e) Reset the anti-fall safety device and lubricate according to Chapter 8,
“Inspections and Lubrication”.
When installing the coupling, you cannot use the hammer to knock it,
but using rubber. After the replacement, carry out the drop test.

9.4.4 Replacing the guide rollers

When the guide rollers wear limit reaches to the specified wear limit in clause 8.5
and after having adjusted the eccentric shaft to the limit, it still cannot meet the
clearance requirements in paragraph 6.6.1, thus the guide roller should be replaced.

9.4.5 Replacing the side guide rollers

a) Lock (or set aside) the cage, and relax the side guide roller to be replaced.
b) With a special wrench remove the side guide rollers.
c) Install the new side guide rollers and rotate the eccentric shaft of side guide
rollers.
d) Tighten the mounting bolts, with tightening torque of 200N · m.

9.4.6 Replacement of upper double guide rollers

a) Plug a wedge iron between the column pipe of rail frame and the safety hook

9-8
Operation Instruction of SC Series Construction Hoist Maintenance

and fix the cage to the rack rail.


During removing of the guide rollers, the wedge iron should be with sufficient
support so that the cage cannot decline.
b) Loosen the bolts guide rollers and turn the eccentric shaft to keep proper
clearance between the guide rod and the column tube of rail frame.
c) Remove the old guide rollers.
d) Install the new guide rollers and adjust the eccentric shaft of guide roller until
the wedge iron looses and falling. Then tighten the bolt with tightening torque
of 170 N · m.

9.4.7 Replacement of lower double guide rollers

a) Plug a wedge iron between the column pipe of rail frame and the lower safety
hook and fix the cage to the rack rail;
b) Loosen the nuts for center shaft of lower double guide rollers and then remove
the whole lower double guide rollers;
c) Loosen the positioning bolts or nuts of guide roller device and remove the old
rollers from the double guide roller device;
d) Install the new guide rollers and don’t tighten the positioning bolts or nuts
temporarily;
e) Mount the lower double guide rollers with new guide rollers to its original
position and the tightening torque of center shaft is 600N·m;
f) Adjust the eccentric shaft of guide roller until the wedge iron looses and falling.
Then tighten the bolt with tightening torque of 170 N · m.

9.4.8 Replacement of transmission gear

Before installation, you should check the wear of gear to easily replace it;
Suggestion: Even if the amount of wear of the gear has not reached the allowed
maximum value, the gear was identified only to work for short-term; it should also be
replaced;
For construction hoist in use, in the replacement of gear, you must park the
cage on chassis with sleeper height of which must be greater than the height of the
buffer spring. The sleeper should also be level and firm so as to unload the gear. Then,
replace it as the following procedure:
a) Remove the shaft elastic retaining ring outside of drive gear and the old gear
with special removal tool (Referring to Figure 9.2);

9-9
Operation Instruction of SC Series Construction Hoist Maintenance

b) Clean and lubricate the shaft spline and then install the new gear.
c) Mount the shaft elastic retaining ring;
d) Check the engagement of gear and rack and adjust it as required in section 8.4;
e) Remove the sleepers under the cage;

9.4.9 Replacing masts

When the max decrease of wall thickness of mast main chord is 25% of the rated

thickness of production, the mast must be scrapped or being used less.

9.4.10 Replacement of rack

According to the provisions of section 8.7.2, if the rack has reached its wear limit
or been damaged, replace it as the following procedures:
a) Remove the old rack, (if it is difficult to remove it, use gas welding to heat the
rack to loosen its bolts).
b) Clean screw holes on the pad of rack.
c) Install the new rack and its bolt tightening torque is 170N · m.

9.4.11 Replacing the back wheel

a) Tighten respectively the drive gear and anti-fall safety device with rack by
special clamp to unload the back wheel.
b) Remove the old back wheel.

9-10
Operation Instruction of SC Series Construction Hoist Maintenance

c) Install the new back wheel and adjust the eccentric sleeve to keep the gap
between the back wheel and the rack at O.5mm. Then tighten the mounting bolts,
with tightening torque of 300N · m.
d) Remove the special clamps.

9.4.12 Replacing worm reducer

a) Separate the motor from the worm reducer according to Section 9.3.1
“Replacing the motor”.
b) Use a special drawing die to remove half of the coupling from reducer.
c) Clean up the lubricant inside the reducer.
d) Mount the drive gear on the new reducer as the procedures in section 9.3.8
“Replacing the reducer”.
e) Lubricate the input shaft of new reducer with grease and mount the half
coupling having removed before.
f) The wedge is placed under the handle of brake release of motor to release
brake.
g) To match the two coupling halves at one side of reducer and one side of motor
and their clearance should be as required. Then bolt the motor and reducer, at the
same time the concentricity error of motor shaft and the worm shaft should be
≤0.05mm.
h) According to procedures in section 9.3.1 “Replacing the motor” install the
reducer unit and the motor assembly.

9-11
Operation Instruction of SC Series Construction Hoist Removal

10 Removal of Hoist
10.1Principles for removal

Before uninstalling, you must be familiar with the entire contents of the chapter
2.2 “Safety Requirements of Installation and removal” and comprehensively
understand the mechanical and electrical properties of each part of construction hoist;
During uninstalling, please comply with the followings:
a) Comply with Ten Disciplines for Safety Producing after access to the site;
b) Safety warning area at construction site should be set up with someone to
guard;
c) Uninstalling personnel are not allowed to wear hard-soled shoes or high heels
and should wear tight clothing and safety belts;
d) Personnel for aerial operations like removal of guide frame (mast), must find a
secure and proper position, fasten the safety belt and hang up the insurance hook;
e) In uninstallation process of construction hoist, the bolts, axle pins, cotter pins
and other fasteners should not have defects and scrapped ropes, cranes and other
equipment shall not be used;
f) In decreasing the masts of construction hoist, it is prohibited for vertical
transport operation.
g) In decreasing the masts of construction hoist, we must always pay attention to
that the cage guide wheels should be very close to the masts under it.

10.2Preparations before removal

a) Before demolition, check and confirm the operations of mechanisms are


normal.
b) Before demolition, check the base site of construction hoist and tie-in devices
in order to confirm to be normal.
c) Clean up the removal field to keep it flat and firm, without any obstacle.
d) Check whether there are high-voltage wires or cables or not in aerial area, if
there is, whether being confirmed by relevant department.
e) The construction side for removal of construction hoist should prepare program
files of (Construction Task Explanations Bill of Construction hoist) and
(Removal Construction Program of Construction Hoist), and make the relevant
confirmation procedures.

10-1
Operation Instruction of SC Series Construction Hoist Removal

f) The construction side shall prepare a detailed construction plan for removal of
construction (Removal Task Bill of Construction hoist).

10.3Carrying out the removal procedures

a) Workers should be carefully read, understand and master the content of the
Instruction and the removing program detail to make sure the removing process is
strictly as required.
b) Make sure all personnel in construction site bear the relevant safety rules.
c) Remove relevant tie-in devices when the hoist is lowered to certain height
according to operational requirements of construction hoist.
d) Conduct the removal procedures of hoist as required step by step.
e) During removing, check all connections and tightening of each part. If there is
any problem, correct it instantly to ensure the hoist in removal can work properly and
reliably.
f) After removal of hoist, clean up the field and transport it for next use or put it in
storage.

10.4 Removing procedures

Contents of construction hoist removal are basically similar to installation


procedures, only in the opposite order. (Detailed demolition procedures can be
found in flashback program in Section 6 “Installation”), the followings are
only the disassembly focuses:
a) Operate the operational box of cage on the cage top (operation button assembly
of top cage of frequency construction hoist is installed on the electrical control
box on cage top of the);
b) Mounted the installing boom on cage top;
c) Drive the cage to the top of the rail frame and remove the up limit switch cam
and deceleration limit cam (frequency construction hoist) and power supply
limit switch cam;
d) Remove the buffer spring of counterweight and place sleepers of sufficient
height under the counterweight;
e) Drive cage slowly rise up to an appropriate distance to stop counterweight
firmly on sleepers to unload steel rope;
f) Remove the steel rope from the counterweight and eccentric rope device and
collect all steel wire ropes using the steel disk on cage top;

10-2
Operation Instruction of SC Series Construction Hoist Removal

g) Remove the wheel frame;


h) Remove the guide frame (mast), tie-in frame and the cable guide device;
i) Remain the bottom rail frame of three masts and remove the installation boom.
Dismantle the buffer spring and switches of up and down limit, deceleration
limit and extreme limit baffle at bottom.
j) Place two proper sleepers on fence chassis;
k) Pull the brake-releasing handle of motor to slide the cage slowly onto sleepers;
l) Cut off the main power box on the ground and remove the cable connected to
the cage;
m) Suspend the drive system apart from the rail frame;
n) Suspend the cage apart from the rail frame;
o) Suspend the counterweight apart from the rail frame;
p) Remove the fence and the remained three masts;
q) when removing the rail frame, ensure the highest guide roller of cage is always
in a position under the rail frame (mast) joints to be demolished, and after the
spreader and boom are in place remove the connecting bolts;
Construction lifts in wind speed over 12.5m / s or bad weathers like
thunderstorm or snow, you should not conduct disassembly operations.
For demolition job at cage top you must press the emergency stop
button!
In the demolition process, you must ensure the maximum suspending
height of rack rail frame is in accordance with Table 5.1

10-3
Operation Instruction of SC Series Construction Hoist AppendixⅠ

Appendix I
Table l0.3 Major wearing parts list of construction hoist
No. Name Code Type&specification Qty Remark

1 Drive gear 6
2 Back wheel 4
3 Roller unit 24
4 Long roller unit 8
5 New roller unit 8
Medium-speed
6 Phantom gear 4
frequency hoist
Medium-speed
7 Niddle bearing GB/T307-2005 NK5035 4
frequency hoist
8 Roller unit 8 For pulley
9 Oil seal HG4-692-67 PD 40×52×7 6
Buffer
10 ML8 6 For coupling
octagonal glue
Upward and
downward contacts,
LC1D80E7C 1
main contact, and
11
Contact frequency contact
Contact at cage
LC1D80M7C 1
bottom
12 LC1D25E7C 1 Brake contact
Up and down limits,
13 Limit TL422-01Y-U180-2512-6 1 up and down limits of
deceleration
FM-103G copper-base powder
14 Brake block 8ZJ.274.030 60
metallurgy
15 Disc brake 5ZJ.275.038 Copper-base wire asbestos 6 For motor
16 GB/T276.1994 6308-Z(40×90×23)
6
17 GB/T276-1994 6307-Z(35×80×21)
18 Bearing GB297-84 7510
19 GB297-84 7313 4 For reducer
20 G8283-81 42309
21 GB298-64 27309E 8 For reducer
22 Bearing GBl235-76 220×5.7
23 GBl235-76 140×3.1 4 For reducer
24 GBl235-76 115×3.1
0-type seal
25 GBl235-76 100×3.1 8 For reducer
Note: the quantity in the table is for double-cage hoist with two drive systems

1
Operation Instruction of SC Series Construction Hoist Appendix Ⅲ

Appendix II
Table l0.4 Major purchased parts list of construction hoist

Qty Type Specification


No. Name Single-c Doubl
age e-cage

1 Motor 2 4 YZZ 132L2-4 P=18.5kW

2 Reducer 2 4 SJ100-2 i=21.05


Rated braking load:30kN
SAJ30—1.2 Rated braking
Anti-off
speed:1.2m/s
3 safety 1 2
Rated braking load:40kN
device
SAJ40—1.2 Rated braking
speed:1.2m/s
3×16+2×6
4 Power cable YC cable
3×25+2×10
5 Guide roller 20 40 Bottom diameter: Φ74mm
6 Drive gear 3 6 m=8;z=15
Phantom
7 2 4 m=8;z=15
gear
Rack(each
8 1 2 m=8;z=60
mast)
Overload
9 1 2 HBSC-3
protector

2
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Appendix Ⅲ

Technical Files of Construction Hoist


Installation and Removal
Construction unit
Construction site
Installing unit
Hoist type
Equipment supervisor
Designer
Collator
Date

Department

3
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Installation Task Bill of Construction hoist


Hoist inspection mark (01)
Program Construction site

Construction Construction
unit supervisor
Hoist type Code Erection (m)
height
Erection Date M D to M D Erection
supervisor
Personnel management(Filled in by labor depolyer)

General commander Safety supervisor Driver Electrician

Lifting worker

Machine worker

Repair and maintenance conclusion:(Filled in by device keeper)

Cage l No deformation2 No bending3 No flaw 1 2 3 Taking cover of base is qualified

Mast 1 No deformation2 No bending3 No flaw 1 2 3 Running of mechanisms is qualified

Tie-in 1 No deformation2 No bending 3 No flaw 1 2 3 others as required

Note:being qualified is √ ;being unqualified is ×

Site situation and plane and elevation figures (specific drawings as optional)

Installation equipment for hoist ton truck crane or tower crane type

nearby ;

Y M D Receiver Device supervisor Fill-in people

4
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Removal Task Bill of Construction hoist


Hoist inspection mark (02)
Program Construction
site
Construction unit Construction
supervisor
Hoist type Code Erection height (m)

Erection Date M D to M D Erection


supervisor
Personnel management(Filled in by labor depolyer)

General commander Safety supervisor Driver Electrician

Lifting worker

Machine worker

Device current situation: (Filled in by device keeper)

Cage l No deformation2 No bending3 No flaw 1 2 3 verticality of hoist is at the allowed

range

Mast 1 No deformation2 No bending3 No flaw 1 2 3 tie-in frame is stable and mechanisms

work well

Tie-in 1 No deformation2 No bending 3 No flaw 1 2 3 others as required

Note:being qualified is √ ;being unqualified is ×

Site situation and plane and elevation figures (specific drawings as optional)

Removal equipment for hoist ton truck crane or tower crane type nearby ;

Decrease the height of hoist to m for removal.

Y M D Receiver Device supervisor Fill-in people

5
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Construction Task Explanations Bill of


Construction hoist
Hoist inspection mark (03)
Program Construction site

Construction Construction
unit supervisor
Hoist type Code Erection height (m)

Erection Date M D to M D Erection


supervisor
Precautions for installation: .
1. Comply with Ten Disciplines for Safety Producing after access to the site;
2. Safety warning area at construction site should be set up with someone to guard; ’
3. Don’t install or uninstall the construction hoists in bad weather, like wind speed over l2.5m /
s, thunderstorm days, or snowy weather.
4. Installing and operating personnel are not allowed to wear hard-soled shoes or high heels
and should wear tight clothing and safety belts;
5. Personnel for aerial operations like installation and removal of guide frame (mast), must
find a secure and proper position, fasten the safety belt and hang up the insurance hook;
6. In installation process of construction hoist, the bolts, axle pins, cotter pins and other
fasteners should not have defects and scrapped ropes, cranes and other equipment shall not be
used;
7. In increasing or decreasing the masts of construction hoist, it is prohibited for vertical
transport operation.
8. In increasing or decreasing the masts of construction hoist, we must always pay attention to
that the cage guide wheels should be very close to the masts under it.
9. After having increased masts for hoist, tighten all fastening parts and correct the verticality
of mast as required.
10. After having increased masts for hoist, check all tightening parts and safety devices which
should be intact and good.
11. Supplement:

Y M D Receiver Device supervisor Fill-in people

6
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Installation Construction Program of


Construction Hoist
Hoist inspection mark (04)
Program Construction site

Construction Construction
unit supervisor
Hoist type Code Erection height (m)
Erection Date M D to M D Erection supervisor

Preparation stage of installation


1. Before installation, repair and maintain each mechanism and make out the quality confirmation
procedures.
2. Before installation, maintain the painting of metal structures of hoist, such as tie-in frames and rack rail
frame.
3. Clean up the installation field to keep it flat and firm, without any obstacle.
4. There is (or not) high-voltage wires or cables in aerial area, if there is, whether being confirmed
by relevant department .
5. According to procedures in hoist inspection mark (01) and (03), carry out relevant confirmation
procedures.
6.Design detailed installation and construction plan (attached)
Installation stage
1. Workers should be carefully read, understand and master the content of the Instruction and the installing
program detail to make sure the installing process is strictly as required.
2. Make sure all personnel in construction site bear the relevant safety rules.
3. The site for construction hoist installation should be clean and have warning signs to prohibit
non-operating personnel to enter, with special people guard.
4. Conduct the installation procedures of hoist as required step by step.
5. Operate hoist according to the requirements to certain working height.
6. Install relevant tie-in devices when the hoist is heightened to certain height.
7. After having installed hoist, check all connections and tightening of each part. If there is any problem,
correct it instantly to ensure the installed hoist can work properly and reliably.
8. Debug the hoist according to the acceptance test procedures and contents in hoist inspection mark (07),
with relevant confirmation procedures.
9. Supplement:
Above construction plan has been confirmed Installing&removing signature Commander
signature

Y M D Receiver Device supervisor Fill-in people

7
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Removal Construction Program of


Construction Hoist
Hoist inspection mark (05)
Program Construction site

Construction Construction
unit supervisor
Hoist type Code Erection height
(m)
Erection Date M D to M D Removal supervisor

Preparation stage of removal


1. Before removal, repair and maintain each mechanism and make out the quality confirmation
procedures.
2. Before removal, maintain the painting of metal structures of hoist, such as tie-in frames and
rack rail frame.
3. Clean up the removal field to keep it flat and firm, without any obstacle.
4. There is (or not) high-voltage wires or cables in aerial area, if there is, whether being
confirmed by relevant department .
5. According to procedures in hoist inspection mark (02) and (03), carry out relevant
confirmation procedures.
6.Design detailed removal and construction plan (attached)

Installation stage
1. Workers should be carefully read, understand and master the content of the Instruction and the
removing program detail to make sure the removing process is strictly as required.
2. Make sure all personnel in construction site bear the relevant safety rules.
3. The site for construction hoist removal should be clean and have warning signs to prohibit
non-operating personnel to enter, with special people guard.
4. Remove relevant tie-in devices when the hoist is lowered to certain height.
5. Conduct the removal procedures of hoist as required step by step.
6. During removing, check all connections and tightening of each part. If there is any problem,
correct it instantly to ensure the hoist in removal can work properly and reliably.
7. After removal of hoist, clean up the field and transport it for next use or put it in storage.
8. Supplement:

Above construction plan has been confirmed Installing&removing signature

Commander signature

Y M D Receiver Device supervisor Fill-in people

8
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Process Record of Installation&Removal of


Construction Hoist
Hoist inspection mark (06)
Program Construction site

Construction Construction
unit supervisor
Hoist type Code Erection height (m)

Erection Date M D to M D Erection


supervisor
Personnel / work type Content

Date Date

Y M D Receiver Device supervisor Fill-in people

9
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Acceptance Bill of Embedding Program and Tie-in


Device Installation of Construction Hoist
Hoist inspection mark (07)
Program Construction
site
Construction Construction
unit supervisor
Hoist type Code Erection height (m)
Erection Date M D to M D Erection
supervisor

Acceptance inspection for embedding devices of hoist:


1. Check whether the endurance of ground layer under hoist base is as required or not.
2. Check whether the concrete base size is as required or not.
3. Check that the arrangement of steel bars in concrete foundation of hoist is as
required or not.
4. Check whether the pre-embedded bolts or anchor bolts in concrete base of hoist is as
required or not.
The above inspections have relevant confirmation procedures.
Installation signature Commander signature

Acceptance inspection for tie-in devices of hoist:


1. Check whether the pre-embedded parts of tie-in devices in wall are as required or
not.
2. Check whether the size of tie-in device is as required or not.
3. Check whether the horizontality of tie-in device is as required or not.
4. Check whether the verticality of hoist, after its tie-in devices have been adjusted, is
as required or not.
The above inspections have relevant confirmation procedures.
Installation signature Commander signature

Appendix: The Acceptance Test Report of Embedding Devices of Base

Y M D Receiver Device supervisor Fill-in people

10
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Installation Quality Acceptance Card of


Construction Hoist
Hoist inspection mark (07)
Program Construction site

Construction unit Construction


supervisor
Hoist type Code Erection height
(m)

Erection Date M D to M D Erection


supervisor
Item Contents and requirements Inspection Re-inspection

Concrete foundation platform without tilting or crack

Base and Around the concrete foundation platform are drainage facilities
fence Fence facilities without distortion, cracks, or corrosion with
devices cage
At the bottom of cage and buffer spring with correctly
positioned counterweight
No deformation, cracks, severe corrosion and other damage as
well
Cage part Enter gate start flexibly and limits are effective. Counterweight
is running well. No grazing phenomenon. Cable without
damage, running well.
Worm gear box is lubricated well, operating normally, no
abnormal noise or oil leakage or overheating (oil temperature
does not exceed 100 ℃)
Brake operation is flexible and reliable; the gap between the
fixed brake disc and the rotation disk space is not less than Actual gap: Actual gap:
0.5mm.
The maximum wear limit of gear is 35.1mm (normal line); Gear wear: Gear wear:
The maximum wear limit of rack is l0.6mm. Rack wear: Rack wear:
Drive Rack is securely fastened and lubricated well. And the wear
system degree does not exceed the standard.

Guide wheel securely fastened and lubricated well; no obvious Center wheel Center wheel
tilt or deflection in guide. Be flexible. Center wheel gap is gap: gap:
0.5mm and side wheel gap is 0.5mm. Side wheel gap:Side wheel gap:

Tighten the back wheel and lubricate it well. No obvious tilt or


Actual gap: Actual gap:
deflection in guide. The gap is 0.5mm.
Anti-fall safety device is running without sound, touch its case
by hand without click feeling.

11
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Hoist inspection mark (07)


Item Contents and requirements Inspection Re-inspection
Mast and its Mast steel structure without significant Actual Actual
accessory deformation or cracking; mast node deviation is less deviation: deviation:
than 0.8mm; verticality at installation height is as Actual Actual
required in Table 6.1 rack rail verticality deviation verticality: verticality:
table;
Mounting bolts of mast are as required and the
tightening torque is correct.
Tie-in support must be the standard products; the Actual level:Actual level:
level of erection is not more than ± 8 °; Tie-in
support must be bolted to the wall.
Installing boom on cage top has been removed, and
shall not affect the up and down running of cage.
Electrical Illumination is good and the electrical bell is
system effective
Cable power supply system should be normal, the
allowed deviation of working voltage is 380V ±
5%.
Contactor and contact of breaker is good

Control operation device is flexible and reliable

Electrical components and safety devices are intact


and complete
Ground resistance not more than 4Ω Actual Actual
resistance: resistance:
Insulation resistance of electrical system against the Actual Actual
ground is not less than lMΩ resistance: resistance:
Check whether the electrical interlock of fence door
Safety and is reliable and safe
limit devices Electrical interlock of cage is reliable and safe

Up and down limit is intact and reliable

Braking distance of up and down limit is as required

Up and down deceleration limit switches are intact


and reliable
Anti-fall device is tested to be effective

Commissioni Empty load Rated load 125% rated load Additional


ng explanation:
Weight Height Weight Height Weight Height Empty load:
Rated load:

12
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Check whether the drive system work is stable, with or 125 % rated
without abnormal sound; the hydraulic system has leak (fast type) load:
or not; manipulation and control system is sensitive and reliable; Identifier:
Check whether there is a permanent deformation or crack on Date:
metal structure; the whether the brake is reliable; tune
It is less than three times detections needed after the adjustment of
safety device.

Hoist inspection mark (07)


Problems in acceptance test:
Identifier: Y M D

Improvement condition:
Improvementsignature: Y M D

Re-test suggestion:
Re-test signature: Y M D

Signature Date

Hoist commander

Installing supervisor

Identifi Safety supervisor department


er

Technical&Quality department

Device management department

Y M D Receiver Device supervisor Fill-in people

13
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Acceptance Bill of Debugging Limit Device of Construction


Hoist
Hoist inspection mark (08)
Program Construction
site
Construction Construction
unit supervisor
Hoist type Code Erection height (m)

Erection Date M D to M D Erection


supervisor

Down limit:effective or not distance mm


Bottom limit:effective or not distance mm
Up limit:effective or not distance mm
Top limit:effective or not distance mm
Limit of fence door:effective or not distance mm

Condition: Condition:
Driver signature: Date Debugging signature: Date

Condition: Condition:
Commander signature: Date Supervisor signature: Date

Y M D Receiver Device supervisor Fill-in people

14
Operation Instruction of SC Series Construction Hoist Appendix Ⅳ

Drop Test Bill of Construction Hoist


Hoist inspection mark (09)
Program Construction
site
Construction Construction
unit supervisor
Hoist type Code Erection height
(m)
Erection Date M D to M D Erection
supervisor

No. Content Test requirements

(1) Cement: kg

1 Rated load (2) Steel: kg

(3) Others : kg

Counterweig (1) With or without:


2
ht (2) Weight: kg

3 Cage Lifting height in test: m

Left cage Right cage Others

(1) 0.25m

(2) 0.35m

(3) 0.45m

(4) 0.55m

(5) 0.65m
4 Drop data
(6) 0.75m

(7) 0.85m

(8) 0.95m

(9) 1.05m
(10) 1.20m
5 Weather Wind speed in test: temperature in test:

Installing personnel:

Test personnel:
6 Signature
Operation personnel:
Safety officer (Construction hoist rental company):

Y M D Receiver Device supervisor Fill-in people

15
生产单位:徐工集团徐州建机工程机械有限公司
Manufacturer:XCMG Xuzhou Construction Machinery Co.,Ltd
地址:中国.江苏省徐州经济技术开发区徐海路80号
Add:No.80,XuhaiRoad,Economic&Techinological DevelopmentZone,Xuzhou,Jiangsu Province.
国内销售电话(Demestic sales Tei):0516–83052720
国际销售电话(International sales Tei):+86–516–87767266
传真(Fax):0516–83052561
传真(Fax):0516–87763896
邮编(Post Code):221000
网址(Website):http://www.xcmg.com
版本编号(Version number):2022年5月版
全国统一客服热线(Service phone):400-110-9999

版权所有 侵权必究